Moore v. Gibbs Construction

Court of Appeals for the Fifth Circuit·Decided March 25, 2004·No. 95-60096·Unpublished

Opinion

UNITED STATES COURT OF APPEALS For the Fifth Circuit

No. 95-60096

LEWIS MOORE, United States of America for the use of d/b/a Lewis Moore Painting,

Plaintiff-Appellant,

VERSUS

GIBBS CONSTRUCTION COMPANY, INC., ET AL., Defendants-Appellees.

Appeal from the United States District Court For the Southern District of Mississippi (1:93-CV-491-RR)

February 23, 1996

Before GARWOOD, EMILIO M. GARZA, and DeMOSS, Circuit Judges.

PER CURIAM:* Plaintiff Lewis Moore (Moore) appeals from final judgment entered sua sponte prior to trial on the basis of arguments presented in the parties' cross-motions to limit evidence. We vacate and remand to the district court for further proceedings.

*

Pursuant to Local Rule 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in Local Rule 47.5.4.

BACKGROUND

Defendant Gibbs Construction Company (Gibbs) contracted with the United States to repair and renovate the interior of the Tyler House apartments on Kessler Air Force Base in Biloxi, Mississippi. As required by law, Gibbs arranged for a bond as surety for payment of claims against Gibbs. The payment bond was issued by co- defendant Fidelity & Deposit Company of Maryland (Fidelity).1 In November 1991, Gibbs subcontracted with Moore to paint and install wall coverings inside the Tyler House.

After Moore commenced performance, it became apparent that the existing surface on the interior doors and door frames in the Tyler House would not bond with the paint called for in Moore's subcontract with Gibbs. Moore delivered a sample of the door surface to the paint manufacturer and it was examined by a chemist, who specified an extensive surface preparation procedure for getting the paint to adhere. Moore then informed Gibbs in writing that the doors would require substantially more surface preparation than was contemplated by the subcontract. Accordingly, Moore requested a change order granting additional compensation for reworking the doors which Moore had already painted and for preparing the surface on the balance of the doors. Gibbs denied Moore's request for additional compensation, responding that the subcontract placed the burden of selecting and completing the proper surface preparation on Moore. Thereafter, Moore wrote

1 For purposes of this appeal Fidelity's interests are aligned with those of Gibbs. The defendants are referred to collectively as "Gibbs."

directly to the Air Force about the problem. Following an investigation, the Air Force agreed with Gibbs.

As a result of the ongoing dispute, Gibbs withheld part of Moore's requested payment for September.2 In October 1992, Gibbs did not submit any pay request for Moore to the Air Force. Gibbs claims that it never received Moore's October pay request, and that funds would have been withheld anyway because Moore's performance continued to be unsatisfactory. Moore contends that the request was mailed to Gibbs according to his usual procedure.

On November 9, 1992, Moore walked off the job, leaving approximately half of the painting work incomplete. Gibbs subsequently subcontracted with another painting contractor and was able to complete the painting work for less than the amount provided in Moore's subcontract, although the dispute with Moore did significantly delay Gibbs' departure from the job site.

PROCEDURAL HISTORY

Moore filed this suit in October 1993. Federal jurisdiction was based on the Miller Act, 40 U.S.C. § 270a et seq., which requires certain contractors in privity with the United States on federal construction projects to provide a payment bond for the protection of subcontractors that are not in privity with the United States. Id. at § 270a. The Act creates a statutory cause of action, in favor of the subcontractor, and against the surety bond, when the subcontractor is not paid on a timely basis for

2 The subcontract provided for Moore to receive progress payments for work completed each month.

labor and materials furnished to the federal project. Id. at § 270b(a).

Moore also alleged claims, in the alternative, under Mississippi state law for (1) breach of contract, and (2) fraud and misrepresentation. Moore's breach of contract claim was based on Gibbs' non-payment and Gibbs' failure to issue a change order after Moore encountered a job site that materially differed from that contemplated by the parties. Moore's fraud and misrepresentation claims were based on allegations that project managers for both Gibbs and the Air Force represented to Moore prior to contracting that the surface preparation required would be minimal. Moore sought recovery of the following damage elements: (1) $ 30,794.50 for labor and materials already supplied to the contract; (2) $ 6,858 for materials purchased by Moore for the contract; (3) $ 3,807 for extra-contractual work performed to remedy the surface adhesion problem; (4) $ 17,233.16 in attorney fees, on the basis of Gibbs' bad faith; (5) $ 15,983.52 in expectation damages, for profits lost due to Gibbs' alleged breach; (6) $ 50,000 in punitive damages; and (7) pre-judgment interest.

Gibbs answered that Moore committed the first breach by abandoning performance, and that Moore failed to mitigate his damages because he refused to sell materials purchased for the job to Gibbs. Therefore, Gibbs claimed entitlement to an offset for more than the damages claimed by Moore. Gibbs further answered that unambiguous subcontract language imposed upon Moore the obligation and expense of selecting an appropriate method of

surface selection, and that the contract specifications contemplated the extent of surface preparation required at the Tyler House.

Moore demanded a jury trial and the case was initially set for October 1994. In early October 1994, the parties signed a pretrial order and trial was reset for March 1995. The pretrial order was entered on October 18, 1994.

On October 14, 1994, the district court received Gibbs' motion to limit evidence and for leave of court. On November 4, Moore also moved to limit evidence and for leave of court. On December 20, the district court heard argument on the parties' cross-motions to limit evidence.

On January 13, 1995 the district court issued a lengthy order:

(1) determining that Mississippi law applied; (2) excluding all of Moore's evidence; and (3) declining to recognize any offset recovery in favor of Gibbs. On January 18, 1995, after a hearing on Moore's request that the district court reconsider its January 13 ruling, the district court announced that it would enter final judgment in seven days unless the parties settled.

On February 27, 1995, the district court entered an order sua sponte "dismissing" the case. The February 27 order clarified that the district court had intended to deny all of Moore's claims in its January 13 order. The February 27 order further stated that the rights and liabilities of all parties had been fully adjudicated, and ordered entry of final judgment in accordance with

Federal Rule of Civil Procedure 58. Final judgment was entered March 1, 1995. Moore filed a timely notice of appeal.

On March 6, after final judgment was entered, the district court entered an order, sua sponte taking notice that the evidence excluded by its January 13 order was not part of the record. The March 6 order required the parties to submit copies of the excluded evidence by March 10, 1995.

Moore raises three main issues on appeal. First, Moore challenges the procedure employed by the district court, arguing that his case was thrown out of court without adequate notice and without a fair hearing. Second, Moore contends that the district court erroneously determined that the entire dispute was governed by Mississippi law because his Miller Act claims are governed by federal law standards that displace state law. Third, Moore contends that the findings made by the district court in the January 13 order are erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Moore v. Gibbs Construction, (5th Cir. 2004).

Moore v. Gibbs Construction (Moore v. Gibbs Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related