Morgan ex rel. Parker v. Mayor of Baltimore

58 Md. 509, 1882 Md. LEXIS 50
CourtCourt of Appeals of Maryland
DecidedJuly 12, 1882
StatusPublished
Cited by4 cases

This text of 58 Md. 509 (Morgan ex rel. Parker v. Mayor of Baltimore) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan ex rel. Parker v. Mayor of Baltimore, 58 Md. 509, 1882 Md. LEXIS 50 (Md. 1882).

Opinion

Irving, J.,

delivered, the opinion of the Court.

The appellant sued the Mayor and City Council of Baltimore, in The Baltimore City Court, and declared in two counts. The first count was for money payable to the plaintiff for work and labor done by the plaintiff for the defendant at defendant's request; the second count set up a special contract, made with the Water Board of the City of Baltimore, for dredging Lake Roland ; which contract it alleged the city had stopped the plaintiff from completing, by' which he had lost large profits he would have received, if he had been permitted to complete the contract.

At the trial the appellant was permitted by the Court to recover, and did recover for certain work and labor mentioned in his third prayer which was granted; but by the instructions of the Court he was denied recovery for the alleged wrongful abrogation of the contract by the city, and for what he claimed to have done, by the directions of the engineer of the Water Board, in the way of spreading and grading the deposit removed from the lake, and which he contended was extra work, not called for by the contract. The City Court thought, that by the true construction of the contract, the City had the right to terminate the contract when three hundred thousand cubic yards of deposit had been removed from the lake ; and also that the work, charged for as extra work, was required by the contract, and no extra compensation was demand-able for it. The jury was so instructed, as asked by the first and third prayers of the appellee.

The Court also rejected the first and second prayers of the plaintiff, (appellant here), which presented the contrary view. The second prayer of the defendant (appel[515]*515lee) was also granted, which in substance asserted that there was no evidence that the Water Board had the power and right to make the contract, on behalf of the city, which was sued on; but we have not thought it necessary to discuss or to decide the question raised by this instruction, and so elaborately and ably argued by counsel ou. each side; for, assuming the City Court was in error on that question, the appellant has not suffered by the instruction. If the Water Board bad all the power, which appellant’s counsel claim for ih,—(which we do not ■decide,) still we think the Court was right in the construction of the contract; and the appellant was permitted to recover all he would bo entitled to. By the third prayer of the plaintiff (appellant) the measure of damages was fixed at the contract price. This prayer, asked for by him, was granted, and he cannot complain that he was so restricted when ho asked for no other measure of damages, and nothing is said on the subject in the instructions on behalf of the defendant.

The contract which we are to construe is made up of the following proposals and specifications: “Washington, December 6th, 1815. To the Water Board of the City of Baltimore, Gentlemen:—We propose to remove the deposit in Lake Roland, in accordance with the appended specification, viz., six hundred (600) cubic yards per day for twenty-two (22) cents per cubic yard, not less than 300,000 cubic yards shall be removed.” The specifications appended were as follows, viz., “The material from the great basin of the lake, or from tire entrance to Jones’ Falls and Roland Run, thence to near the Relay House, ■shall' be removed to the shore or land at north of lake, hound by mouth of Roland Run and Ellicott’s Branch. All of the material shall be laid not less than ten feet from the upper edge of the slopes, and distributed as directed by the engineer, around the above bounds. The material removed from Roland' Run will be deposited on [516]*516each embankment, also on Jones’ Palis, as directed by the engineer of the Water Board. A convenient and intelligent mode of measurement must be agreed upon by the contractor and engineer in charge. The City’s agent will, with the contractor’s agent, keep a record of the duty performed, which will be paid for by monthly estimates of the amount removed, less twenty (20) per cent., until the completion of the contract, when any money due will be paid. Should' the Water Board direct periodical operations of the machine, which will be of the clam shell construction, in consequence of the turbid condition (of the water) that the agitation may produce, it shall be so understood and accepted by the contractors. Signed James M. Allen, Thomas P. Morgan.”

Subsequently, at the request of James Curran, who. was the Water Board engineer, the contractors submitted this projsosal, which was drafted by Curran: April 19th, 1816. To the Water Board of the City of Baltimore, Gentlemen:—In addition to the dredging of Lake Roland, we propose to remove the material to any point directed by the engineer on the City’s land bordering on the lake. And for all material moved beyond the limits of the specifications, thirty-five (35) feet, which shall be the minimum, and the maximum the City’s land. We agree to do the work for ten cents per cubic yard.” This proposal was also accepted by the Water Board, and the work proceeded during the summer and fall of 1816. In the spring of 1811 Allen assigned the contract to Morgan, the plaintiff, and the Water Board accepted Morgan as the contractor. The work was carried on from time to time during the years 1811, 1818, 1819 and 1880, until 1880,. in the month of April, when over three hundred thousand cubic yards having been dredged and removed, (for which $94,636.16 was paid,) the work was stopped by order of the Water engineer, acting under directions from the Water Board. When this was done, the plaintiff con[517]*517tends the whole bottom surface of the lake had not been dredged, which he insists the contract contemplated; and therefore claims damages for not being allowed to complete the dredging of the whole lake. It is very clear, that these two proposals with the specifications annexed form the contract. The circular letter of the, engineer, which > brought the proposal of the 6th of December, 1815, is not in the record, but it is stated in the bill of exceptions to have been an invitation for proposals to dredge the lake. When the proposal came, it was for dredging not less than 300,000 cubic yards. That proposal was accepted, and bound the employes not to stop the work before that much work had been done. By its very terms, as we understand them, the right of the Board to have the work stopped when that much was dredged is recognized by necessary implication. Fearing that after the contractor had fitted up for the work, he might be stopped before he had paid himself sufficiently for his undertaking, they stipulate that he shall be permitted to do that much work at the least. If he had chosen, when the 300,000 cubic yards had been done, to stop the work, because he found it unremunerative, he could undoubtedly have done so, without the City having any claim on him for breach of contract. That much was to be done, and it was to be done within a period capable of immediate ascertainment, for he was to take out six hundred cubic yards per day. By the specifications, the City reserved the power to have it done in periods, if the condition of the water in the lake made periodical labor necessary. Nothing is said anywhere about dredging the whole lake. The deposit in the lake to the extent of three hundred thousand cubic yards was to be removed; and when that was done, in our opinion either party was at liberty to suspend the work and close the contract. It is in evidence, that the portions of the lake toward the mouth of the tributaries that.feed it, were dredged over several times during the four years

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Structures, Inc. v. Mayor of Baltimore
364 A.2d 55 (Court of Appeals of Maryland, 1976)
State ex rel. Shaw v. Thompson
131 N.W. 231 (North Dakota Supreme Court, 1911)
American Mortgage Co. v. Boyd
92 Ala. 139 (Supreme Court of Alabama, 1890)
Banks v. Chas. P. Harris Manuf'g Co.
20 F. 667 (U.S. Circuit Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
58 Md. 509, 1882 Md. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-ex-rel-parker-v-mayor-of-baltimore-md-1882.