H.E. Sargent, Inc. v. Town of Millinocket

478 A.2d 683, 1984 Me. LEXIS 737
Supreme Judicial Court of Maine·Decided July 10, 1984·Published·Cited by 9 cases

Opinion

VIOLETTE, Justice.

H.E. Sargent, Inc. (“Sargent”) appeals from a judgment entered by the Superior Court, Penobscot County, confirming an arbitration award pursuant to 14 M.R.S.A. § 5937 (1980). The award was made by a panel of arbitrators of the American Arbitration Association and was intended to resolve several claims arising out of the construction of a wastewater treatment plant in Millinocket, Maine. Because we find the award incomplete and ambiguous, we hold that the Superior Court erred in confirming the award. Accordingly, we vacate the judgment and remand to the Superior Court with directions to submit the award to the arbitration panel for clarification.

In July 1976, Sargent entered into a construction contract with the Town of Milli-nocket (“the Town”) for construction of a municipal wastewater treatment plant. Sargent subcontracted some of the work, including the installation of the plant’s aeration system, to Salter Corporation (“Salter”). Both Sargent’s contract with the Town and its contract with Salter contain a clause that requires “any controversy or claim arising out of or relating to [the contracts]” to be “settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.” Each contract also provides that judgment upon any award made by the arbitration panel may be entered in any court having jurisdiction thereof.

During construction a dispute arose between Sargent and the Town over the terms of the primary construction contract. A dispute also arose between Salter and Sargent over the terms of the subcontract. Acting pursuant to the Construction Industry Arbitration Rules, Sargent submitted its claims against the Town in a Demand for Arbitration dated June 25, 1979. Sargent’s demand states that it incurred additional costs, loss of profits and a claim by Salter, all caused, it claims, by changes in the design of the project as well as by delays created by the action or inaction of the Town or the Town’s agent. Sargent sought $809,706.00 in damages. The Town answered Sargent’s demand and asserted a counterclaim for $64,400.00 in liquidated damages under the contract. The Town also asserted a claim for the $100,000.00 it claimed to have erroneously paid to Sargent for corrective work that was occasioned by the faulty construction work of Sargent or its subcontractors.

Salter submitted its claim against Sargent in a Demand for Arbitration dated March 26, 1980. Salter sought $205,262.91 in damages, claiming it was required to perform extra work because of delays and design changes. Salter also requested that its claim against Sargent be consolidated with Sargent’s claim against the Town and the Town’s counterclaim against Sargent since all claims involved “common issues of *685 fact and law.” The panel agreed to hear all the claims in a consolidated proceeding.

On April 4, 1980, legal counsel for the Town, Sargent and Salter attended a pre-hearing conference with the arbitration panel. The panel issued a Report of Pre-hearing Conference dated April 7, 1980, in which the claims of the parties are detailed. As is pertinent to the present appeal, the report reveals that Sargent’s $809,706.00 claim against the Town included the $205,-262.91 claimed by Salter against Sargent. The report also states that upon request of counsel for Salter and without objection from the other parties, the panel agreed “to enter separate awards at the time of decision, stating separately the award of Salter against Sargent, if any, and the awards of Sargent against the Town of Millinocket and the Town of Millinocket against Sargent, if any.” Finally, the report notes that the parties agreed that any pre-trial memoranda filed by the parties together with the Report of Pre-hearing Conference constituted the arbitration submission agreement.

The hearings on the arbitration demands lasted for more than 30 days spanning a period of nearly two years. On September 28, 1982, the arbitration panel issued its award. The panel made the following awards to the parties:

To Salter $63,677.79
To Sargent $119,481.66
To The Town $60,000.00

The award, however, does not follow the simplistic form reproduced here. Instead, the award comprises four and one-half typewritten pages and separately lists the various claims advanced by each party and the corresponding award, if any, granted by the arbitration panel on each claim. The award lists seven separate claims advanced by Salter, six separate claims advanced by Sargent and four separate claims advanced by the Town. The panel conferred an award on four of Salter’s claims, on four of Sargent’s claims and on one of the Town’s claims. Nowhere, however, does the award state the party against whom each individual claim or award was made, nor does it state the interrelationship, if any, of the individual awards. Most importantly, for the proper resolution of all claims advanced by the parties, the award does not state whether the panel found Sargent directly liable for the $63,677.69 awarded to Salter or whether, as would be expected from the terms of the Pre-hearing Report, Sargent was indemnified by the Town against the claims made by, and the award made to Salter. 1 Nevertheless, after various lengthy procedural maneuverings by all parties to the arbitration culminating in Sargent’s motion for summary judgment, which the court treated as a motion to confirm the arbitration award pursuant to 14 M.R.S.A. § 5937 (1980), 2 the Superior Court, by order filed July 14, 1983, confirmed the award and entered judgment as follows:

It is hereby ORDERED that the arbitration award # 1110-0145-79, which was entered on September 28, 1982 is confirmed. Judgment is entered for Salter Corporation and against H.E. Sargent in the amount of sixty-three thousand six *686 hundred seventy-seven dollars and seventy-nine cents ($63,677.79). Judgment is also entered for H.E. Sargent against Town of Millinoeket on its claim in the amount of one hundred nineteen thousand four hundred eighty-one dollars and sixty-six cents ($119,481.66). Judgment is also entered for the Town of Millinock-et and against H.E. Sargent in the amount of sixty-thousand dollars and no cents ($60,000.00).

The entry of a judgment pursuant to 14 M.R.S.A. § 5940 (1980), upon confirmation of an award under section 5937, serves the obvious purpose of allowing court enforcement of the terms of the award made by the arbitration panel. See Maine Central Railroad v. Bangor and Aroostook Railroad, 395 A.2d 1107, 1121 (Me.1978). The judgment entered by the court in the present case, however, does not serve such a purpose because the court added to the arbitration award the names of the parties that it decided were responsible for the individual awards made by the arbitrators. 3 In so doing, the court substituted its judgment for that of the arbitration panel and effectively denied the parties the right to have their disputes settled by the arbitrators, not the Superior Court. Lisbon School Committee v. Lisbon Education Ass’n,

Free access — add to your briefcase to read the full text and ask questions with AI

H.E. Sargent, Inc. v. Town of Millinocket, 478 A.2d 683, 1984 Me. LEXIS 737 (Me. 1984).

478 A.2d 683 (H.E. Sargent, Inc. v. Town of Millinocket) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Morabito v. Nelsen
Maine Superior, 2009
Beal v. Allstate Ins. Co.
Maine Superior, 2004
General Accident Insurance Co. of America v. MSL Enterprises, Inc.
547 S.E.2d 97 (Court of Appeals of North Carolina, 2001)
Pelletier & Flanagan, Inc. v. Maine Court Facilities Authority
673 A.2d 213 (Supreme Judicial Court of Maine, 1996)
Mausbach v. Lemke
866 P.2d 1146 (Nevada Supreme Court, 1994)
Hearst Corp. v. Swiss Bank Corp., New York Branch
584 A.2d 655 (Supreme Judicial Court of Maine, 1991)