Moe v. Eugene Zurbrugg Construction Co.

123 P.3d 338, 202 Or. App. 577, 2005 Ore. App. LEXIS 1492
CourtCourt of Appeals of Oregon
DecidedNovember 16, 2005
Docket0012-12966; A120140
StatusPublished
Cited by4 cases

This text of 123 P.3d 338 (Moe v. Eugene Zurbrugg Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moe v. Eugene Zurbrugg Construction Co., 123 P.3d 338, 202 Or. App. 577, 2005 Ore. App. LEXIS 1492 (Or. Ct. App. 2005).

Opinion

*579 WOLLHEIM, J.

Defendants appeal from a judgment in favor of plaintiff on his claims for negligence and for damages for personal injuries under the Employer’s Liability Law (ELL), ORS 654.305 - 654.336. On appeal, defendants assign error to the trial court’s denial of their motions for a directed verdict, the trial court’s failure to give defendants’ requested jury instructions, and the trial court’s admission of expert testimony. We affirm.

The facts relevant to the disposition of the case are as follows: Defendant Park Lanes operated a bowling facility in Hillsboro, Oregon, on leased property. When the lease ended in 1998, Park Lanes purchased nearby property in order to relocate the facility. Park Lanes contracted with defendant Zurbrugg Construction Company to build the new facility, although Park Lanes planned to relocate and install the lanes itself. The contract between Park Lanes (the Owner) and Zurbrugg (the Contractor) specified, in part:

“9.1 The Contractor shall supervise and direct the Work, using the Contractor’s best skill and attention. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning these matters.
«>lí ‡ ‡
“9.7 The Contractor shall be responsible to the Owner for the acts and omissions of the Contractor’s employees, Subcontractors and their agents and employees, and other persons performing portions of the Work under a contract with the Contractor.
“16.1 The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the performance of the Contract. The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss to:
*580 “.1 employees on the Work and other persons who may be affected thereby;
“.2 the Work and materials and equipment to be incorporated therein; and
“.3 other property at the site or adjacent thereto.
“The Contractor shall give notices and comply with applicable laws, ordinances, rules, regulations and lawful orders of public authorities bearing on safety of persons and property and their protection from damage, injury or loss.”

Zurbrugg subcontracted the interior walls, sheet rock, and acoustic tile ceilings to Cascade Acoustics Company, plaintiffs employer. The written contract between Zurbrugg and Cascade did not contain any language regarding Cascade’s responsibility for safety. Cascade did have a safety plan, which specified that “100% Fall Protection shall be provided at all times when an employee is exposed to a fall distance of 6 feet or greater” and “[f]loor openings shall be guarded with guard rails or covered with a substantial cover.” Cascade also had a fall protection plan that specified, in part:

“A. Floor Openings & HVAC or Elec. Cutouts.
“1. No Cascade employees allowed in any area until General Contractor has installed proper Guardrail System and covered all interior floor penetrations.”

Installation of the bowling alleys was a time-consuming and complicated process that required each lane, split into four sections weighing several thousand pounds, to be correctly positioned and leveled to within 40/1000th of an inch, and took four to six months to complete. Before the lanes were brought in, other Zurbrugg subcontractors installed electrical wiring, heating ducts, and sprinklers throughout the ceiling. Cascade employees also hung a metal ceiling grid from the roof, in which the acoustic ceiling tile was to be placed. Work on the lanes started before the ceiling was completed. Gary Zurbrugg, the project manager, testified that, because the custom-made heating units for the building were not ready, a decision was made to wait to install the ceiling tile, which was subject to warping.

*581 All work up to this point was done from a flat concrete surface, using scissor-lift scaffolds. After Park Lanes began to install the bowling lanes, the floor became much more hazardous. Between each lane was a trench that was left open so that Park Lanes workers could level the lanes, work on the ball return tracks and the wiring, and lay sheetrock. Park Lanes did not cover the holes, and workers sometimes stepped into the holes. Plaintiff presented testimony that Gary Zurbrugg considered the area a general area and had stated that he was not going to cover the holes because it was up to each individual contractor, although he provided pieces of plywood so that workers could cover a trench while they worked above it.

On the day prior to plaintiffs injury, and about a month after work on the lanes began, two Cascade employees were told to install the ceiling tiles. Dale Dodge, Cascade’s on-site supervisor, testified that Zurbrugg did not specify the exact date to install the tiles, but that they were to be installed “within a few days” of the order. The workers used Baker’s scaffolds — framed scaffolds mounted on wheels — to straddle a trench, with the wheels on the two lanes on each side of the trench. The workers would drop in ceiling tile and then pull themselves down the lanes by holding on to the metal ceiling grid. Several witnesses testified that this method was commonly used in the industry. Witnesses also testified that other types of scaffolds, such as a scissor-lift, would either be unsafe to use or were not available. The next day, plaintiff, who had been hanging sheetrock at the site, was asked to help with the installation. At some point during the work, one of the wheels on plaintiffs Baker’s scaffold fell into a trench, causing it to flip and send plaintiff to the ground. As a result of the fall, plaintiff suffered severe injuries.

In his first amended complaint, plaintiff brought two claims for relief. The first claim was under the ELL and the second claim was based on negligence. The first claim was divided into three “counts,” in that it alleged that defendants had violated the ELL (1) based on safety codes, (2) not based *582 on safety codes, and (3) based on the Oregon Safe Employment Act (OSEA), 1 ORS 654.001 - 654.295, ORS 654.750 - 654.780; ORS 654.991.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yeatts v. Polygon Northwest Co.
341 P.3d 864 (Court of Appeals of Oregon, 2014)
Peterson v. McCAVIC
277 P.3d 572 (Court of Appeals of Oregon, 2012)
Estate of Schwarz v. Philip Morris Inc.
135 P.3d 409 (Court of Appeals of Oregon, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
123 P.3d 338, 202 Or. App. 577, 2005 Ore. App. LEXIS 1492, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moe-v-eugene-zurbrugg-construction-co-orctapp-2005.