Morey v. Public Utilities Commission

629 P.2d 1061, 1981 Colo. LEXIS 702, 1981 WL 610431
CourtSupreme Court of Colorado
DecidedJune 8, 1981
Docket79 SA 301
StatusPublished
Cited by22 cases

This text of 629 P.2d 1061 (Morey v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morey v. Public Utilities Commission, 629 P.2d 1061, 1981 Colo. LEXIS 702, 1981 WL 610431 (Colo. 1981).

Opinion

DUBOFSKY, Justice.

Appellant C. M. Morey, doing business as Star Motor Freight Lines (Star) 1 , appeals from a district court order affirming a decision of the Public Utilities Commission (P. U. C. or Commission). The P. U. C. denied Star’s application for a certificate of convenience and necessity authorizing it to transport general commodities as a motor vehicle common carrier 2 between Denver, Pueblo and Lamar, Colorado. 3

*1063 We previously considered the Commission’s denial of this application in Morey v. Public Utilities Commission, 196 Colo. 153, 582 P.2d 685 (1978) (Morey I). There we remanded the matter to the Commission for “a decision properly applying the doctrine of regulated competition.” 196 Colo. at 158, 582 P.2d at 688. In compliance with our mandate, the P. U. C. reviewed the record and, in Decisions C78-1696 and C79-192, again refused to issue the certificate requested by Star. Star now contends that the P. U. C.’s decisions on remand misconceive our ruling in Morey I that “[u]nder the policy of ‘regulated competition,’ the controlling consideration is the public need,” 196 Colo. at 156, 582 P.2d at 687 (emphasis in original), and are otherwise unsupported by competent or substantial evidence in the record. Because we conclude that the criterion of “public need” announced in Morey I is broad enough to subsume the decisional guidelines applied by the P. U. C. in Decisions C78-1696 and C79-192, and because we find that the Commission’s findings and conclusions in those decisions are adequately supported in the record, we affirm the order of the district court.

Star has held contract carrier 4 authority to serve the routes in question for many years. However, it did not actively begin serving Pueblo until sometime after 1967, and did not initiate service to points in the Arkansas Valley until 1974. Shortly after it began operations in the Valley, Star filed an application for “conversion” to a common carrier with authority to serve Colorado Springs, Pueblo and the Arkansas Valley. 5

Several common carriers already serving these routes or municipalities intervened to protest the application. After a series of hearings at which Star presented the testimony of public witnesses favoring its application and the protestants adduced evidence that additional competition would have an adverse impact on existing common carrier services, the hearing officer recommended approval of the greater part of Star’s application. 6 The protestants filed exceptions to the examiner’s recommended decision and, after reviewing the record of the hearing, the P. U. C. entered its own decision denying the bulk of the application but authorizing Star to operate as a common carrier between Denver and Colorado Springs.

Star appealed to the district court, which reversed the Commission and granted the' entire authority recommended by the hearing officer. The protestants and the P. U. C. appealed to this Court, which affirmed the Denver-Colorado Springs certification, reversed the decision of the district court granting the remainder of the application, and remanded the cause to the Commission for reconsideration in light of the statutory policy of “regulated competition” ‘adopted by the legislature in 1967, section 40-10-105(2), C.R.S.1973, and first construed by this Court in Miller Brothers, Inc. v. Public Utilities Commission, 185 Colo. 414, 525 P.2d 443 (1974) and its companion cases.

After remand, the Commission reviewed the record a second time and entered two new decisions, Nos. C78-1696 and C79-192, again denying Star’s application. It is from these decisions that Star appeals.

*1064 I.

