Morganti Inc. v. Conn. Ed. Assoc., No. Cv91-0702652 (Apr. 30, 1992)

1992 Conn. Super. Ct. 3906, 7 Conn. Super. Ct. 580
CourtConnecticut Superior Court
DecidedApril 30, 1992
DocketNo. CV91-0702652 CV91-702669
StatusUnpublished

This text of 1992 Conn. Super. Ct. 3906 (Morganti Inc. v. Conn. Ed. Assoc., No. Cv91-0702652 (Apr. 30, 1992)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morganti Inc. v. Conn. Ed. Assoc., No. Cv91-0702652 (Apr. 30, 1992), 1992 Conn. Super. Ct. 3906, 7 Conn. Super. Ct. 580 (Colo. Ct. App. 1992).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION RE MOTIONS TO VACATE AND TO CONFIRM ARBITRATION AWARD Applicant Morganti, Incorporated (Morganti), brings an application to vacate a certain arbitration award in one action and Connecticut Education Association (CEA) brings an application to confirm that same award in the other action.

FACTS

On or about February 10, 1989, CEA entered into a contract with Morganti to construct a seven-story office CT Page 3907 building on property owned by CEA in Hartford, Connecticut, for a "lump sum" contract price of $12,950,000. Morganti started to perform its obligations.

The contract had an arbitration clause, which in pertinent part is as follows:

All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof . . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.

After Morganti started to work, it claimed that certain unforeseen subsurface conditions in the nature of unanticipated rock were encountered on the project. This claim led to a substantial dispute between the parties, which resulted in CEA's demand for arbitration.

On January 22, 1990, Morganti filed an answer. It also filed a counterclaim, claiming that CEA had breached the contract by failing to pay Morganti for the removal of the rock.

Before any arbitration hearings started CEA's claim was settled by a Settlement Agreement on July 17, 1990.

The original contract did not provide for liquidated damages. The Settlement Agreement provided for two kinds of liquidated damages. One such kind of damages was to result if Morganti failed to complete the top three floors of the project to such an extent that they were "permanently watertight" and ready for tenant fit-up work by July 17, 1990. Those damages were to be in the amount of $4,000 per day.

The other kind of liquidated damages the Settlement Agreement provided for were to result if Morganti failed substantially to complete the entire project by October 2, 1990. Those damages were to be $6,000 per day.

The Settlement Agreement also contained its own arbitration clause as follows:

The Parties agree that any dispute arising out of the requirements and conditions of this agreement shall also be subject to arbitration, in accordance with the terms of CT Page 3908 the Contract. In the event that all of the terms and conditions hereof are fully met and accomplished by all of the parties, then the arbitration pending, which has been deferred by agreement of the parties, will be withdrawn.

It also provided:

Should either party to this agreement find it necessary to institute or demand arbitration to enforce any provision herein, then the prevailing party in said action or arbitration shall be entitled to recover its reasonable legal fees, costs and expenses for arbitration and arbitrators (if any), and all other necessary and reasonable costs and expenses incurred to enforce this Agreement.

Morganti claimed that it substantially completed the top three floors of the project by July 17, 1990 in accordance with the Settlement Agreement. CEA's architect found that those were not ready until July 23, 1990, and on that basis, CEA assessed $24,000 in liquidated damages against Morganti (6 days x $4,000).

After signing the Settlement Agreement, Morganti claimed more unforeseen subsurface conditions which caused Morganti delay in the excavation of the project.

Morganti also claimed that as a result of the excavation delay it failed to achieve substantial completion of the project until March 1, 1991, or 150 days beyond the date set forth in the Settlement Agreement. Because of that failure CEA assessed only $894,000 in liquidated damages against Morganti, (149 days x $6,000).

CEA withheld a total of $918,000 ($24,000 + $894,000) from the progress payments due Morganti during the course of construction.

On September 4, 1990, Morganti filed an amended counter-claim in the arbitration seeking a determination that it had completed the top three floors of the project in full accordance with the Settlement Agreement and was, therefore, not liable for liquidated damages. This counterclaim was followed by a second amended counterclaim filed on December 7, 1990 setting forth that:

[Morganti] seeks a determination that: (1) It delivered the fifth, sixth, and seventh floors of the building in question to the owner CT Page 3909 in full accordance with and satisfaction of the terms of the Settlement Agreement executed by the parties on July 17, 1990 and is not, therefore, liable for liquidated damages as provided in the Settlement Agreement; and (2) it is not liable for liquidated damages as provided in the Settlement Agreement because it did not [sic] achieve substantial completion on the building on October 2, 1990.

