Morgenroth & Associates, Inc. v. Town of Tilton

431 A.2d 770, 121 N.H. 511, 1981 N.H. LEXIS 359
CourtSupreme Court of New Hampshire
DecidedJune 12, 1981
Docket80-313
StatusPublished
Cited by31 cases

This text of 431 A.2d 770 (Morgenroth & Associates, Inc. v. Town of Tilton) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgenroth & Associates, Inc. v. Town of Tilton, 431 A.2d 770, 121 N.H. 511, 1981 N.H. LEXIS 359 (N.H. 1981).

Opinion

Douglas, J.

The plaintiff, Morgenroth & Associates, Inc., seeks to recover from the defendants, the Towns of Tilton and Northfield and the State of New Hampshire, the cost of preparing engineering plans for the construction of sewerage systems in those towns. The Superior Court (Batchelder, J.) granted the defendants’ motions to dismiss for lack of jurisdiction under RSA 491:8 because the pleadings failed to allege an express or implied in fact contract with the State. The plaintiff appeals, arguing 1) that RSA 491:8 abrogates the State’s sovereign immunity for contracts implied in law as well as for express and implied in fact contracts; 2) that it has alleged a contract implied in fact; and 3) that the trial court erred in dismissing the action against the towns based on RSA 491:8. We hold that the trial court correctly ruled that it did not have jurisdiction to hear claims against the State based on implied in law contracts, but hold that the plaintiff has made out a claim for an implied in fact contract. We further hold that the court erred in dismissing the action against the towns based on RSA 491:8. Accordingly, we reverse and remand.

In 1968 the plaintiff entered into contracts with the defendant towns to do certain preconstruction engineering work for the construction of a separate sewerage system for each town. Those contracts were expressly conditioned upon the towns’ receipt of grant money from the U.S. Department of Housing and Urban Development. The funding for the work did not become available, and all parties agree that the plaintiff has no cause of action based on those contracts.

The facts beyond that point are in dispute. The plaintiff alleges that, after the federal funding became unavailable, it made *514 arrangements with the New Hampshire Water Supply and Pollution Control Commission (WSPCC) and the towns to proceed with the design phase of the project at the same time the towns looked elsewhere for construction grant funds. In 1970, the towns appropriated the funds needed for the preconstruction engineering work at town meetings attended by the plaintiff and the WSPCC. The plaintiff alleges that all parties understood that it was to do the work and that it would be paid when the money became available.

The plaintiff further alleges that it performed the work, periodically consulting with the WSPCC and companies referred to it by the towns, and, in 1972, it turned over its plans and drawings for both systems to the WSPCC. In turn, the WSPCC gave the plans to another engineering company, which used the plans in another project to build an interceptor running the length of the Winnipesaukee River Basin.

Through the administrative procedures of the WSPCC, the plaintiff sought compensation for the work it had done. When that approach proved unsuccessful, the plaintiff brought suit to recover compensation against the Town of Northfield and the State in Merrimack County Superior Court and against the Town of Tilton in Belknap County Superior Court. The cases were consolidated, and Batchelder, J., granted the defendants’ motions to dismiss the actions against all defendants based on lack of jurisdiction under RSA 491:8. The plaintiff appeals.

RSA 491:8 partially abrogates the State’s sovereign immunity by conferring jurisdiction upon the superior court to decide claims against the State “founded upon any express or implied contract with the state.” The plaintiff argues that the term “implied contract” encompasses both implied in fact contracts and implied in law contracts. An implied in fact contract is a true contract that is not expressed in words; the terms of the parties’ agreement must be inferred from their conduct. 1 A. Corbin, Contracts § 18 (1963); Restatement of Contracts § 5, comment a (1932); 1 S. Williston, A Treatise on the Law of Contracts § 3 (1957). An implied in law contract, on the other hand, is not a contract but is a legal remedy imposed by a court “without reference to the assent of the obligor, [arising] from the receipt of a benefit the retention of which is unjust, and requiring the obligor to make restitution.” Presby v. Bethlehem Village District, 120 N.H. 493, 495, 416 A.2d 1382, 1383 (1980) (quoting State v. Haley, 94 N.H. 69, 72, 46 A.2d 533, 535 (1946)). Technically, only implied in fact contracts may be called “implied contracts”; implied in law contracts are more accurately called “quasi-contracts.” 1 A. Cor- *515 bin, Contracts § 19 (1963); Restatement of Contracts § 5, comment a (1932); 1 S. Williston, A Treatise ON the Law of Contracts § 3A (1957). Courts, however, including this one, have used the phrase “implied in law contract” when referring to a quasi-contract. Presby v. Bethlehem Village District, supra at 495, 416 A.2d at 1383. Because the statutory words “implied contract” may refer either to implied in fact contracts only or also to implied in law contracts, the phrase is ambiguous.

