Molloy v. . Village of Briarcliff Manor

112 N.E. 429, 217 N.Y. 577, 1916 N.Y. LEXIS 1348
CourtNew York Court of Appeals
DecidedApril 11, 1916
StatusPublished
Cited by9 cases

This text of 112 N.E. 429 (Molloy v. . Village of Briarcliff Manor) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Molloy v. . Village of Briarcliff Manor, 112 N.E. 429, 217 N.Y. 577, 1916 N.Y. LEXIS 1348 (N.Y. 1916).

Opinion

Hiscock, J.

This action was brought to recover a balance alleged to he due on a contract entered into by the plaintiff with the defendant for laying pavements, building bridges and performing other work. This balance consisted largely of amounts claimed to be due for extra or additional work, and without discussing the details of the claim and of the recovery which plaintiff secured it is sufficient to say that we see no reason for reversing the judgment unless one or both of the rulings made by the trial judge upon two questions were erroneous, and we shall confine our consideration to them.

We shall assume as claimed by plaintiff and as was held by the Appellate Division on appeal from a former judgment, that the contract between the parties provided for compensation on the “lump sum” basis, so called, and not on the unit price plan. The plaintiff’s complaint, however, was framed on the former theory, and notwithstanding the determination of the Appellate Division that this theory was wrong no application to amend the complaint was made before the second and present trial, and over various objections made by defendant plaintiff introduced his evidence under the complaint as thus framed. At the conclusion of his case he made a much delayed application for an amendment of his. complaint so that it should conform to the evidence which had been introduced and this motion was granted.

Of course the decision of the question whether plaintiff’s laches in making a motion for an amendment of his pleadings should be overlooked and excused rested *581 entirely in the discretion of the trial judge, but it is a rule superior to the exercise of discretion that a party shall not be thus allowed to have his pleading amended when the result will be to deprive his adversary of a valid objection to the admission of evidence under the pleading as it stood before amendment. (Barnes v. Seligman, 55 Hun, 339, 349; Beard v. Tilghman, 66 Hun, 12, 15; Charlton v. Rose, 24 App. Div. 485.)

Therefore we come to the inquiry whether the defendant had made any valid objections to the introduction of evidence under plaintiff’s complaint as it originally stood. We think that it had not. The only objection which is found challenging the form of the complaint is one to the introduction of the agreement between the parties, and which was objected to as incompetent and inadmissible under the contract pleaded in the complaint, and which objection was overruled with exception. As I view it, the introduction of this contract was perfectly proper, for in addition to the provisions which it contained governing the performance of the work originally contemplated and provided for, it also contained clauses fixing the prices at which on the option of the defendant work and material might be added to or subtracted from what was thus originally provided for. As has been stated, a large proportion of the balance which plaintiff was seeking to recover was for such additional work and material, and it was, therefore, not only proper but necessary that he should introduce this agreement for the purpose of establishing the prices at which such work and material should be paid for. I am all the more ready to adopt this view because, while plaintiff seems to have been guilty of laches in making his motion, it is also true that defendant understood perfectly well what his claim was, and, therefore, was not actually any more than technically prejudiced by the amendment.

The next ruling to be considered involved a rule of pleading and is more important.

*582 The defendant claimed on the trial that in carrying out his contract plaintiff required or permitted his employees to work more than eight hours a day in violation of the provisions of section 3 of the Labor Law, (Oons. Laws, ch. 31) and that this violation barred his right to recover. Its offer to introduce evidence in support of this claim, however, was refused on the ground that this defense was not permissible under a general denial of plaintiff’s complaint and that it was not sufficiently pleaded as an affirmative defense.

Plaintiff’s complaint, after setting forth the contract, alleged that he “ proceeded to perform and carry out the said contract and has performed large quantities of work thereunder, and had on or about the 1st day of November, 1907, fully completed the same according to the plans, drawings and specifications as changed and varied by the engineer * '* * and said work has been duly accepted by the defendant.” These allegations were met by a general denial. It is a familiar rule that plaintiff under such allegations need only prove such facts as are necessary to entitle him to recover, and that defendant under a general denial can only give such evidence as legitimately tends to disprove the facts necessary to be established by the plaintiff. (Milbank v. Jones, 127 N. Y. 370, 376; Weaver v. Barden, 49 N. Y. 286.)

Therefore, the real underlying question becomes the one whether plaintiff was obliged to prove as part of his case that he had not violated the Labor Lafw. If he was not, it is plain that it was necessary for defendant to plead such alleged violation as an affirmative defense. The answer to this question requires in the first instance a consideration of the pertinent provisions of the statute.

That statute provides as follows: § 3. Hours to constitute a day’s work. * * * Each contract to which the state or a municipal corporation * * * is a party which may involve the employment of laborers, workmen, or mechanics shall contain a stipulation that no laborer, *583 workman or mechanic in the employ of the contractor subcontractor or other person doing or contracting to do the whole or a part of the work contemplated by the contract shall be permitted or required to work more than eight hours in any one calendar day except in cases of extraordinary emergency caused by fire, flood or danger to life or property. * * * Each contract for such public work hereafter made shall contain a provision that the same shall be void and of no effect unless the person or corporation making or performing the same shall comply with the provisions of this section; and no such person or corporation shall be entitled to receive any sum nor shall any officer, agent or employee of the state or of a municipal corporation pay the same or authorize its payment from the funds under his charge or control to any such person or corporation for work done upon any contract, which in its form or manner of performance violates the provisions of this section. * * * ”

The statute thus attempts to enforce compliance with its prohibition of labor in excess of eight hours in a day in two ways. First it requires that certain clauses looking to an observance of its commands must be incorporated in the written contract in order to make it valid. This requirement relates to the form and inception of the contract, and if it is violated the defect shows on the face of the instrument. There is no claim that the contract in question here does not comply with these provisions, and, therefore, it was valid at the time of its execution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

School Bus Sales, Inc. v. Eureka Williams Corp.
10 A.D.2d 773 (Appellate Division of the Supreme Court of New York, 1960)
Kathleen Foley, Inc. v. Gulf Oil Corp.
3 A.D.2d 928 (Appellate Division of the Supreme Court of New York, 1957)
Mackey v. Empire Rollerdrome of Brooklyn, Inc.
267 A.D. 995 (Appellate Division of the Supreme Court of New York, 1944)
Coughlin v. Jones
162 Misc. 843 (City of New York Municipal Court, 1937)
Stokes Brothers, Inc. v. Drefs
244 A.D. 524 (Appellate Division of the Supreme Court of New York, 1935)
Bank of United States v. Ribman
244 A.D. 209 (Appellate Division of the Supreme Court of New York, 1935)
David v. City National Securities Co.
174 A.D. 593 (Appellate Division of the Supreme Court of New York, 1916)
New York Lubricating Oil Co. v. C. E. Mills Oil Co.
173 A.D. 628 (Appellate Division of the Supreme Court of New York, 1916)
Branower & Son, Inc. v. Waldes
173 A.D. 676 (Appellate Division of the Supreme Court of New York, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
112 N.E. 429, 217 N.Y. 577, 1916 N.Y. LEXIS 1348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/molloy-v-village-of-briarcliff-manor-ny-1916.