Montana Power Co. v. Fondren

737 P.2d 1138, 226 Mont. 500, 1987 Mont. LEXIS 1022
CourtMontana Supreme Court
DecidedMay 12, 1987
Docket86-373, 86-374
StatusPublished
Cited by8 cases

This text of 737 P.2d 1138 (Montana Power Co. v. Fondren) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montana Power Co. v. Fondren, 737 P.2d 1138, 226 Mont. 500, 1987 Mont. LEXIS 1022 (Mo. 1987).

Opinion

*503 MR. JUSTICE SHEEHY

delivered the Opinion of the Court.

Landowners Fondren, Cochran and Kezer appeal the order of the District Court, Sixth Judicial District, Park County, which found the District Court had no jurisdiction to determine the existence of public necessity with respect to a proposed electric transmission line under the provisions of the Utility Siting Act of 1973 or the Montana Major Facility Siting Act of 1975, Title 75, Chapter 20, MCA. We affirm for the reasons set forth below.

In June, 1974, Montana Power Company (MPC) filed an application for certification of environmental compatibility and public need under the Montana Utility Siting Act of 1973 (now the Major Facility Siting Act) for the purpose of gaining approval for construction of a transmission facility known as the Clyde Park — Dillon 161 kv transmission line. In October, 1977, the Board of Natural Resources and Conservation (Board) issued a certificate of environmental compatibility and public need, and issued findings of fact, opinion, decision, order and recommendations. The selection of the final center-line for the two mile wide corridor was made by the Board in October, 1985.

Landowners Fondren and Cochran purchased property southwest of Livingston, Montana, in 1980. The property is located in the “Canyon Mountain” area of the Clyde Park to Emigrant segment of the transmission line. When Fondren and Cochran purchased the real estate, there was nothing of record in the office of the county clerk and recorder to indicate that the power line corridor approved by the Board would pass through or include the property. They first learned the power line might be routed through their property in late 1981. After the Board approved the final centerline location by order dated October 11, 1985, MPC sent letters to landowners Fondren, Cochran, and Kezer offering to purchase right-of-way easements and to pay an additional amount in advance for damages to crops and vegetation. The landowners refused the offers.

In February, 1986, MPC filed an action for condemnation of the landowners’ properties pursuant to the Montana Eminent Domain Act. The cases were consolidated in May, 1986. MPC also filed motions to be put in possession and for a preliminary condemnation order. On May 30, 1986, the District Court began hearing testimony in the condemnation action. Hearings were also held June 12. Both MPC and the landowners submitted briefs on the issue of the District Court’s jurisdiction under the Major Facility Siting Act, specifi *504 cally Section 75-20-407, MCA. On June 26, 1986, the District Court issued an order stating it had no jurisdiction to determine the existence of public necessity under the Major Facility Siting Act. The District Court issued a preliminary condemnation order in favor of MPC on July 7, 1986. That order has been stayed pending this appeal.

The landowners raise nine issues on appeal:

1. Did the District Court err by ruling that it had no jurisdiction to determine the existence of “necessity?”

2. Did the District Court err in finding that respondent MPC has established by a preponderance of the evidence those facts which are a prerequisite to condemnation under Section 70-30-111, MCA?

3. Does the District Court have jurisdiction to determine what constitutes “least private injury” in an action for condemnation pursuant to the Montana Eminent Domain Act, Title 70, Chapter 30, MCA?

4. Does the District Court have jurisdiction to determine whether MPC has violated the findings of fact, opinion, decision, order and recommendation of the Board of Natural Resources?

5. Does the District Court have jurisdiction to determine whether the interests sought by MPC are the “minimum necessary interests” pursuant to Section 70-30-203(6), MCA?

6. Whether MPC is restricted to those remedies provided by the Major Facility Siting Act, Sections 75-20-404, -405, or -408, MCA, thus precluding an action in eminent domain under Title 70, Chapter 30, MCA?

7. Has the District Court violated the landowners’ due process rights under the Montana Constitution by vacating the condemnation hearings?

8. Was judicial review a remedy available to the landowners?

9. Does the Montana Major Facility Siting Act violate the landowners’ due process rights where the Act provides no mechanism for recording and giving notice to successor landowners that a power line corridor has been approved across their property, and where eight and a half years have elapsed between the time of corridor approval and the choice of a centerline?

MPC contends there is only one issue on appeal:

“Whether the District Court was correct in ruling it did not have jurisdiction to determine public necessity because that determination was already properly made by the Board of Natural Resources pursuant to the Major Facility Siting Act?”

*505 As a preliminary matter, MPC argues that this Court should not hear issues relating to the preliminary condemnation order, since the landowners never specifically filed a notice of appeal as to that order. The procedural sequence of events was as follows:

1. June 26, 1986: District Court issued its order declining to take jurisdiction over the issue of public necessity.

2. July 3, 1986: Landowners filed their notice of appeal of the June 26 order.

3. July 7, 1986: The preliminary condemnation order was filed in District Court (although signed by Judge Rapkoch July 3).

The filing of a notice of appeal is jurisdictional, and the failure to timely file is a fatal defect altered only on the most extenuating circumstances. Leitheiser v. Montana State Prison (1973), 161 Mont. 343, 346, 505 P.2d 1203, 1205; Payne v. Mountain States Tel. & Tel. Co. (1963), 142 Mont. 406, 408, 385 P.2d 100, 102. While Rule 3, M.R.App.Civ.P., allows a suspension of the rules in the interest of expediting a decision before this Court, the late filing of a notice of appeal is one exception to the equitable reach of Rule 3. See Rules 21(b) and 5, M.R.App.Civ.P.; Zell v. Zell (1977), 172 Mont. 496, 565 P.2d 311.

We therefore hold that appellants’ issues 2 and 3 relating to the preliminary condemnation order of July 7, 1986 are not properly before us, since appellants failed to timely file a notice of appeal to that order under Rule 5, M.R.App.Civ.P.

The other issues raised by appellants essentially fall into two categories: Issues 1, 4, 5 and 6 present questions concerning the jurisdiction of the District Court and Issues 7-9 raise questions of due process under the Montana Constitution. Accordingly, we will treat the issues in that order.

JURISDICTION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ault v. Whitney
Montana Supreme Court, 1997
Glaude v. State Compensation Insurance Fund
894 P.2d 940 (Montana Supreme Court, 1995)
Bohmer v. Uninsured Employers' Fund
880 P.2d 816 (Montana Supreme Court, 1994)
City of Bozeman Ex Rel. Department of Transportation v. Vaniman
869 P.2d 790 (Montana Supreme Court, 1994)
First Security Bank of Havre v. Harmon
841 P.2d 521 (Montana Supreme Court, 1992)
Birrer v. Trustees, Wheatland County School District No. 15
786 P.2d 1161 (Montana Supreme Court, 1990)
Searight v. Cimino
748 P.2d 948 (Montana Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
737 P.2d 1138, 226 Mont. 500, 1987 Mont. LEXIS 1022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montana-power-co-v-fondren-mont-1987.