Montana Power Company v. Bokma

457 P.2d 769, 153 Mont. 390, 1969 Mont. LEXIS 440
CourtMontana Supreme Court
DecidedAugust 7, 1969
Docket11671
StatusPublished
Cited by30 cases

This text of 457 P.2d 769 (Montana Power Company v. Bokma) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montana Power Company v. Bokma, 457 P.2d 769, 153 Mont. 390, 1969 Mont. LEXIS 440 (Mo. 1969).

Opinion

MR. JUSTICE HASWELL

delivered the Opinion of' the Court.

*392 This case is a condemnation proceeding instituted by plaintiff Montana Power Company to acquire á right-of-way easement across defendants’ lands for the purpose of constructing an electric power transmission line. Prom the preliminary order of condemnation entered by the district Court, defendants appeal.

Plaintiff Montana Power Company is a public utility engaged in..the production, distribution and sale of electric power. Defendants are owners and occupiers of agricultural land located generally northwest of Conrad, Montana. Plaintiff utility seeks to construct a 115 KV electric power transmission line from Great Falls to a point south of Cut Bank, Montana, where the Continental Pipe Line Company, a common carrier of crude oil transported through a pipeline system, operates a pumping-station.

The construction of the electric power line essentially involves placing “H-type” double pole structures in the ground to carry the wires. These structures are to bé placed at an average interval of about 750 feet, although the spacing intervals vary somewhat with the terrain and at some points three poles with supporting guy wires are contemplated. A distance of 10% feet separates the two poles in each double pole structure:

Between Conrad and Continental’s pumping station, plaintiff seeks to acquire by condemnation an easement on a 60 foot strip running across defendants’ lands for construction of this power line.

Early in 1968, plaintiff utility was contacted by personnel of the Continental Pipe Line Company in regard to furnishing electrical power for their pumping station south of Cut Bank. Negotiations culminated in a written agreement generally comprehending substantial amounts of electrical power to be furnished by plaintiff utility. The 115 KV power line was planned (1) to furnish these power requirements of Continental Pipe Line Company, (2) to meet the anticipated increasing power needs of the Conrad, Choteau, and Valier areas, arising from *393 normal growth, and (3) because of the possibility of an interconnection with electrical line of the Bureau of Reclamation and Glacier Electric Cooperative. At the present time the power line from Conrad northwest to its terminus at Continental’s pumping station south of Cut Bank will serve only Continental, but service from that line is available to other customers should such service be required.

The four cases concerning the landowners heretofore mentioned were consolidated for hearing on the issue of public use and necessity. Hearing was held' in the district court of Pondera County before the Hon. Victor H. Fall, district judge presiding. The district court entered findings to the effect that plaintiff has the right to acquire property by eminent domain; that the use for which the property was sought is a public use; that the taking is necessary to such use; that the public interest requires such taking; and that the electric power transmission line has been located in a manner and along a route most compatible with the ' greatest public good and thé least private injury. Based upon 'those findings, the district court entered its preliminary order of condemnation.

Subsequently plaintiff utility deposited in court the amounts claimed by defendants and secured an order from the district court placing it in possession of the condemned property during the pendency of the action. Defendants' now appeal from the district court’s preliminary order of condemnation.

Upon appeal defendant landowners assign four issues for review which can be summarized as follows:

(1) Is the proposed taking for a public use?

(2) Is the proposed taking necessary for such use?

(3) Is the proposed taking compatible with the greatest public good and the least private injury?

(4) Does the proposed taking deprive the landowners of ‘■‘due process” as required by the Federal and State Constitutions ?

The gist of the landowners’ contention on the first issue is *394 that the proposed taking is to provide electric power and service to a single customer; as such it is a taking for a private use and not a public use; and a taking for a private use will not support eminent domain proceedings. Alternatively they argue that the contract for furnishing power by plaintiff utility to Continental Pipe Line Company is illusory and does not require plaintiff utility to furnish power even to that one customer.

