STATE OF MAINE SUPERIOR COURT , I CUMBERLAND, ss. .' CIVIL ACTION
E OCKE} NO. C;V-,06-280 \A' CL.{ r~ I - ! Ij:.....,,.~-,,'Ci )./'~ . "\ "'il' j ,) , i ,I
" RICHARD M. MORABITO, SR. and MARY MORABITO
Plaintiffs ORDER v.
DONALENE NELSON, WAYNE NELSEN, D&W HOMEBUILDERS, INC., and DWN ASSET MANAGEMENT
Defendants
This case comes before the Court on Plaintiffs' Application for
Confirmation of Award pursuant to 14 M.R.S.A. §5937 and Defendants' Motion
for Modification and Correction of Award pursuant to 14 M.R.S.A. §5939.
BACKGROUND
On or about April 19, 2002, the Morabitos entered into a home
construction contract with the Defendants. Under the agreement, disputes were
to be submitted to binding arbitration.
A dispute arose concerning the construction of the Morabitos' residence.
The Morabitos alleged that the vinyl siding and roof shingles of the residence
were improperly installed, and that there were certain structural defects that
needed repair. 1 Attempts to informally settle the dispute failed, and therefore,
the matter went to binding arbitration.
1Specifically, the Morabitos alleged that the center girder in the garage was not to specifications, that new concrete footing was needed for a lally column, that 12-18 electrical wires needed to be relocated so as not to penetrate the new On January 22,2007, the arbitrator, Michael Dell'Olio, decided that the
vinyl siding and roof shingles were improperly installed, and therefore, ordered
the Defendants to pay to the Morabitos: (1) $456.24 for the defective vinyl
installation, (2) $7,930.00 for the defective roof installation, and (3) an additional
$875.00 "as damages relating to the roofing issue." The arbitrator did not decide
the issue concerning structural defects, noting, "this issue remains open and will
be determined when all papers have been submitted."
On February 21,2007, based on the arbitrator's findings, the Morabitos
filed a motion for confirmation of arbitration award pursuant to M.R.S.A. §5937.
The Defendants objected to this motion, arguing that it was premature to confirm
the award because the arbitrator did not decide the "structural defects" issue.
The court agreed, staying the motion for confirmation of arbitration award until
the arbitrator reached a decision on this issue. The matter did not go to
arbitration until January 22, 2008. On August 7,2008, the arbitrator issued his
dispute resolution report, concluding that there were structural integrity
problems with the Morabitos' residence. Further, he ordered that (1) Defendants
pay for the cost of repairing the Morabitos' residence in the amount of $27,500.00,
(2) all parties must sign off on the final work product of the repairs, (3)
Defendants pay the Morabitos $1,758.00 as damages for the structural defects,
and finally (4) Defendants pay the final arbitration fee of $1,060.00.
On August 25,2008, the Morabitos filed a second application for
confirmation of an award pursuant to 14 M.R.S.A. §5937. On September 9, 2008,
column, and that the "hump" in the kitchen's hardwood floor needed to be repaired.
2 the Defendants filed their motion for modification and correction of award
pursuant to 14 M.R.S.A. §5939.
In their motion for modification, the Defendants (1) request a conclusion
of law and of fact from the arbitrator on the issue of individual liability,
specifically on the issue of whether the corporate veil has been pierced in
accordance with Maine case law; (2) request the arbitrator to decide whether the
right to cure applies in this case; (3) request a finding of fact why Defendants'
expert report, prepared by Associated Design Partners, Inc., was not found
credible; (4) requests a finding of fact why Chase Custom Homes' estimate
concerning the cost to fix the structural integrity was deemed conclusive; and
finally, (5) a finding as to why a monetary award is proper given the fact that the
Morabitos maintain that this dispute has "nothing to do with money." The
Morabitos claim that the arbitration award speaks for itself on all of these issues.
