Moran v. Lafarge North America, Inc.

286 F. Supp. 2d 1002, 2003 U.S. Dist. LEXIS 23970, 2003 WL 22330331
CourtDistrict Court, N.D. Indiana
DecidedSeptember 4, 2003
Docket2:03-cv-00176
StatusPublished
Cited by2 cases

This text of 286 F. Supp. 2d 1002 (Moran v. Lafarge North America, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moran v. Lafarge North America, Inc., 286 F. Supp. 2d 1002, 2003 U.S. Dist. LEXIS 23970, 2003 WL 22330331 (N.D. Ind. 2003).

Opinion

ORDER

LOZANO, District Judge.

This matter is before the Court on the Petition for Temporary Injunction Under Section 10(j) of the National Labor Relations Act, as Amended, filed by Petitioner, Gail R. Moran, 1 on May 15, 2003. For the reasons set forth below, this Petition is GRANTED.

BACKGROUND

LaFarge North America, Inc. (Respondent) operates as a slag granulation facility at Ispat Inland’s Indiana Harbor Works, a plant which is comprised of a collection of steel-related facilities in East Chicago, Indiana. Approximately 5,700 employees at Ispat’s plant are represented by a labor union. Of those, approximately 5,600 are represented by Local 1010 of the United Steelworkers of America (Local 1010).

Local 1010 entered into its latest collective bargaining agreement with Ispat on August 1, 1999; it is valid through July 2004. This collective bargaining agreement basically prohibits contracting out *1005 any work capable of being performed by bargaining unit employees; the type of work subject to these provisions covers both inside and outside construction work done on Ispat’s premises. In the past, employees represented by the United Steelworkers have performed slag removal at Blast Furnace No. 7. Thus, Local 1010 and Ispat were under the impression the collective bargaining agreement did not permit the contracting out of slag removal.

Sometime around the Spring of 1999, Respondent and Ispat began discussing the possibility of an agreement through which Respondent would build and operate a new slag processing facility as Blast Furnace No. 7 using a new advanced process. On or about December 20, 1999, Respondent met with Ispat and Local 1010 to discuss the construction, operation and manning of the proposed slag plant. Respondent was interested in having the prerogative to contract out the construction of the facility; however, pursuant to the collective bargaining agreement, Local 1010 expressed concerns because they maintained that slag removal was bargaining unit work. During the meeting, Respondent, with Ispat’s participation, attempted to convince Local 1010 to waive their subcontracting protection under the collective bargaining agreement and allow Respondent to remove the slag. At the end of the meeting, Local 1010 indicated they would give Respondent’s proposal serious consideration, but if they were going to give up their rights under the collective bargaining agreement, they needed Ispat to give them some incentives.

On January 7, 2000, Local 1010 again met with Respondent to discuss the proposed construction project. Local 1010 reiterated their concerns about the loss of Local 1010 union member jobs and asked questions regarding construction, operation and maintenance of the facility and the movement of slag. Respondent expressed concern about using the pattern contract normally used in the steel industry, and maintained that it was inappropriate for the proposed slag project. Respondent told Local 1010 that they wanted protection from a strike because, if there were a cessation in the removal of slag, a shutdown of Blast Furnace No. 7 could result in a shutdown of the entire plant operation. After the meeting, Respondent sent Local 1010 a copy of a collective bargaining agreement it had used for one of its Canadian slag facilities.

On January 18, 2000, Respondent sent Local 1010 a copy of Respondent’s initial contract proposal. Three days later, Respondent again met with Local 1010 and discussed the terms of the proposed contract. Respondent agreed to recognize Local 1010 after a card check and also agreed to give preference to adversely affected Local 1010 members who were affected by the impact of the new slag facility. In addition, it was agreed that if Local 1010 got a majority status, that the subsequent agreement would become the contract. 2

Between February 9, 2000 through March 14, 2000, Respondent and Local 1010 attempted to outline and resolve most of their outstanding issues. On March 14, *1006 2000, Respondent sent Local 1010 a signed but undated copy of a proposed contract between Respondent and Local 1010 for Local 1010’s approval and signature. Sometime after March 14, 2000, Local 1010 signed the contract, which did not have an effective bargaining date or specific termination date. 3 At this point, Respondent had not yet begun hiring any employees for the new slag granulation facility.

Respondent’s slag granulation facility began construction in early 2001. In June 2001, Respondent hired Steve Marcus as plant manager for the new facility. A few months later, Respondent advertised in local newspapers for certain job openings and solicited resumes from various other sources as well. Ultimately, fourteen employees were hired through this effort.

In December 2001, Local 1010 met with a number of newly hired workers at Respondent’s facility at its union hall. There, Local 1010 asked the workers to sign a Local 1010 authorization card, authorizing Local 1010 to represent them. By January 25, 2002, approximately 9 to 12 of the workers at Respondent’s facility had signed the authorization card. This fact was communicated to Respondent. On that date, Respondent and Local 1010 formally signed, executed and ratified their contract of March 14, 2000.

On February 6, 2002, International Union of Operating Engineers, Local 150 (Local 150) Organizer, David Fagan, informed Marcus, that two employees, Jim Utley and Mike Hardin, were engaging in organizational activities for Local 150 at Respondent’s East Chicago facility. By the middle of February, 17 of Respondent’s employees signed revocation of authorization forms in an attempt to withdraw and revoke prior authorization of Local 1010 to represent them for purposes of collective bargaining. A number of these workers then signed authorization cards authorizing Local 150 to be their collective bargaining representative. Local 150 filed a representation petition with the NLRB asserting that it be certified as the collective bargaining representative for Respondent’s employees engaged in the slag production at the East Chicago facility.

In early May 2002, several of Respondent’s supervisors distributed dues authorization cards for Local 1010 to hourly employees at the new slag facility pursuant to the union security and dues checkoff provisions of the contract with Local 1010. The hourly employees were instructed by the supervisors to turn the checkoff cards in to Respondent by about May 10, 2002.

Subsequently, Region 13 of the National Labor Relations Board (Petitioner) filed a complaint alleging unfair practice charges against Respondent. The thrust of Petitioner’s complaint alleged the March 2000 contract, executed in January 2002, between Respondent and Local 1010 was illegal. In concert, Petitioner also contended Respondent engaged in numerous other unfair practices with regard to recognizing and authorizing Local 1010 to be its employees’ collective bargaining representative. As a result, an Administrative Law Judge of the National Labor Relations Board (ALJ) conducted a full hearing on the merits of Petitioner’s complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Labor Relations Board v. Irving Ready-Mix Inc.
780 F. Supp. 2d 747 (N.D. Indiana, 2011)
Lineback v. Frye Electric, Inc.
539 F. Supp. 2d 1111 (S.D. Indiana, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
286 F. Supp. 2d 1002, 2003 U.S. Dist. LEXIS 23970, 2003 WL 22330331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moran-v-lafarge-north-america-inc-innd-2003.