Morabito v. Nelsen
Opinion
STATE OF MAINE SUPERIOR COURT , I
CUMBERLAND, ss. .' CIVIL ACTION
E OCKE} NO. C;V-,06-280 \A' CL.{ r~ I - ! Ij:.....,,.~-,,'Ci )./'~ . "\
"'il' j ,) ,
i
,I
"
RICHARD M. MORABITO, SR. and MARY MORABITO
Plaintiffs
ORDER
v.
DONALENE NELSON, WAYNE NELSEN, D&W HOMEBUILDERS, INC., and DWN ASSET MANAGEMENT
Defendants
This case comes before the Court on Plaintiffs' Application for Confirmation of Award pursuant to 14 M.R.S.A. §5937 and Defendants' Motion for Modification and Correction of Award pursuant to 14 M.R.S.A. §5939.
BACKGROUND
On or about April 19, 2002, the Morabitos entered into a home construction contract with the Defendants. Under the agreement, disputes were to be submitted to binding arbitration.
A dispute arose concerning the construction of the Morabitos' residence.
The Morabitos alleged that the vinyl siding and roof shingles of the residence were improperly installed, and that there were certain structural defects that needed repair. 1 Attempts to informally settle the dispute failed, and therefore, the matter went to binding arbitration.
1Specifically, the Morabitos alleged that the center girder in the garage was not to specifications, that new concrete footing was needed for a lally column, that 12-18 electrical wires needed to be relocated so as not to penetrate the new
On January 22,2007, the arbitrator, Michael Dell'Olio, decided that the vinyl siding and roof shingles were improperly installed, and therefore, ordered the Defendants to pay to the Morabitos: (1) $456.24 for the defective vinyl installation, (2) $7,930.00 for the defective roof installation, and (3) an additional $875.00 "as damages relating to the roofing issue." The arbitrator did not decide the issue concerning structural defects, noting, "this issue remains open and will be determined when all papers have been submitted."
On February 21,2007, based on the arbitrator's findings, the Morabitos filed a motion for confirmation of arbitration award pursuant to M.R.S.A. §5937. The Defendants objected to this motion, arguing that it was premature to confirm the award because the arbitrator did not decide the "structural defects" issue. The court agreed, staying the motion for confirmation of arbitration award until the arbitrator reached a decision on this issue. The matter did not go to arbitration until January 22, 2008. On August 7,2008, the arbitrator issued his dispute resolution report, concluding that there were structural integrity problems with the Morabitos' residence. Further, he ordered that (1) Defendants pay for the cost of repairing the Morabitos' residence in the amount of $27,500.00, (2) all parties must sign off on the final work product of the repairs, (3) Defendants pay the Morabitos $1,758.00 as damages for the structural defects, and finally (4) Defendants pay the final arbitration fee of $1,060.00.
On August 25,2008, the Morabitos filed a second application for confirmation of an award pursuant to 14 M.R.S.A. §5937. On September 9, 2008,
column, and that the "hump" in the kitchen's hardwood floor needed to be repaired.
the Defendants filed their motion for modification and correction of award pursuant to 14 M.R.S.A. §5939.
In their motion for modification, the Defendants (1) request a conclusion of law and of fact from the arbitrator on the issue of individual liability, specifically on the issue of whether the corporate veil has been pierced in accordance with Maine case law; (2) request the arbitrator to decide whether the right to cure applies in this case; (3) request a finding of fact why Defendants' expert report, prepared by Associated Design Partners, Inc., was not found credible; (4) requests a finding of fact why Chase Custom Homes' estimate concerning the cost to fix the structural integrity was deemed conclusive; and finally, (5) a finding as to why a monetary award is proper given the fact that the Morabitos maintain that this dispute has "nothing to do with money." The Morabitos claim that the arbitration award speaks for itself on all of these issues.
DISCUSSION
Under 14 M.R.S.A. §5937, a court shall confirm an arbitration award unless, within a certain time, "grounds are urged for vacating or modifying or correcting the award." Under 14 M.R.S.A. §5935, "if an application to the court is pending under sections 5937 to 5930/, on submission to the arbitrators under
2This is the case here, where Defendants have moved for a modification or correction of the award pursuant to Section 5939. This section provides:
1. Application. Upon application made within 90 days after delivery of a copy the award to the applicant, the court shall modify or correct the award where:
A. There was an evident miscalculation of figures or an evident mistake in the description of any person, thing or property referred to in the award;
such condition as the court may order, the arbitrators may modify or correct the award on the grounds stated in section 5939, subsection 1, paragraphs A and C or for the purposes of clarifying the award." (Emphasis added).
In order to confirm an award under 14 M.R.S.A. §5937, the award must be "sufficiently clear and definite so that it is susceptible of enforcement and those called upon to enforce it must not be misled or called upon to pay more than is due." Lisbon School Committee v. Lisbon Educational Ass'n, 438 A.2d 239,245 (Me. 1981). Past Law Court decisions "demonstrate that the standard of 'clarity and definiteness necessary for a court of law to confirm and enter judgment' requires arbitration decisions to be unambiguous and enforceable by their terms." Hearst Corp. v. Swiss Bank Corp., New York Branch, 584 A.2d 655,659 (Me. 1990)(quoting Sargent v. Town ofMillinocket, 478 A.2d 683, 686 (Me. 1984)).
For example, in Sargent, the Law Court held that it was error for the trial court to confirm an arbitration award that failed to "state the party against whom each individual claim or award was made, nor [did] it state the interrelationship, if any, of the individual awards." 478 A.2d at 685. Based on this failure, the Law Court held that the court should have submitted the award to the arbitrators for clarification. Id. at 687.
Here, the Dispute Resolution Award prepared by Mr. Dell'Olio outlines the amount of money owed to the Morabitos by the Defendants. However, the award does not specifically state which Defendant, referred to by Mr. Dell'Olio
B. The arbitrators have awarded upon a matter not submitted to them and the award may be corrected without affecting the merits of the decision upon the issues submitted; or
C. The award is imperfect in a matter of form, not affecting the merits of the controversy.
collectively as the "Respondents," is responsible for what portion of the amount owed to the Morabitos. As was the case in Sargent, the arbitrator's failure to explicitly state the party against whom each individual award was made makes the award ambiguous. It is especially ambiguous here, where the arbitrator referred to Wayne and Donalene Nelson, D&W Homebuilders, and DWN Asset Management collectively as "Respondents" even though the original home construction contract, which was signed by Wayne Nelson and identifies D&W Builders, Inc. as party to the contract, is devoid of any mention of Donalene Nelson or DWN Asset Management. As such, the award cannot be confirmed, and the matter should be resubmitted to the arbitrator for the sole purpose of delineating what the award is against each of the parties.
The other issues raised by the Defendants do not go to the award's "definitiveness or clarity" and therefore, do not need to be clarified for the award to be unambiguous and enforceable. Moreover, these issues do not fall under any of the grounds for modification or correction under Section 5939(1). Therefore, the entry is:
Plaintiffs' motion for confirmation of arbitration award is DENIED.
Free access — add to your briefcase to read the full text and ask questions with AI
Morabito v. Nelsen (Morabito v. Nelsen) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.