On December 14, 1990, the parties began the arbitration hearings. On May 2, 1991 Morganti added to its counterclaim a request for additional relief as follows:

An equitable adjustment to the contract sum to compensate it for damages resulting from the unforeseen subsurface conditions encountered after July 17, 1990, including, but not limited to, extra labor, materials, and equipment and delay damages.

The three arbitrators were, Attorney Mark Shipman (Shipman); Charles A. Ahlstrom, an architect (Ahlstrom); and William M. Ivler, a contractor and Attorney (Ivler). During the course of the hearings Ivler became ill and the parties agreed to go forward with only two arbitrators. The hearings ended July 11, 1991, at which time the arbitrators ordered post-hearings briefs to be filed by August 28, 1991, and reply briefs by September 10, 1991. The hearings then would be deemed closed under Rule 35 of the Construction Industry Arbitration Rules of the AAA (AAA Rules), and the award would be due 30 days thereafter. The parties submitted their post-hearings briefs and reply briefs in accordance with the orders and awaited the decision of the panel.

On October 3, 1991, Robert M. Barrack (Barrack), one of Morganti's attorneys, received a telephone call from John C. Yavis, Jr. (Yavis), co-counsel for CEA, who explained that he had the arbitrators on the telephone line, and that they wanted to ask him (Yavis) a question. Yavis then put the arbitrators on his speaker phone so that Barrack could hear the conversation. Shipman told Barrack that the arbitrators were in executive session in Shipman's office and they wanted a clarification from Yavis regarding an item in Appendix B of CEA's post-hearings brief, but wanted to make sure Morganti's counsel was listening to the conversation.

Appendix B to CEA's post-hearings brief is entitled "Capital Place Project Costs Summary", and contained a line item entitled "carrying costs". That summary showed that CT Page 3910 $709,000 was allocated to the line item for carrying costs, out of the $21.5 million project budget and that as of July 31, 1991 none of these "carrying costs" had been expended. However, the summary did indicate that the full budgeted amount of $709,000 would eventually be expended and comprise part of the total project cost prior to final completion.

Shipman indicated that the arbitrators did not understand what the carrying costs were and why none of them had been as yet expended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Costello Construction Corporation v. Teamsters Local 559
355 A.2d 279 (Supreme Court of Connecticut, 1974)
Berger v. Shanahan
118 A.2d 311 (Supreme Court of Connecticut, 1955)
Board of Trustees v. Federation of Technical College Teachers
425 A.2d 1247 (Supreme Court of Connecticut, 1979)
Ramos Iron Works, Inc. v. Franklin Construction Co.
392 A.2d 461 (Supreme Court of Connecticut, 1978)
Von Langendorff v. Riordan
163 A.2d 100 (Supreme Court of Connecticut, 1960)
Local 63, Textile Workers Union of America v. Cheney Bros.
141 Conn. 606 (Supreme Court of Connecticut, 1954)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Borough of Naugatuck v. AFSCME, Council 4, Local 1303
460 A.2d 1285 (Supreme Court of Connecticut, 1983)
Town of Trumbull v. Trumbull Police Local 1745
470 A.2d 1219 (Connecticut Appellate Court, 1983)
Brown v. Wheeler
17 Conn. 345 (Supreme Court of Connecticut, 1845)
Hanson Development Co. v. East Great Plains Shopping Center, Inc.
485 A.2d 1296 (Supreme Court of Connecticut, 1985)
O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3
523 A.2d 1271 (Supreme Court of Connecticut, 1987)
City of New Haven v. AFSCME, Council 15, Local 530
544 A.2d 186 (Supreme Court of Connecticut, 1988)
Watertown Police Union Local 541 v. Town of Watertown
555 A.2d 406 (Supreme Court of Connecticut, 1989)
Lizotte v. Conservation Commission of the Town of Somers
579 A.2d 1044 (Supreme Court of Connecticut, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1992 Conn. Super. Ct. 3906, 7 Conn. Super. Ct. 580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morganti-inc-v-conn-ed-assoc-no-cv91-0702652-apr-30-1992-connsuperct-1992.