Moore v. October Corp.

CourtSuperior Court of Maine
DecidedOctober 1, 2004
DocketLINcv-02-045
StatusUnpublished

This text of Moore v. October Corp. (Moore v. October Corp.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore v. October Corp., (Me. Super. Ct. 2004).

Opinion

STATE OF MAINE SUPERIOR COURT Lin, B CIVIL ACTION LINCOLN, ss. “Oe ete, DOCKET NO. CV-02-045 “MY Dye LIN I Spe

MARTIN E. MOORE and ‘Oy Op COASTAL DESIGNERS Hop, ty ; AND CONSULTANTS, INC,, Voy. Plaintiffs v. DECISION AND ORDER OCTOBER CORPORATION and BOULOS PROPERTY MANAGEMENT, Defendants bu G IG I. Introduction. OCT 20 ayy

Pending before the court is the defendants’ motion for partial summary judgment which seeks disposition in their favor on count I of the plaintiffs’ second amended complaint. For their part, the plaintiffs oppose this motion but assert that because the contract at issue is unambiguous and because the defendants breached its terms, summary judgment ought to be entered for the plaintiffs on this count. Thus, each set of parties ask the court to resolve count I in its respective favor via the pending

motion.’ By this decision and order, the court will endeavor to address these competing

requests. II. Facts.

Based on the parties’ submissions in support of, or in opposition to, the pending motion, the following facts or disputes of fact, may be found in the record.

October Corporation (October) purchased the former Pineland Center from the

State in 2000 and decided to develop a dairy farm there which would include a dairy

* Counts I and III which allege, respectively, Unjust Enrichment and Quantum Meruit, are not the subject of this motion and, therefore will survive this motion and, apparently, be in order for trial. barn. It engaged Coastal Designers and Consultants (“CDC”), of whom plaintiff Martin

E. Moore (Moore) is the principal, to design the dairy barn. On July 21, 2001, the

defendants signed a contract, which is the subject of the dispute in this case, by which

CDC was to provide the design services for the dairy barn.

The contract, entitled “Standard Proposal Agreement for Construction

Drawings” (“Agreement”) was drafted by CDC and contained the following list of

services it would provide:

elevations

Site visit - Master planning session On site review of revised preliminary master plan, floor plans &

On site review meeting of revised preliminary plans

On site review first draft of construction drawings & specifications On site review proof set of construction dwes & specifications

On site deliver & review construction drawings & specifications for contractor bid

Assistance in selection of all finishing materials

Assistance in selection of suppliers

Assistance in selection of contractors

Consultation during construction via telephone, fax & Federal Express Contractor bid review meeting

Pre construction meeting w/G.C.

The contract also included the following relevant text under its section entitled

“Standard Policy”:

A design fee of 10% will be charged based on the project construction cost excluding landscaping/bldg. permits fees

In the event that the Owners stop this project for any reason, the Owners will only be responsible for the percentage of the drawings & specifications completed to date when we received notice to

stop the project.

The design fee will be charged for all portions of the project excluding landscaping & building permit.

Finally, the contract contained the following language as the payment schedule

for the services that CDC would provide October: PAYMENT SCHEDULE

#1. Retainer at start o work $ 7,500.00 #2. Progress payment due & appreciated at preliminary drawing review meeting [Preliminary site plan layout —

floor plan & elevations] $15,500.00 #3. Progress payment due & appreciated at first draft

construction drawing review meeting $45,000.00 #4. Progress payment due & appreciated at the proof set of

construction dwg & specification review meeting $40,000.00 #5. Payment due & appreciated when bid documents are :

delivered [Dwgs. & specifications] $42,000.00 #6. Balance due [if any] balance of 10% design fee when

contractor bid is obtained $ Pending #7, Final payment due [if any] 10% design fee of change orders $ Pending

The numbers cited above total $150,000 through step #5 in the schedule, namely when bid documents are delivered to the owner. The parties dispute the significance of this figure. The defendants say it represents 10%, CDC’s fee, of a pre-contract budget estimate of $1,500,000 which would allow CDC to be paid $150,000 if October did not complete the project. DSMF, { 24. Moore disagrees with this interpretation, and asserts that his fee was to be 10% of the cost of construction, but agrees that the figure of $1.5 million came from a discussion with individuals from October or Boulos Property Management (Boulos) as to the possible scope of the project. PRSME, { 20. He also agrees that the Agreement “suggests that a $1.5 million dollar project would be the minimum project cost.” Id. Moore also testified that when he filled out the payment schedule, he used the 10% figure to calculate the payment schedule and that that 10% was applied against a $1.5 million building figure which he had discussed with the defendants. DRSME, q 20.

Thereafter, CDC received payments #1 through #4 under the Agreement’s payment schedule which totaled $108,000. It also received $23,692.50 for work outside

the contract for the dairy processing plant. On November 5, 2001, CDC provided the defendants with a set of design development drawings which the defendants characterize as “preliminary drawings,” DSMF, { 30, but which Moore refers to as “the first draft of construction drawings.” PRSME, { 30. On this date, CDC submitted an invoice for progress payment #3 in the amount of $45,000. Apparently it was paid.

The defendants say they then wished to get a budget estimate of the cost of constructing the dairy barn as it was depicted on the November 5, 2001, plans so gave these “preliminary” plans to Pochebit, a construction company, to get this estimate for constructing the dairy barn. Pochebit responded in December of 2001 with an estimated budget price of over $2.8 million which was more than the defendants contemplated spending.

In reaching this figure, Michael White of Pochebit testified that he understood his firm’s task was to “get a preliminary budget estimate for the project;” that it was “real preliminary ... a high and a low type of estimate... it was a range.”” DSMF, { 43.

The defendants further say that, based upon the costs given to them by Pochebit, they decided to look at various options, including “value engineering” for the dairy barn, to see if cost reductions could be made so that a variation of the November 5, 2001 plans could be constructed. DSMF, J 44. The plaintiffs dispute this and assert that CDC provided Boulos with “90% complete” drawings on or about December 14, 2001,

which, it believes, were given to Pochebit and used to discuss “value engineering.”

* The plaintiffs do not dispute the defendants’ assertion at paragraph 41 of their statement of material facts that the latter gave the November 5, 2001 plans to Pochebit early that month and that Pochebit continued to work on numbers in December. PRSMF, § 41.

It is unknown if there are two sets of plans, one that was submitted to Pochebit in November, 2001, the “preliminary” or “draft” plan, and a second “90% complete” plan that was developed later and given to Pochebit on or about December 14, 2001. See DSMF, { 41, PRSMF, {{ 40, 42(b), 44; DRSME, 44. The defendants deny that there was a second set of plans and assert that the only set given to Pochebit was dated November 5, 2001.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loyal Erectors, Inc. v. Hamilton & Son, Inc.
312 A.2d 748 (Supreme Judicial Court of Maine, 1973)
Acadia Insurance Co. v. Buck Construction Co.
2000 ME 154 (Supreme Judicial Court of Maine, 2000)
Searles v. Trustees of St. Joseph's College
695 A.2d 1206 (Supreme Judicial Court of Maine, 1997)
American Protection Insurance v. Acadia Insurance Co.
2003 ME 6 (Supreme Judicial Court of Maine, 2003)
Portland Valve, Inc. v. Rockwood Systems Corp.
460 A.2d 1383 (Supreme Judicial Court of Maine, 1983)
Fay, Spofford & Thorndike, Inc. v. Massachusetts Port Authority
387 N.E.2d 206 (Massachusetts Appeals Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Moore v. October Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-v-october-corp-mesuperct-2004.