Morehouse Lumber & Building Material Co. v. Walker

139 So. 713, 1932 La. App. LEXIS 312
CourtLouisiana Court of Appeal
DecidedFebruary 16, 1932
DocketNo. 4034
StatusPublished
Cited by3 cases

This text of 139 So. 713 (Morehouse Lumber & Building Material Co. v. Walker) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morehouse Lumber & Building Material Co. v. Walker, 139 So. 713, 1932 La. App. LEXIS 312 (La. Ct. App. 1932).

Opinion

MeGREGOR, J.

This is a suit involving the right of a judgment creditor of a building contractor to garnishee funds in the hands of the owner but due to the contractor on the basis of estimates made from time to time as the work progresses. On December 11, 1929, Jacob & Walker, a building copartnership, and C. N. Storey, the owner of a lot in the town of Bas-trop, entered into a contract wherein Jacob & Walker, referred to as the contractors, agreed to build for C. N. Storey, referred to as the owner, a one-story brick veneer residence and a garage, all according to certain plans and specifications attached to the contract. This contract and the bond given as required by law were duly recorded in the mortgage records of Morehouse parish.

In the contract it was agreed that the contractors should “find, purchase and furnish all labor and material of such kind and quality as mentioned in the specifications in such quantity for completion and finishing' said building as provided in said specifications and plans.” The contract price agreed upon for the completion of the work was $6,000. One of the paragraphs in the contract provides as follows: “The Owner for and in consideration of the Contractors’ completion and faithfully executing the aforesaid work and furnishing all the material therefor, agrees to pay to the Contractors a sufficient amount of money to pay for material actually on the ground and labor from time to time as the work progresses, provided no payments or sums of payments exceed eighty-five (85%) per cent, of the contract price, and upon the completion and acceptance of said work and building by the Owner to pay to the Contractors a sufficient amount of money to make the amount of money paid including the amount advanced from time to time as the work progresses, eighty-five (85%) per cent, of the contract price; and thirty (30) days from the date of completion of said work and acceptance of the same by the Owner, to pay to the Contractors the balance due on said contract price.”

On January 23, 1930, while the contractors were erecting the building for the owner, the plaintiff, Morehouse Lumber & Building Material Company, Inc., filed suit against the contractors on a promissory note for $819.45, with interest and attorney’s fee, less a credit of $100, and judgment was rendered by default as prayed for. It should be mentioned in passing that the indebtedness represented by the note had no connection with the material and labor required for the erection of the building under the contract referred to above.

On February 19, 1930, the plaintiff caused to be issued a writ of fi. fa. on its judgment against the defendants, and at the same time filed a supplemental petition, and caused the owner, C. N. Storey, to be made garnishee and cited to declare under oath in what sum, if any, he was indebted to the defendants. Storey answered the interrogatories propounded ’to him, and stated that under the terms of the contract between him and the defendants he had, prior to the service of the interrogatories upon him, paid the defendants the sum of $2,210, and that at the time [715]*715of and since-tile garnishment the defendants, in accordance with the terms of the contract, had presented to him an estimate under which they are claiming the sum of $214.05, which sum he had recognized as being justly due. He further answered that $6,000 would be due thirty days after the completion of the job, less all payments made from time to time as the work should progress. This sum of $214.05 was held by Storey, the owner, subject to the further orders of the court in the garnishment proceedings.

On March 7, 1930, the defendants answered the supplemental petition of the plaintiff in the garnishment proceedings, and caused a rule to issue directed to the plaintiff and the garnishee, ordering them to show cause why the writs of fieri facias and garnishment should not be set aside and annulled, and why O. N. Storey, the owner and garnishee, should not be ordered to pay to the defendants, contractors, the sum due and owing for labor performed and material furnished in the erection of the building described in the contract between the contractors and the owner.

In their answer to the supplemental petition of the plaintiff and their application for a rule, the defendants set out the terms and conditions of their contract with Storey; that up to February 22, 1930, $2,210 had been received by them, and that on that date there was due to them the sum of $214.05. It was specially alleged that this amount was due and owing for labor performed and material used in the erection of the owner’s building, and that it was not to inure to the benefit of the contractors in any way, but was to be used solely for the payment of the labor performed and material furnished under the terms of the contract. They then allege that the amount due labor for work done on the said building and due subcontractors for work performed and for material already furnished on the building exceeds the balance due to defendants on the contract price, and that all these, the laborers, the subcontractors, and the furnishers of material, have a lien and privilege on the building, on the contract price, and on any sums of money due and owing by the owner, O. N. Storey, priming and outranking any and all other claims against them. They allege that, since the full amount due for labor and material already furnished exceeds the difference between the contract price and the amount already paid, none of the fund due and to become due can be subject to garnishment for the payment of plaintiff’s judgment. Subsequently the defendants filed a supplemental answer for the purpose of asserting a claim against the plaintiff, by way of reconvention. It is contended that they have been damaged by the illegal issuance of the garnishment to the extent of $2,750, and judgment for that sum is prayed for. Because of the conclusions reached herein, it is useless to enumerate the items making up this sum. On the trial of the case in the lower court, there was judgment dissolving the garnishment and dismissing the defendants’ demands in reconvention as of nonsuit. From that judgment the plaintiff has appealed. The defendants filed a motion to dismiss the appeal, and this was denied.

Opinion.

The question to be decided is as to whether the $214.05 held by C. N. Storey, the owner, was subject to garnishment under a writ of fieri facias issued by virtue of a judgment against Jacob & Walker, the contractors. It is the contention of the defendants that ’this money was not due to them in such a way that it was subject to garnishment, but that it was due for labor and material already performed and furnished. They hold that not only this particular sum of money, but all money due under the contract, was to be paid by the owner “in the manner and way set forth in the contract,” and that it “was therefore to be paid upon a contingency and therefore not subject to garnishment.” They assert further that the money sought to he garnished is subject to the liens of the laborers and the furnishers of material, and therefore not subject to garnishment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AF Blair Co., Inc. v. Mason
406 So. 2d 6 (Louisiana Court of Appeal, 1981)
Morehouse Lumber & Building Material Co. v. Jacob & Walker
147 So. 504 (Supreme Court of Louisiana, 1933)
Morehouse Lumber & Building Material Co. v. Jacob & Walker
144 So. 190 (Louisiana Court of Appeal, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
139 So. 713, 1932 La. App. LEXIS 312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morehouse-lumber-building-material-co-v-walker-lactapp-1932.