Morabito v. Nelsen

CourtSuperior Court of Maine
DecidedJune 19, 2009
DocketCUMcv-06-280
StatusUnpublished

This text of Morabito v. Nelsen (Morabito v. Nelsen) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morabito v. Nelsen, (Me. Super. Ct. 2009).

Opinion

STATE OF MAINE SUPERIOR COURT , I CUMBERLAND, ss. .' CIVIL ACTION

E OCKE} NO. C;V-,06-280 \A' CL.{ r~ I - ! Ij:.....,,.~-,,'Ci )./'~ . "\ "'il' j ,) , i ,I

" RICHARD M. MORABITO, SR. and MARY MORABITO

Plaintiffs ORDER v.

DONALENE NELSON, WAYNE NELSEN, D&W HOMEBUILDERS, INC., and DWN ASSET MANAGEMENT

Defendants

This case comes before the Court on Plaintiffs' Application for

Confirmation of Award pursuant to 14 M.R.S.A. §5937 and Defendants' Motion

for Modification and Correction of Award pursuant to 14 M.R.S.A. §5939.

BACKGROUND

On or about April 19, 2002, the Morabitos entered into a home

construction contract with the Defendants. Under the agreement, disputes were

to be submitted to binding arbitration.

A dispute arose concerning the construction of the Morabitos' residence.

The Morabitos alleged that the vinyl siding and roof shingles of the residence

were improperly installed, and that there were certain structural defects that

needed repair. 1 Attempts to informally settle the dispute failed, and therefore,

the matter went to binding arbitration.

1Specifically, the Morabitos alleged that the center girder in the garage was not to specifications, that new concrete footing was needed for a lally column, that 12-18 electrical wires needed to be relocated so as not to penetrate the new On January 22,2007, the arbitrator, Michael Dell'Olio, decided that the

vinyl siding and roof shingles were improperly installed, and therefore, ordered

the Defendants to pay to the Morabitos: (1) $456.24 for the defective vinyl

installation, (2) $7,930.00 for the defective roof installation, and (3) an additional

$875.00 "as damages relating to the roofing issue." The arbitrator did not decide

the issue concerning structural defects, noting, "this issue remains open and will

be determined when all papers have been submitted."

On February 21,2007, based on the arbitrator's findings, the Morabitos

filed a motion for confirmation of arbitration award pursuant to M.R.S.A. §5937.

The Defendants objected to this motion, arguing that it was premature to confirm

the award because the arbitrator did not decide the "structural defects" issue.

The court agreed, staying the motion for confirmation of arbitration award until

the arbitrator reached a decision on this issue. The matter did not go to

arbitration until January 22, 2008. On August 7,2008, the arbitrator issued his

dispute resolution report, concluding that there were structural integrity

problems with the Morabitos' residence. Further, he ordered that (1) Defendants

pay for the cost of repairing the Morabitos' residence in the amount of $27,500.00,

(2) all parties must sign off on the final work product of the repairs, (3)

Defendants pay the Morabitos $1,758.00 as damages for the structural defects,

and finally (4) Defendants pay the final arbitration fee of $1,060.00.

On August 25,2008, the Morabitos filed a second application for

confirmation of an award pursuant to 14 M.R.S.A. §5937. On September 9, 2008,

column, and that the "hump" in the kitchen's hardwood floor needed to be repaired.

2 the Defendants filed their motion for modification and correction of award

pursuant to 14 M.R.S.A. §5939.

In their motion for modification, the Defendants (1) request a conclusion

of law and of fact from the arbitrator on the issue of individual liability,

specifically on the issue of whether the corporate veil has been pierced in

accordance with Maine case law; (2) request the arbitrator to decide whether the

right to cure applies in this case; (3) request a finding of fact why Defendants'

expert report, prepared by Associated Design Partners, Inc., was not found

credible; (4) requests a finding of fact why Chase Custom Homes' estimate

concerning the cost to fix the structural integrity was deemed conclusive; and

finally, (5) a finding as to why a monetary award is proper given the fact that the

Morabitos maintain that this dispute has "nothing to do with money." The

Morabitos claim that the arbitration award speaks for itself on all of these issues.

DISCUSSION

Under 14 M.R.S.A. §5937, a court shall confirm an arbitration award

unless, within a certain time, "grounds are urged for vacating or modifying or

correcting the award." Under 14 M.R.S.A. §5935, "if an application to the court is

pending under sections 5937 to 5930/, on submission to the arbitrators under

2This is the case here, where Defendants have moved for a modification or correction of the award pursuant to Section 5939. This section provides:

1. Application. Upon application made within 90 days after delivery of a copy the award to the applicant, the court shall modify or correct the award where:

A. There was an evident miscalculation of figures or an evident mistake in the description of any person, thing or property referred to in the award;

3 such condition as the court may order, the arbitrators may modify or correct the

award on the grounds stated in section 5939, subsection 1, paragraphs A and C

or for the purposes of clarifying the award." (Emphasis added).

In order to confirm an award under 14 M.R.S.A. §5937, the award must be

"sufficiently clear and definite so that it is susceptible of enforcement and those

called upon to enforce it must not be misled or called upon to pay more than is

due." Lisbon School Committee v. Lisbon Educational Ass'n, 438 A.2d 239,245 (Me.

1981). Past Law Court decisions "demonstrate that the standard of 'clarity and

definiteness necessary for a court of law to confirm and enter judgment' requires

arbitration decisions to be unambiguous and enforceable by their terms." Hearst

Corp. v. Swiss Bank Corp., New York Branch, 584 A.2d 655,659 (Me. 1990)(quoting

Sargent v. Town ofMillinocket, 478 A.2d 683, 686 (Me. 1984)).

For example, in Sargent, the Law Court held that it was error for the trial

court to confirm an arbitration award that failed to "state the party against whom

each individual claim or award was made, nor [did] it state the interrelationship,

if any, of the individual awards." 478 A.2d at 685. Based on this failure, the Law

Court held that the court should have submitted the award to the arbitrators for

clarification. Id. at 687.

Here, the Dispute Resolution Award prepared by Mr. Dell'Olio outlines

the amount of money owed to the Morabitos by the Defendants. However, the

award does not specifically state which Defendant, referred to by Mr. Dell'Olio

B. The arbitrators have awarded upon a matter not submitted to them and the award may be corrected without affecting the merits of the decision upon the issues submitted; or

C. The award is imperfect in a matter of form, not affecting the merits of the controversy.

4 collectively as the "Respondents," is responsible for what portion of the amount

owed to the Morabitos. As was the case in Sargent, the arbitrator's failure to

explicitly state the party against whom each individual award was made makes

the award ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon School Committee v. Lisbon Education Ass'n
438 A.2d 239 (Supreme Judicial Court of Maine, 1981)
Hearst Corp. v. Swiss Bank Corp., New York Branch
584 A.2d 655 (Supreme Judicial Court of Maine, 1991)
H.E. Sargent, Inc. v. Town of Millinocket
478 A.2d 683 (Supreme Judicial Court of Maine, 1984)
State v. Weinschenk
2005 ME 28 (Supreme Judicial Court of Maine, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Morabito v. Nelsen, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morabito-v-nelsen-mesuperct-2009.