Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc.

District Court, E.D. Oklahoma·Decided July 23, 2025·No. 6:22-cv-00091·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF OKLAHOMA MORSE ELECTRIC, INC., Plaintiff, v. Case No. 22-CV-91-JWB-GLJ

STEARNS, CONRAD AND SCHMIDT, CONSULTING ENGINEERS, INC., Defendant. MEMORANDUM DECISION Morse Electric, Inc. (“MEI” or “Plaintiff”) filed a complaint against Stearns, Conrad and

Schmidt, Consulting Engineers, Inc. (“SCS” or “Defendant”) asserting claims of breach of contract, tortious interference with prospective economic gain, and violations of the Minnesota Prompt Payment Act. (Doc. 2.) Defendant counterclaimed for breach of contract. These claims all arose from the course of performance of a contract between the parties which required Plaintiff to perform electrical construction services for the Pine Bend Renewable Natural Gas Production Facility (the “Project”) in Inver Grove Heights, Minnesota. This court has subject matter jurisdiction over this matter pursuant to 28 U.S.C. § 1332(a)(1). The court presided over a bench trial April 22–25, 2025, and took the matter under advisement. The court has thoroughly considered the evidence and arguments presented at trial, the parties’ post-trial submissions, and the relevant law, and makes the following findings of fact and conclusions of law as required by

Rule 52(a) of the Federal Rules of Civil Procedure. For the reasons discussed herein, the court enters judgment for Defendant and against Plaintiff on all of Plaintiff’s claims. The court also enters judgment for Defendant and against Plaintiff on Defendant’s counterclaim of breach of contract. I. Findings of Fact The following sets forth the facts material to the issues determined by the court. Where appropriate, additional facts found by the court will be discussed throughout the following section on the conclusions of law. Plaintiff is an Oklahoma corporation that specializes in providing electrical services in the

oil and natural gas industry. Defendant is an engineering firm specializing in environmental consulting and contracting. Defendant hired PDDM Solutions, LLC (“PDDM”) to provide construction management services after it entered into the prime contract with Pine Bend (the “Owner”) for the Project. The prime contract was executed on September 9, 2020, and it set March 1, 2022, as the substantial completion date for the Project. On June 9, 2021, the parties executed a service purchase order (the “subcontract”). (Ex. 801 at 3.) The subcontract was executed by Brian Morse, co-owner of MEI, and Darren Nightingale, SCS’s project manager. The subcontract was for a fixed price lump sum amount of $1,771,100. The subcontract included as attachments the prime contract, the drawings and specifications for the electrical work, and MEI’s proposal.1 The subcontract, however, stated that

MEI’s bid proposal was for informational purposes only. (Id. at 6.) Under the subcontract, MEI agreed to perform the electrical contractor work under the prime contract as demonstrated in the drawings and specifications attached to the subcontract. The drawing and specifications were included in Attachment D as the Issued for Construction (“IFC”) electrical construction drawings and specifications. (Id. at 1, 64–121.) The IFC drawings were dated April 12, 2021, and the baseline drawings were referred to as “Rev 0.”

1 The court’s conclusions of law as to the terms of the subcontract are discussed infra. The subcontract contains a provision that SCS may unilaterally order changes in the work. (Id. at 4.) Throughout the performance of the subcontract, there were revisions to the IFC drawings. Under the terms of the subcontract, however, a written change order by SCS was required in order for an adjustment to the contract price. MEI was to submit invoices for work performed to SCS for its review and approval. SCS

was to pay MEI 45 days after the receipt of the approved invoice; however, SCS was not obligated to make payment until 15 days after SCS received payment from the Owner. (Id.) SCS also withheld retainage of 5% from the payments made to MEI. Under Article 6 of the subcontract, retainage could be withheld and was due to MEI after total completion of the work by MEI and final inspection and acceptance by SCS and the Owner. (Id.) The subcontract also allowed SCS to withhold payment for various reasons, including reasonable evidence that the work could not be completed for the unpaid balance of the contract price or that the work cannot be completed within the work schedule. (Id. at 5.) Attachment A included additional terms for the subcontract, including a provision which stated that SCS could have a third party complete the work under the