In construing the ambiguous language of a statute, this court must determine the legislature’s intent. Silva v. Botsch, 120 N.H. 600, 601, 420 A.2d 301, 302 (1980); Corson v. Brown Prods., Inc., 119 N.H. 20, 23, 397 A.2d 640, 642 (1979). Although there is no legislative history to guide us in interpreting RSA 491:8, the reports of the Judicial Council can be an acceptable source of information on legislative intent. See Corson v. Brown Prods., Inc., supra at 23, 397 A.2d at 642; 2A C. SANDS, SUTHERLAND STATUTORY Construction § 48.11 (3d ed. rev. 1973).

In 1950 the Judicial Council, pursuant to the authority conferred on it by the legislature, Laws 1945, 169:1 (current codification at RSA 494:3), recommended enactment of a statute abrogating State sovereign immunity for claims based on express or implied contracts and submitted a draft bill to the legislature. N.H. Judicial Council, The Third Report 42 (1950). The law as originally enacted did not follow the Judicial Council’s recommendation with regard to implied contracts. N.H. Judicial Council, The Fourth Report 34 (1952); see Laws 1951, 243:1. In 1952, the Judicial Council renewed its recommendation, commenting:

“It seems probable that the refusal to confer general authority upon the Superior Court in actions founded upon contract was due to some misconception as to the nature of an implied contract. An implied contract in its essential characteristics is not different from an express contract except that some terms must be implied. In any suit founded on contract, either express or implied, recovery depends upon the existence of a contract. The fact that some of the terms may be implied or inferred from the conduct of the parties does not alter the basic character of the action.”

N.H. Judicial Council, The Fourth Report 34 (1952).

That explanation, and the examples that followed, show that the Judicial Council understood an “implied contract” to be an implied in fact contract. Id.-, see 1 A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XTL-NH, Inc. v. New Hampshire State Liquor Commission & a.
183 A.3d 897 (Supreme Court of New Hampshire, 2018)
ROK Builders v. 2010-1 SFG Venture
2012 DNH 148 (D. New Hampshire, 2012)
Jean Moreau & Assoc. v. Health Center Comm'n
Supreme Court of Virginia, 2012
Durgin v. Pillsbury Lake Water District
903 A.2d 1003 (Supreme Court of New Hampshire, 2006)
Lorenz v. New Hampshire Administrative Office of Courts
883 A.2d 265 (Supreme Court of New Hampshire, 2005)
Invest Almaz v. Temple-Inland
2000 DNH 037 (D. New Hampshire, 2000)
Roderick v. NH Hospital, et al.
2000 DNH 026 (D. New Hampshire, 2000)
Pacamor Bearings v. Minebea, Ltd.
D. New Hampshire, 1995
Pacamor Bearings, Inc. v. Minebea Co., Ltd.
892 F. Supp. 347 (D. New Hampshire, 1995)
Town of Tilton v. State
629 A.2d 791 (Supreme Court of New Hampshire, 1993)
Stone and Michaud Ins., Inc. v. Bank Five for Sav.
785 F. Supp. 1065 (D. New Hampshire, 1992)
Nashua Young Women's Christian Ass'n v. State, Department of Labor
597 A.2d 535 (Supreme Court of New Hampshire, 1991)
Hydro Conduit Corp. v. Kemble
793 P.2d 855 (New Mexico Supreme Court, 1990)
Panto v. Moore Business Forms, Inc.
547 A.2d 260 (Supreme Court of New Hampshire, 1988)
Riblet Tramway Co. v. Stickney
523 A.2d 107 (Supreme Court of New Hampshire, 1987)
Goodwin Railroad v. State
517 A.2d 823 (Supreme Court of New Hampshire, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
431 A.2d 770, 121 N.H. 511, 1981 N.H. LEXIS 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgenroth-associates-inc-v-town-of-tilton-nh-1981.