DISCUSSION
Under 14 M.R.S.A. §5937, a court shall confirm an arbitration award
unless, within a certain time, "grounds are urged for vacating or modifying or
correcting the award." Under 14 M.R.S.A. §5935, "if an application to the court is
pending under sections 5937 to 5930/, on submission to the arbitrators under
2This is the case here, where Defendants have moved for a modification or correction of the award pursuant to Section 5939. This section provides:
1. Application. Upon application made within 90 days after delivery of a copy the award to the applicant, the court shall modify or correct the award where:
A. There was an evident miscalculation of figures or an evident mistake in the description of any person, thing or property referred to in the award;
3 such condition as the court may order, the arbitrators may modify or correct the
award on the grounds stated in section 5939, subsection 1, paragraphs A and C
or for the purposes of clarifying the award." (Emphasis added).
In order to confirm an award under 14 M.R.S.A. §5937, the award must be
"sufficiently clear and definite so that it is susceptible of enforcement and those
called upon to enforce it must not be misled or called upon to pay more than is
due." Lisbon School Committee v. Lisbon Educational Ass'n, 438 A.2d 239,245 (Me.
1981). Past Law Court decisions "demonstrate that the standard of 'clarity and
definiteness necessary for a court of law to confirm and enter judgment' requires
arbitration decisions to be unambiguous and enforceable by their terms." Hearst
Corp. v. Swiss Bank Corp., New York Branch, 584 A.2d 655,659 (Me. 1990)(quoting
Sargent v. Town ofMillinocket, 478 A.2d 683, 686 (Me. 1984)).
For example, in Sargent, the Law Court held that it was error for the trial
court to confirm an arbitration award that failed to "state the party against whom
each individual claim or award was made, nor [did] it state the interrelationship,
if any, of the individual awards." 478 A.2d at 685. Based on this failure, the Law
Court held that the court should have submitted the award to the arbitrators for
clarification. Id. at 687.
Here, the Dispute Resolution Award prepared by Mr. Dell'Olio outlines
the amount of money owed to the Morabitos by the Defendants. However, the
award does not specifically state which Defendant, referred to by Mr. Dell'Olio
B. The arbitrators have awarded upon a matter not submitted to them and the award may be corrected without affecting the merits of the decision upon the issues submitted; or
C. The award is imperfect in a matter of form, not affecting the merits of the controversy.
4 collectively as the "Respondents," is responsible for what portion of the amount
owed to the Morabitos. As was the case in Sargent, the arbitrator's failure to
explicitly state the party against whom each individual award was made makes
the award ambiguous.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF MAINE SUPERIOR COURT , I CUMBERLAND, ss. .' CIVIL ACTION
E OCKE} NO. C;V-,06-280 \A' CL.{ r~ I - ! Ij:.....,,.~-,,'Ci )./'~ . "\ "'il' j ,) , i ,I
" RICHARD M. MORABITO, SR. and MARY MORABITO
Plaintiffs ORDER v.
DONALENE NELSON, WAYNE NELSEN, D&W HOMEBUILDERS, INC., and DWN ASSET MANAGEMENT
Defendants
This case comes before the Court on Plaintiffs' Application for
Confirmation of Award pursuant to 14 M.R.S.A. §5937 and Defendants' Motion
for Modification and Correction of Award pursuant to 14 M.R.S.A. §5939.
BACKGROUND
On or about April 19, 2002, the Morabitos entered into a home
construction contract with the Defendants. Under the agreement, disputes were
to be submitted to binding arbitration.
A dispute arose concerning the construction of the Morabitos' residence.
The Morabitos alleged that the vinyl siding and roof shingles of the residence
were improperly installed, and that there were certain structural defects that
needed repair. 1 Attempts to informally settle the dispute failed, and therefore,
the matter went to binding arbitration.
1Specifically, the Morabitos alleged that the center girder in the garage was not to specifications, that new concrete footing was needed for a lally column, that 12-18 electrical wires needed to be relocated so as not to penetrate the new On January 22,2007, the arbitrator, Michael Dell'Olio, decided that the
vinyl siding and roof shingles were improperly installed, and therefore, ordered
the Defendants to pay to the Morabitos: (1) $456.24 for the defective vinyl
installation, (2) $7,930.00 for the defective roof installation, and (3) an additional
$875.00 "as damages relating to the roofing issue." The arbitrator did not decide
the issue concerning structural defects, noting, "this issue remains open and will
be determined when all papers have been submitted."
