Moore v. Gibbs Construction

CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 25, 2004
Docket95-60096
StatusUnpublished

This text of Moore v. Gibbs Construction (Moore v. Gibbs Construction) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore v. Gibbs Construction, (5th Cir. 2004).

Opinion

UNITED STATES COURT OF APPEALS For the Fifth Circuit

No. 95-60096

LEWIS MOORE, United States of America for the use of d/b/a Lewis Moore Painting,

Plaintiff-Appellant,

VERSUS

GIBBS CONSTRUCTION COMPANY, INC., ET AL.,

Defendants-Appellees.

Appeal from the United States District Court For the Southern District of Mississippi (1:93-CV-491-RR)

February 23, 1996 Before GARWOOD, EMILIO M. GARZA, and DeMOSS, Circuit Judges.

PER CURIAM:*

Plaintiff Lewis Moore (Moore) appeals from final judgment

entered sua sponte prior to trial on the basis of arguments

presented in the parties' cross-motions to limit evidence. We

vacate and remand to the district court for further proceedings.

* Pursuant to Local Rule 47.5, the Court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in Local Rule 47.5.4. BACKGROUND

Defendant Gibbs Construction Company (Gibbs) contracted with

the United States to repair and renovate the interior of the Tyler

House apartments on Kessler Air Force Base in Biloxi, Mississippi.

As required by law, Gibbs arranged for a bond as surety for payment

of claims against Gibbs. The payment bond was issued by co-

defendant Fidelity & Deposit Company of Maryland (Fidelity).1 In

November 1991, Gibbs subcontracted with Moore to paint and install

wall coverings inside the Tyler House.

After Moore commenced performance, it became apparent that the

existing surface on the interior doors and door frames in the Tyler

House would not bond with the paint called for in Moore's

subcontract with Gibbs. Moore delivered a sample of the door

surface to the paint manufacturer and it was examined by a chemist,

who specified an extensive surface preparation procedure for

getting the paint to adhere. Moore then informed Gibbs in writing

that the doors would require substantially more surface preparation

than was contemplated by the subcontract. Accordingly, Moore

requested a change order granting additional compensation for

reworking the doors which Moore had already painted and for

preparing the surface on the balance of the doors. Gibbs denied

Moore's request for additional compensation, responding that the

subcontract placed the burden of selecting and completing the

proper surface preparation on Moore. Thereafter, Moore wrote

1 For purposes of this appeal Fidelity's interests are aligned with those of Gibbs. The defendants are referred to collectively as "Gibbs."

2 directly to the Air Force about the problem. Following an

investigation, the Air Force agreed with Gibbs.

As a result of the ongoing dispute, Gibbs withheld part of

Moore's requested payment for September.2 In October 1992, Gibbs

did not submit any pay request for Moore to the Air Force. Gibbs

claims that it never received Moore's October pay request, and that

funds would have been withheld anyway because Moore's performance

continued to be unsatisfactory. Moore contends that the request

was mailed to Gibbs according to his usual procedure.

On November 9, 1992, Moore walked off the job, leaving

approximately half of the painting work incomplete. Gibbs

subsequently subcontracted with another painting contractor and was

able to complete the painting work for less than the amount

provided in Moore's subcontract, although the dispute with Moore

did significantly delay Gibbs' departure from the job site.

PROCEDURAL HISTORY

Moore filed this suit in October 1993. Federal jurisdiction

was based on the Miller Act, 40 U.S.C. § 270a et seq., which

requires certain contractors in privity with the United States on

federal construction projects to provide a payment bond for the

protection of subcontractors that are not in privity with the

United States. Id. at § 270a. The Act creates a statutory cause

of action, in favor of the subcontractor, and against the surety

bond, when the subcontractor is not paid on a timely basis for

2 The subcontract provided for Moore to receive progress payments for work completed each month.

3 labor and materials furnished to the federal project. Id. at §

270b(a).

Moore also alleged claims, in the alternative, under

Mississippi state law for (1) breach of contract, and (2) fraud and

misrepresentation. Moore's breach of contract claim was based on

Gibbs' non-payment and Gibbs' failure to issue a change order after

Moore encountered a job site that materially differed from that

contemplated by the parties. Moore's fraud and misrepresentation

claims were based on allegations that project managers for both

Gibbs and the Air Force represented to Moore prior to contracting

that the surface preparation required would be minimal. Moore

sought recovery of the following damage elements: (1) $ 30,794.50

for labor and materials already supplied to the contract; (2) $

6,858 for materials purchased by Moore for the contract; (3) $

3,807 for extra-contractual work performed to remedy the surface

adhesion problem; (4) $ 17,233.16 in attorney fees, on the basis of

Gibbs' bad faith; (5) $ 15,983.52 in expectation damages, for

profits lost due to Gibbs' alleged breach; (6) $ 50,000 in punitive

damages; and (7) pre-judgment interest.

Gibbs answered that Moore committed the first breach by

abandoning performance, and that Moore failed to mitigate his

damages because he refused to sell materials purchased for the job

to Gibbs. Therefore, Gibbs claimed entitlement to an offset for

more than the damages claimed by Moore. Gibbs further answered

that unambiguous subcontract language imposed upon Moore the

obligation and expense of selecting an appropriate method of

4 surface selection, and that the contract specifications

contemplated the extent of surface preparation required at the

Tyler House.

Moore demanded a jury trial and the case was initially set for

October 1994. In early October 1994, the parties signed a pretrial

order and trial was reset for March 1995. The pretrial order was

entered on October 18, 1994.

On October 14, 1994, the district court received Gibbs' motion

to limit evidence and for leave of court. On November 4, Moore

also moved to limit evidence and for leave of court. On December

20, the district court heard argument on the parties' cross-motions

to limit evidence.

On January 13, 1995 the district court issued a lengthy order:

(1) determining that Mississippi law applied; (2) excluding all of

Moore's evidence; and (3) declining to recognize any offset

recovery in favor of Gibbs. On January 18, 1995, after a hearing

on Moore's request that the district court reconsider its January

13 ruling, the district court announced that it would enter final

judgment in seven days unless the parties settled.

On February 27, 1995, the district court entered an order sua

sponte "dismissing" the case. The February 27 order clarified that

the district court had intended to deny all of Moore's claims in

its January 13 order. The February 27 order further stated that

the rights and liabilities of all parties had been fully

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Moore v. Gibbs Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-v-gibbs-construction-ca5-2004.