To understand the context in which the questions presented by this appeal have arisen, the bases for the remand in Morey I must be summarized. There the Commission ruled that, notwithstanding our decisions in Miller Brothers, Inc. v. Public Utilities Commission, supra, Red Ball Motor Freight, Inc. v. Public Utilities Commission, 185 Colo. 438, 525 P.2d 439 (1974); and D & G Sanitation, Inc. v. Public Utilities Commission, 185 Colo. 386, 525 P.2d 455 (1974):

“Even assuming ... that the testimony of [Star’s] own presently satisfied customers makes out a case of public need, there has been no showing of any substantial inadequacy in the existing service. It is true, of course, that since [section 40-10-105(2)] a showing of inadequacy is no longer an indispensable element of every case. In several of the prior conversion cases, the adequacy issue was in fact relegated to fairly minor importance. But those were unusual cases. They marked the transition from the days of regulated monopoly to a competitive common carrier system. The establishment of a competitive system was the driving consideration in those earlier cases. It was necessary to look beyond the mere adequacy of existing service.”

Morey I, 196 Colo. at 157, 582 P.2d at 688 (quoting from the decision of the P. U. C.) (emphasis added). Because Star, unlike the applicants in the Miller Brothers, Red Ball, and D & G Sanitation cases, did not commence its Denver-Pueblo and Arkansas Valley contract carrier services until after the enactment of section 40-10-105(2), the Commission distinguished Star’s application for “conversion” from the applications granted in those earlier, “unusual” cases. In the Commission’s eyes, Star’s application for common carrier authority stood on “.. . the same footing as any other application in which a carrier is seeking to expand its operations into a new territory,” id., and it held that, in such cases, a certificate of public convenience and necessity may not be granted unless the applicant proves both a public need for the proposed services and a substantial inadequacy in the services furnished by existing common carriers. Since Star’s evidence failed to disclose any such inadequacy in existing common carrier services, the P. U. C. denied its application.

We rejected the Commission’s purported distinction between the earlier “conversion” applications and Star’s 1974 application. Recurring to our interpretation of section 40-10-105(2) in Miller Brothers, Inc. v. Public Utilities Commission, supra, we reasoned that the legislature intended the doctrine of “regulated competition” to supplant the old policy of “regulated monopoly” not for the limited purpose of integrating contract carriers then operating as

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trans-Western Express, Ltd. v. Public Utilities Commission
877 P.2d 350 (Supreme Court of Colorado, 1994)
Durango Transportation, Inc. v. City of Durango
786 P.2d 428 (Colorado Court of Appeals, 1990)
Atchison, Topeka & Santa Fe Railway Co. v. Public Utilities Commission
763 P.2d 1037 (Supreme Court of Colorado, 1988)
Colo. Mun. League v. MOUNTAIN STATES TEL.
759 P.2d 40 (Supreme Court of Colorado, 1988)
Colorado-Ute Electric Ass'n v. Public Utilities Commission
760 P.2d 627 (Supreme Court of Colorado, 1988)
GTE Sprint Communications Corp. v. Public Utilities Commission
753 P.2d 212 (Supreme Court of Colorado, 1988)
Colorado Office of Consumer Counsel v. Public Utilities Commission
752 P.2d 1049 (Supreme Court of Colorado, 1988)
G & G Trucking Co. v. Public Utilities Commission
745 P.2d 211 (Supreme Court of Colorado, 1987)
Acme Delivery Service, Inc. v. Cargo Freight Systems, Inc.
704 P.2d 839 (Supreme Court of Colorado, 1985)
RAM Broadcasting of Colorado, Inc. v. Public Utilities Commission
702 P.2d 746 (Supreme Court of Colorado, 1985)
Colorado Energy Advocacy Office v. Public Service Co.
704 P.2d 298 (Supreme Court of Colorado, 1985)
Colorado Municipal League v. Public Utilities Commission
687 P.2d 416 (Supreme Court of Colorado, 1984)
City of Montrose v. PUBLIC UTILITIES COM'N, ETC.
629 P.2d 619 (Supreme Court of Colorado, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
629 P.2d 1061, 1981 Colo. LEXIS 702, 1981 WL 610431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morey-v-public-utilities-commission-colo-1981.