On February 21,2007, based on the arbitrator's findings, the Morabitos
filed a motion for confirmation of arbitration award pursuant to M.R.S.A. §5937.
The Defendants objected to this motion, arguing that it was premature to confirm
the award because the arbitrator did not decide the "structural defects" issue.
The court agreed, staying the motion for confirmation of arbitration award until
the arbitrator reached a decision on this issue. The matter did not go to
arbitration until January 22, 2008. On August 7,2008, the arbitrator issued his
dispute resolution report, concluding that there were structural integrity
problems with the Morabitos' residence. Further, he ordered that (1) Defendants
pay for the cost of repairing the Morabitos' residence in the amount of $27,500.00,
(2) all parties must sign off on the final work product of the repairs, (3)
Defendants pay the Morabitos $1,758.00 as damages for the structural defects,
and finally (4) Defendants pay the final arbitration fee of $1,060.00.
On August 25,2008, the Morabitos filed a second application for
confirmation of an award pursuant to 14 M.R.S.A. §5937. On September 9, 2008,
column, and that the "hump" in the kitchen's hardwood floor needed to be repaired.
2 the Defendants filed their motion for modification and correction of award
pursuant to 14 M.R.S.A. §5939.
In their motion for modification, the Defendants (1) request a conclusion
of law and of fact from the arbitrator on the issue of individual liability,
specifically on the issue of whether the corporate veil has been pierced in
accordance with Maine case law; (2) request the arbitrator to decide whether the
right to cure applies in this case; (3) request a finding of fact why Defendants'
expert report, prepared by Associated Design Partners, Inc., was not found
credible; (4) requests a finding of fact why Chase Custom Homes' estimate
concerning the cost to fix the structural integrity was deemed conclusive; and
finally, (5) a finding as to why a monetary award is proper given the fact that the
Morabitos maintain that this dispute has "nothing to do with money." The
Morabitos claim that the arbitration award speaks for itself on all of these issues.
DISCUSSION
Under 14 M.R.S.A. §5937, a court shall confirm an arbitration award
unless, within a certain time, "grounds are urged for vacating or modifying or
correcting the award." Under 14 M.R.S.A. §5935, "if an application to the court is
pending under sections 5937 to 5930/, on submission to the arbitrators under
2This is the case here, where Defendants have moved for a modification or correction of the award pursuant to Section 5939. This section provides:
1. Application. Upon application made within 90 days after delivery of a copy the award to the applicant, the court shall modify or correct the award where:
A. There was an evident miscalculation of figures or an evident mistake in the description of any person, thing or property referred to in the award;
3 such condition as the court may order, the arbitrators may modify or correct the
award on the grounds stated in section 5939, subsection 1, paragraphs A and C
or for the purposes of clarifying the award." (Emphasis added).
In order to confirm an award under 14 M.R.S.A. §5937, the award must be
"sufficiently clear and definite so that it is susceptible of enforcement and those
called upon to enforce it must not be misled or called upon to pay more than is
due." Lisbon School Committee v. Lisbon Educational Ass'n, 438 A.2d 239,245 (Me.
1981). Past Law Court decisions "demonstrate that the standard of 'clarity and
definiteness necessary for a court of law to confirm and enter judgment' requires
arbitration decisions to be unambiguous and enforceable by their terms." Hearst
Corp. v. Swiss Bank Corp., New York Branch, 584 A.2d 655,659 (Me. 1990)(quoting
Sargent v. Town ofMillinocket, 478 A.2d 683, 686 (Me. 1984)).
For example, in Sargent, the Law Court held that it was error for the trial
court to confirm an arbitration award that failed to "state the party against whom
each individual claim or award was made, nor [did] it state the interrelationship,
if any, of the individual awards." 478 A.2d at 685. Based on this failure, the Law
Court held that the court should have submitted the award to the arbitrators for
clarification. Id. at 687.
