Moretrench American Corporation v. S.J. Groves and Sons Company

839 F.2d 1284, 34 Cont. Cas. Fed. 75,443, 1988 U.S. App. LEXIS 2289, 1988 WL 13286
CourtCourt of Appeals for the Seventh Circuit
DecidedFebruary 24, 1988
Docket87-1671
StatusPublished
Cited by11 cases

This text of 839 F.2d 1284 (Moretrench American Corporation v. S.J. Groves and Sons Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moretrench American Corporation v. S.J. Groves and Sons Company, 839 F.2d 1284, 34 Cont. Cas. Fed. 75,443, 1988 U.S. App. LEXIS 2289, 1988 WL 13286 (7th Cir. 1988).

Opinion

POSNER, Circuit Judge.

Moretrench, a subcontractor on a project to repair a federally owned dam on the Mississippi River, brought suit under the Miller Act, 40 U.S.C. §§ 270a-270d, against its prime contractor, a joint venture named GAB. The district court stayed the suit, at GAB’s request, pending resolution of certain disputes between GAB and the Corps of Engineers (the owner of the dam). Mor-etrench appeals from the stay. The first and only question we shall have to consider is our appellate jurisdiction.

When a subcontractor incurs an additional expense as a result of a change order issued by the owner, or some other change in circumstances for which the owner is responsible, the prime contractor, naturally, does not want to have to reimburse the subcontractor out of its own pocket, but instead wants the owner to bear the expense. To this end, the disputes clause in the contract between GAB and Moretrench provided that in the event of a dispute between the parties that involved the owner, Moretrench would be bound by the determination of responsibility made in accordance with the procedures set forth in the contract between GAB and the Corps of Engineers. That contract provided for initial determination by a federal contracting officer with a right of appeal to a board of contract appeals or to the United States Claims Court.

One of the disputes (and the subject of Count I of Moretrench’s complaint) was over extended pumping. Moretrench, whose job in the project was to “dewater” the area behind a cofferdam, claimed that it had to keep pumping for 292 days beyond the term specified in its contract with GAB, and it sought additional payment for the extra days. GAB duly submitted the claim to the Corps, which acknowledged liability for 95 days at the specified contract price of $5,100 per day and remitted payment for them at that rate to GAB, which in turn paid Moretrench. More-trench argues that GAB, not the Corps, was responsible for the other 197 days of extra pumping, and hence that the only remaining quarrel over the issue is between it (Moretrench) and GAB — a quarrel to which the pending proceeding in the Claims Court is irrelevant. However, GAB claims that not it but the Corps was responsible for the extra 197 days; that is one of the issues in litigation in the Claims Court.

*1286 In Count II of its complaint Moretrench seeks an additional payment of $664,000 for a work modification. The Corps’ contracting officer allocated this amount to Moretrench, and it was paid over to GAB. But rather than remit the money to More-trench, GAB has retained the money as a potential source of funds for satisfying its claims against the Corps arising out of the contract, and these claims too are pending in the Claims Court. Finally, Count III seeks $200,000 that the Corps allocated to Moretrench but then retained in order to offset overpayments that the Corps says it made to GAB under the contract. GAB denies that there were overpayments, and this is another issue in the Claims Court. (So Counts II and III involve mirror images: GAB retaining Moretrench’s money in Count II, the Corps retaining More-trench’s money in Count III.) Moretrench argues forcefully that all three disputes are purely between GAB and the Corps, and that it is entitled to get its money now, without waiting years for the proceeding in the Claims Court to end. In so arguing, Moretrench relies on a provision in the disputes clause of the subcontract that nothing in that clause “shall be construed in any manner to affect Subcontractor’s rights and remedies against the Contractor involving disputes or claims not solely due to the acts or omissions of the Owner.”

The stay granted by the district court is, of course, an interlocutory order. It does not resolve Moretrench’s lawsuit against GAB, but merely postpones proceedings in the suit until a final determination by the Claims Court of the claims that Moretrench submitted to GAB for presentation to the Corps of Engineers. In arguing that the stay is appealable even though it is interlocutory, Moretrench relies primarily on the “Enelow-Ettelson” doctrine, an obscure and disfavored doctrine of appellate jurisdiction, see Olson v. Paine, Webber, Jackson & Curtis, Inc., 806 F.2d 731 (7th Cir.1986), which provides that if the judge in a suit at law grants a stay that is in furtherance of an equitable claim or defense, the stay is appealable immediately under 28 U.S.C. § 1292(a)(1) as a preliminary injunction. The threadbare reasoning that supports this result is that in 1891, when the predecessor to section 1292(a)(1) (which authorizes the immediate appeal of orders granting, denying, etc. preliminary injunctions) was first enacted, such a stay could have been issued only by a chancellor, and it is therefore in the nature of an injunction. It is doubtful that the historical analysis is correct, and unclear why it should survive the merger of law and equity; but that is neither here nor there, as Enelow-Ettelson is a Supreme Court doctrine that we concluded in Olson is still authoritative.

Moretrench’s suit against GAB is a suit at law; it seeks damages for breach of contract. The fact that it also seeks a declaratory judgment is irrelevant. Although a suit which seeks both legal and equitable relief is deemed equitable for purposes of applying the Enelow-Ettelson doctrine unless the equitable relief sought is nominal (Olson v. Paine, Webber, Jackson & Curtis, Inc., supra, 806 F.2d at 737; Medtronic, Inc. v. Intermedics, Inc., 725 F.2d 440, 443-46 (7th Cir.1984)), a request for declaratory relief is deemed neither legal nor equitable — a proper result, considering the confused lineage of declaratory judgments, on which see, e.g., Petition of Kariher, 284 Pa. 455, 464-65, 131 Atl. 265, 268 (1925); Sunderland, A Modern Evolution in Remedial Rights-The De claratory Judgment, 16 Mich.L.Rev. 69 (1917); Borchard, The Declaratory Judgment — A Needed Procedural Reform, 28 Yale L.J. 105 (1918). Instead, the underlying relief sought determines the character of the suit. See, e.g., Employers Insurance of Wausau v. Shell Oil Co., 820 F.2d 898, 900-01 (7th Cir.1987); Mowbray v. Moseley, Hallgarten, Estabrook & Weeden, Inc., 795 F.2d 1111, 1114 (1st Cir.1986). Since declaratory judgments do not have a clear equitable pedigree — indeed, they did not exist in this country in the nineteenth century, although equivalent forms of relief could sometimes be achieved by other routes, some legal, some equitable — an attractive alternative would have been to classify them as legal for purposes of Ene-low-Ettelson in order to cut down a bit on *1287 the scope of that disfavored doctrine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
839 F.2d 1284, 34 Cont. Cas. Fed. 75,443, 1988 U.S. App. LEXIS 2289, 1988 WL 13286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moretrench-american-corporation-v-sj-groves-and-sons-company-ca7-1988.