Condemnation proceedings by a public utility for the purpose of construction of an electrical power transmission line has been authorized by the legislature and has been so interpreted in past decisions of this Court. The legislature has empowered the plaintiff utility to acquire property by eminent domain. Section 15-2204(d), R.C.M.1947. The legislature has specifically declared that an electric power line is a public use for which private property may be taken by eminent domain proceedings. Section 93-9902(11), R.C.M.1947. This Court has held that dams, reservoirs, power plants, and electric power lines are public uses for which private property may be acquired under eminent domain. Helena Power Transmission Co. v. Spratt, 35 Mont. 108, 88 P. 773, 8 L.R.A.,N.S., 567.

Nonetheless the landowners claim that under the circumstances disclosed here the electric power transmission line is a private line for the benefit of only one customer. They contend that a public use requires an actual use by the public as a whole, or at least the right to use the proposed system by the public in general. They contend that these requirements are absent in the instant case and therefore there is no public use within the meaning of eminent domain proceedings.

At the outset, we recognize that there are two conflicting lines of authority in other jurisdictions concerning the requisites of a “public use” within the meaning of eminent domain proceedings. One view, the limited or narrow view, requires in general the actual use or right to use the proposed system by the public as a whole. The other view, called the board view, essentially requires only a use conferring a “public advantage” *395 or a “public benefit”. Montana, as with many western states, has adhered to the broad view since 1895, presumably to promote general economic development. See Butte, A. & P. Ry. Co. v. Montana U. Ry. Co., 16 Mont. 504, 41 P. 232, 31 L.R.A. 298; Ellinghouse v. Taylor, 19 Mont. 462, 48 P. 757; Helena Power Transmission Co. v. Spratt, 35 Mont. 108, 88 P. 773, 8 L.R.A.,N.S., 567; Rutherford v. City of Great Falls, 107 Mont. 512, 86 P.2d 656; State ex rel. Helena Housing Authority v. City Council, Inc. 108 Mont. 347, 90 P.2d 514. Cases cited by the landowners are not controlling authority for the limited or narrow view—Northern Pacific Ry. Co. v. McAdow, 44 Mont. 547, 121 P. 473 (decided on the issue of necessity, not public use); State v. Aitchison, 96 Mont. 335, 30 P.2d 805

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mdu v. Parkshill Farms
2017 SD 88 (South Dakota Supreme Court, 2017)
Myers v. Dee
2011 MT 244 (Montana Supreme Court, 2011)
Yellowstone Pipe v. Sebena
2004 MT 220N (Montana Supreme Court, 2004)
Cenex Pipeline LLC v. Fly Creek Angus, Inc.
1998 MT 334 (Montana Supreme Court, 1998)
City of Medora v. Golberg
1997 ND 190 (North Dakota Supreme Court, 1997)
City of Jamestown v. Leevers Supermarkets, Inc.
552 N.W.2d 365 (North Dakota Supreme Court, 1996)
Montana Power Co. v. Burlington Northern Railroad
900 P.2d 888 (Montana Supreme Court, 1995)
City of Bozeman Ex Rel. Department of Transportation v. Vaniman
869 P.2d 790 (Montana Supreme Court, 1994)
Public Service Co. of Colorado v. Shaklee
784 P.2d 314 (Supreme Court of Colorado, 1989)
Montana Power Co. v. Fondren
737 P.2d 1138 (Montana Supreme Court, 1987)
State Ex Rel. Department of Highways v. Standley Bros.
699 P.2d 60 (Montana Supreme Court, 1985)
Lincoln/Lewis & Clark County Sewer District v. Bossing
696 P.2d 989 (Montana Supreme Court, 1985)
Schara v. Anaconda Co.
610 P.2d 132 (Montana Supreme Court, 1980)
Schara v. Anaconda Company
Montana Supreme Court, 1980
Williams v. Hyrum Gibbons & Sons Co.
602 P.2d 684 (Utah Supreme Court, 1979)
Groundwater v. Wright
588 P.2d 1003 (Montana Supreme Court, 1979)
State ex rel. Department of Transportation v. Hilderbrand
582 P.2d 13 (Court of Appeals of Oregon, 1978)
United Power Ass'n v. Mund
267 N.W.2d 825 (North Dakota Supreme Court, 1978)
Square Butte Electric Cooperative v. Hilken
244 N.W.2d 519 (North Dakota Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
457 P.2d 769, 153 Mont. 390, 1969 Mont. LEXIS 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montana-power-company-v-bokma-mont-1969.