Modern Drop Forge Company v. Rapid Technologies, Incorporated

94 F.3d 647, 1996 U.S. App. LEXIS 37419, 1996 WL 453235
CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 8, 1996
Docket95-3113
StatusUnpublished

This text of 94 F.3d 647 (Modern Drop Forge Company v. Rapid Technologies, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Modern Drop Forge Company v. Rapid Technologies, Incorporated, 94 F.3d 647, 1996 U.S. App. LEXIS 37419, 1996 WL 453235 (7th Cir. 1996).

Opinion

94 F.3d 647

NOTICE: Seventh Circuit Rule 53(b)(2) states unpublished orders shall not be cited or used as precedent except to support a claim of res judicata, collateral estoppel or law of the case in any federal court within the circuit.
MODERN DROP FORGE COMPANY, Plaintiff-Appellant,
v.
RAPID TECHNOLOGIES, INCORPORATED, Defendant-Appellee.

No. 95-3113.

United States Court of Appeals, Seventh Circuit.

Argued Feb. 21, 1996.
Decided Aug. 8, 1996.

Before BAUER, KANNE and ROVNER, Circuit Judges.

ORDER

In this diversity case, Modern Drop Forge Company ("Modern") seeks to recover consequential damages for the alleged breach by Rapid Technologies, Inc. ("Rapid") of a contract for the design and installation of a furnace at Modern's Blue Island, Illinois facility. The district court dismissed the case after concluding that Modern's claim was foreclosed by a provision of the contract that precludes the recovery of incidental and consequential damages in the event of a breach. The district court subsequently denied Modern's motion to vacate and reconsider that dismissal. In this appeal, Modern advances an array of arguments in an attempt to show that the dismissal was erroneous. Most of those arguments were waived below, however, when Modern failed to present them in response to Rapid's motion to dismiss. As for the lone argument that Modern preserved, we agree with the district court that the contract's damage limitation provision is not unconscionable. We therefore affirm the district court's judgment of dismissal.

I.

In order to demonstrate that most of Modern's present arguments were not preserved below, we lay out the complaint's allegations and Modern's arguments in response to the motion to dismiss in some detail. Although the complaint's allegations are somewhat sketchy, Modern attached various exhibits that fill in the details. Those exhibits are properly considered as part of the complaint in determining whether it states a viable claim for relief. See Fed.R.Civ.P. 10(c); Hamilton v. O'Leary, 976 F.2d 341, 343 (7th Cir.1992). We also at this stage assume the truth of the matters alleged in Modern's complaint. MCM Partners, Inc. v. Andrews-Bartlett & Assoc., Inc., 62 F.3d 967, 969 (7th Cir.1995).

The complaint alleges a claim for breach of contract without identifying the contract allegedly breached. Modern alleges that Rapid sent it a quotation for the design and installation of a "Whole Bar Rapid Heating Furnace and Automatic Loading System" (the "furnace") on approximately September 1, 1992. Included with that quotation were Rapid's standard terms and conditions of sale. Between September 1 and October 6, 1992, Rapid and Modern engaged in further negotiations, adding what Modern calls "an additional term concerning a review phase via letter from Rapid to Modern dated September 10, 1992." (R. 7 at p 6.) On or about October 6, Modern issued a purchase order for the furnace that included its own standard terms and conditions of sale. Modern also made certain modifications to the standard terms and conditions that had accompanied Rapid's quotation. Upon receiving Modern's purchase order, Rapid set about to design and then to install the furnace. Pursuant to the above documents and subsequent purchase orders covering component parts for the furnace, Modern agreed to pay and did pay Rapid $438,214.16.

To prepare for the installation of its new furnace, Modern purchased certain additional equipment and made modifications to its physical plant, all at the direction of Rapid. The furnace that Rapid eventually installed in late May and early June 1994, however, did not perform in accordance with the specifications to which the parties had agreed. On October 27, 1994, Rapid acknowledged that it was incapable of producing a furnace that would perform in accordance with those specifications. It therefore returned to Modern $415,046.66, which reflected the amounts Modern paid for the furnace and all component parts save one. Modern subsequently purchased a furnace for its Blue Island plant from another company.

Modern's complaint further alleges that at all material times, Rapid knew that it did not have the technological capability to design and manufacture a furnace that would meet the specifications in the parties' agreement. Rapid withheld this information from Modern, however, and induced it to purchase necessary equipment and to modify its plant to accommodate the furnace.

Rapid's breach of the parties' contract allegedly caused Modern to suffer the following damages, for which it seeks to recover in this action: cover damages of at least $100,000, freight charges and construction costs of $26,724, equipment costs of $151,394.85, and labor costs, utility expenses, interest expense and lost profits. Modern's complaint alleges that all tolled, its damages exceed $1,000,000.

Rapid promptly moved to dismiss the complaint pursuant to Fed.R.Civ.P. 12(b)(6). Rapid's brief in support of that motion pointed out that Modern's complaint fails to identify the terms of the parties' agreement. Relying on the documents attached by Modern as exhibits to the complaint, then, Rapid set out to do exactly that. Rapid principally argued that Modern could not recover the incidental and consequential damages sought in its complaint because the terms of Rapid's quotation limit the buyer's remedy for a breach to a return of the purchase price. The warranty provision in Rapid's quotation, for example, provides that:

If any defects in material and workmanship of the product develop within the applicable warranty period, Seller shall supply replacement/repair parts F.O.B. Blue Island, freight prepaid. This shall be Buyer's exclusive remedy for Seller's liability hereunder.

(R. 7, Ex. A at p 6.) That quotation also incorporates Rapid's standard terms and conditions of sale, which include the following additional warranty provision:

This warranty does not extend to Buyer's manufacturing process or the quality of Buyer's product. Losses or damage resulting from equipment failure, program errors, or from the time consumed in delivering, installing, or testing the equipment are not covered by this warranty.

In no event shall the Seller be liable for any amount in excess of the sales price of the equipment delivered by the Seller. Further, IN NO EVENT SHALL SELLER BE LIABLE FOR ANY SPECIAL INDIRECT, OR CONSEQUENTIAL DAMAGES OR LOSS OF PROFITS FOR CAUSES COVERED UNDER THIS WARRANTY OR OTHERWISE UNDER THIS CONTRACT.

(Id. at p 11.) Rapid argued that Modern accepted these terms when it sent the October 6, 1992 purchase order. Conceding that Modern made certain modifications to the quotation as alleged in Modern's complaint, Rapid maintained that Modern did not allege that the above warranty and damage limitation provisions had been revised in any way.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Fidelity Life Insurance Co. v. Joan Karaganis
811 F.2d 357 (Seventh Circuit, 1987)
Freeman v. Hubco Leasing, Inc.
324 S.E.2d 462 (Supreme Court of Georgia, 1985)
A-Larms, Inc. v. Alarms Device Manufacturing Co.
300 S.E.2d 311 (Court of Appeals of Georgia, 1983)
Hall v. FRUEHAUF CORPORATION
346 S.E.2d 582 (Court of Appeals of Georgia, 1986)
Fiat Auto U. S. A., Inc. v. Hollums
363 S.E.2d 312 (Court of Appeals of Georgia, 1987)
KKO, INC. v. Honeywell, Inc.
517 F. Supp. 892 (N.D. Illinois, 1981)
Dawson v. General Motors Corp.
977 F.2d 369 (Seventh Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
94 F.3d 647, 1996 U.S. App. LEXIS 37419, 1996 WL 453235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/modern-drop-forge-company-v-rapid-technologies-incorporated-ca7-1996.