Here, the Dispute Resolution Award prepared by Mr. Dell'Olio outlines
the amount of money owed to the Morabitos by the Defendants. However, the
award does not specifically state which Defendant, referred to by Mr. Dell'Olio
B. The arbitrators have awarded upon a matter not submitted to them and the award may be corrected without affecting the merits of the decision upon the issues submitted; or
C. The award is imperfect in a matter of form, not affecting the merits of the controversy.
4 collectively as the "Respondents," is responsible for what portion of the amount
owed to the Morabitos. As was the case in Sargent, the arbitrator's failure to
explicitly state the party against whom each individual award was made makes
the award ambiguous. It is especially ambiguous here, where the arbitrator
referred to Wayne and Donalene Nelson, D&W Homebuilders, and DWN Asset
Management collectively as "Respondents" even though the original home
construction contract, which was signed by Wayne Nelson and identifies D&W
Builders, Inc. as party to the contract, is devoid of any mention of Donalene
Nelson or DWN Asset Management. As such, the award cannot be confirmed,
and the matter should be resubmitted to the arbitrator for the sole purpose of
delineating what the award is against each of the parties.
The other issues raised by the Defendants do not go to the award's
"definitiveness or clarity" and therefore, do not need to be clarified for the award
to be unambiguous and enforceable. Moreover, these issues do not fall under any
of the grounds for modification or correction under Section 5939(1).
Therefore, the entry is:
Plaintiffs' motion for confirmation of arbitration award is DENIED.
Defendants' motion for modification and correction is GRANTED. This matter shall be submitted to the arbitrator for clarification on the issue of what the award is against each of the named parties.
The clerk shall incorporate this Order into the doc pursuant to M.R. Civ. P. 79(a).
DATED: ~ (qlttJ o1
5 IF COURTS and County Box 287 line 04112-0287
RAY PALLAS ESQ 425 MAIN STREET WESTBROOK ME 04092
F COURTS :md County 30x 287 ine 04112-0287
FRANK CHOWDRY ESQ PO BOX 4510 PORTLAND ME 04112 STATE OF MAINE CUMBERLAND, ss.
RICHARD M. MORABITO, SR. ZDOq jUN ! CJ A II: 51 and MARY E. MORABITO
Plaintiffs
v. ORDER
DONALENE NELSEN, WAYNE NELSEN, D&W HOMEBUILDERS, INC., and DWN ASSET MANAGEMENT
This case comes before the Court on Plaintiff's second Application for
Confirmation of Award, made pursuant to 14 M.R.S.A. § 5937.
This case involves a home construction dispute. The Morabitos, alleging
several defects in the Defendants' construction of their home, sought to have the
dispute settled by arbitration. On January 22,2007, the arbitrator, Michael
Dell'Olio, finding that there were several defects with the construction of the
home, decided in the Plaintiffs' favor on the issues submitted to arbitration.
However, at this time, Mr. Dell'Olio failed to decide an issue concerning certain
structural defects, noting, "this issue remains open and will be determined when
all papers have been submitted."
On February 21,2007, based on the arbitrator's findings, the Morabitos
filed a motion for confirmation of arbitration award pursuant to M.R.S.A. § 5937.
This Court stayed the motion for confirmation of arbitration award until the
arbitrator reached a decision on the structural defects issue. On August 7,2008, the arbitrator concluded in his dispute resolution
report that there were structural integrity problems with the Morabitos'
residence. From this, he ordered that (1) Defendants pay for the cost of repairing
the Morabitos' residence in the amount of $27,500.00, (2) all parties must sign off
on the final work product of the repairs, (3) Defendants pay the Morabitos
$1,758.00 as damages for the structural defects, and finally (4) Defendants pay
the final arbitration fee of $1,060.00.
On August 25,2008, the Morabitos filed an application for confirmation of
an award pursuant to 14 M.R.S.A. §5937. On January 6, 2009, this Court
confirmed all but one aspect of the arbitration award. However, based on the fact
that the award did not fully detail each of the Defendants' individual liability,
this Court sent the matter back to Mr. Dell'Olio so that this aspect of the award
could be clarified.
On January 20, 2009, Mr. Dell'Olio filed a clarification with the court.