agreement should MEI fail to comply with the subcontract. (Id. at 20.) The subcontract also provided that the project was “sales tax exempt” and that MEI was liable for all taxes incurred in performing the work. (Ex. 801 at 4, 12.) SCS provided MEI with a sales tax exemption form on June 11, 2021, along with instructions on the form. (Ex. 1039.) The sales tax exemption forms were provided to all the subcontractors on the project. Ultimately, MEI paid sales taxes on the materials purchased for the project even though it was issued the exemption; none of the other subcontractors made claims to SCS for reimbursement of sales tax. (Doc. 199, Tr. 24:4–15.) Turning to the performance, MEI mobilized to the Project shortly after the execution of the subcontract. Jon French was Plaintiff’s project manager but was not at the job site daily. As the project manager, French’s job duties involved developing the schedules sent to SCS, tracking MEI’s work performed, developing the scope of work and pricing for any change orders, and timely submitting change orders. (Doc. 200, Tr. at 256–57.) Nightingale was SCS’s project

manager for the Project. Nightingale was also not on site every day and only visited the site a handful of times during the Project. By June 15, 2021, electrical materials were arriving at the site. By June 17, MEI started laying out duct banks and prefabricating conduits. MEI employees Christy Dunstan and Brian Wilson directed and oversaw MEI’s work at the Project. The work was tracked using MEI’s daily progress reports (“DPR”) which were created in Excel. (Doc. 200, Tr. 94:24–96:11.) The DPRs included a daily description of work performed, any job site delays, and sections for daily progress on the work. (See, e.g. Ex. 1215-c.) Morse testified that there should be a DPR for every day that MEI was working on the project. The DPRs indicated the personnel on site working on the project.

(Doc. 201, Tr. 9:22–23.) When invoices were submitted to SCS for payment, MEI included a project tracking worksheet. This worksheet identified the number of labor hours performed for various tasks under the subcontract. (See, e.g., Ex. 1216-a at 3.) The worksheet had line items for labor hours planned, actual labor hours, and the percentage complete for each task. It also identified the percentage of total job completion. For example, the invoice dated July 2, 2021, states that the field install was 6% complete. (Id.) As evidenced at trial, those percentages grew with each invoice submitted. Based on the project tracking worksheet, the amounts billed reflected the amount of time spent working towards the tasks that were being completed. Nightingale testified that he understood that MEI invoiced based on the percentage of work completed. (Doc. 199, Tr. at 35–36.) Morse also testified that the progress payments are based on the progression of the labor and materials being installed. (Doc. 200, Tr. at 255:22–256:2.) MEI was also required to submit its schedule in Microsoft Project format to PDDM. (Doc. 199, Tr.

Free access — add to your briefcase to read the full text and ask questions with AI

Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc., (E.D. Okla. 2025).

Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc. (Morse Electric, Inc. v. Stearns Conrad and Schmidt Consulting Engineers, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Christenson v. Milde
402 N.W.2d 610 (Court of Appeals of Minnesota, 1987)
Blaine Economic Development Authority v. Royal Electric Co.
520 N.W.2d 473 (Court of Appeals of Minnesota, 1994)
In Re Hennepin County 1986 Recycling Bond Litigation
540 N.W.2d 494 (Supreme Court of Minnesota, 1995)
Carlson Real Estate Co. v. Soltan
549 N.W.2d 376 (Court of Appeals of Minnesota, 1996)
Zobel & Dahl Construction v. Crotty
356 N.W.2d 42 (Supreme Court of Minnesota, 1984)
Charles P. Nelson v. American Family Mutual Ins.
899 F.3d 475 (Eighth Circuit, 2018)
Homestar Prop. Solutions, LLC v. Safeguard Props., LLC
370 F. Supp. 3d 1020 (D. Maine, 2019)
Grant v. Munch
55 N.W. 902 (Supreme Court of Minnesota, 1893)
City of Winona v. Jackson
100 N.W. 368 (Supreme Court of Minnesota, 1904)