There, it was explained that,
DWN Asset Management Inc., [and] Donalene Nelsen conveyed to Richard Morabito and Mary Morabito the track of land as a package deal for the construction of a home. D&W Builders, entered into an agreement on April 19, 2002 with Richard M. Morabito and Mary Morabito, for a home construction package, which included the land. Wayne Nelson signed the contract individually. Wayne Nelsen, as the record indicates, signed personally on various agreements and checks indicating personal liability.
Based on these facts, the arbitrator found that Defendants "are under a common
ownership, have pervasive control of the entities, [and] there was confusion as to
the intermingling of business activities." Coupling these facts with the
conclusion that it would be unjust and inequitable to treat the Defendants as
2 separate entities, Mr. Dell'Olio decided that the corporate veil had been pierced 1,
and that all named Defendants were jointly and severally liable to the Morabitos
in the amount of $29,258.00 for the defective work done in constructing the
residence?
On March 19,2009, the Morabitos filed the present application for
confirmation of an arbitration award.
In order to confirm an award under 14 M.R.S.A. § 3937, the award must be
"sufficiently clear and definite so that it is susceptible of enforcement and those
called upon to enforce it must not be misled or called upon to pay more than is
due." Lisbon School Committee v. Lisbon Educational Ass'n, 438 A.2d 239, 245 (Me.
1981). Past Law Court decisions "demonstrate that the standard of 'clarity and
definiteness necessary for a court of law to confirm and enter judgment' requires
arbitration decisions to be unambiguous and enforceable by their terms." Hearst
Corp. v. Swiss Bank Corp., New York Branch, 584 A.2d 655,659 (Me. 1990)(quoting
Sargent v. Town of Millinocket, 478 A.2d 683, 686 (Me. 1984)). Moreover, for a
court to confirm an arbitration award, the award must "state the party against
whom each individual claim or award was made."
In its January 6, 2009 Order, this Court confirmed the majority of the
arbitration award, but sent the matter back to Mr. Dell'Olio so that he could
clearly delineate each Defendants' individual liability. The arbitrator's
I A corporate veil is pierced "if a plaintiff establishes that: "( 1) the defendant abused the privilege of a separate corporate identity; and (2) an unjust or inequitable result would occur if the court recognized the separate corporate existence." State v. Weinschenk,2005 ME 28, ,-r 19, 868 A.2d 200, 207. 2 This amount came from the original dispute resolution report, issued on August 7, 2008, and has already been confirmed by this Court in its January 6, 2009 Order.
3 clarification, issued on January 20, 2009, clearly explains that, based on record
evidence, the corporate veil had been pieced and that the Defendants are jointly
and severally liable to the Morabitos for the full arbitration award plus the
arbitration fee. As such, as this clearly states the party against whom each claim
or award was made, the arbitration award should be confirmed.
Plaintiff's Motion to Confirm Arbitration Award, made pursuant to 14 M.R.S.A. §5937, is GRANTED.
The clerk shall incorporate this Order into the docket by reference pursuant to M.R. Civ. P. 79(a).
4 06/19/2009 MAINE JUDICIAL INFORMATION SYSTEM gmerritt CUMBERLAND COUNTY SUPERIOR COURT mjxxi013 PAGE A - ATTORNEY BY CASE VIEW RICHARD MMORABITO SR VS DONNALENE NELSEN UTN:AOCSsr -2006-0054014 CASE #:PORSC-CV-2006-00280
SEL VD REPRESENTATION TYPE DATE 01 0000003706 ATTORNEY:CHOWDRY, FRANK K N ADDR:10 FREE STREET PO BOX 4510 PORTLAND ME 04112 F FOR:DONNALENE NELSEN DEF RTND 02/22/2007 F FOR:WAYNE NELSEN DEF RTND 02/22/2007 F FOR:D&W HOME BUILDERS, INC. DEF RTND 02/22/2007
02 0000001594 ATTORNEY:PALLAS, RAY ADDR:425 MAIN STREET WESTBROOK ME 04092 F FOR:RICHARD MMORABITO SR PL RTND 07/30/2007
Enter Option: A=Add, B+Sel=Browse, M=More, R+Sel=RltnEdit:
Select the EXIT KEY for page selection line.