Mobilization Funding, LLC v. Halvorson Construction Group, LLC

CourtDistrict Court, W.D. Washington
DecidedSeptember 14, 2021
Docket2:18-cv-01412
StatusUnknown

This text of Mobilization Funding, LLC v. Halvorson Construction Group, LLC (Mobilization Funding, LLC v. Halvorson Construction Group, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mobilization Funding, LLC v. Halvorson Construction Group, LLC, (W.D. Wash. 2021).

Opinion

1 HONORABLE RICHARD A. JONES

8 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON 9 AT SEATTLE

10 MOBILIZATION FUNDING, LLC, a NO. 2:18-CV-01412-RAJ South Carolina limited liability company, 11

12 Plaintiff,

13 v. 14 HALVORSON CONSTRUCTION 15 GROUP, LLC, a Washington limited 16 liability company; and CEC DEFAULT JUDGMENT AGAINST ELECTRICAL CONTRACTING, LLC, a DEFENDANT HALVORSON 17 CONSTRUCTION GROUP, LLC Washington limited liability company, 18 Defendants. 19 HALVORSON CONSTRUCTION

GROUP, LLC, a Washington limited 20 liability company, 21 Third Party Plaintiff, 22

23 v.

24 JOHN and JANE DOE CHASE, individually 25 and the marital community comprised 26 thereof,

27 Third Party Defendants. 1 I. INTRODUCTION 2 This matter comes before the Court on Plaintiff’s Motion for Default Judgment. 3 Dkt. # 37. Defendant Halvorson Construction Group, LLC (“Halvorson”) has not filed a 4 response. For the reasons below, the Court DENIES Plaintiff’s motion without 5 prejudice. 6 II. BACKGROUND 7 Plaintiff Mobilization Funding (“Plaintiff”) is a South Carolina-based company 8 that provides startup financing to construction subcontractors. Dkt. # 10 at 2. Defendant 9 CEC Electrical Contracting, LLC (“CEC”) is an electrical subcontractor that was retained 10 by Defendant Halvorson Construction Group, LLC (“Halvorson”) to perform electrical 11 work for three of Halvorson’s construction projects (the “Halvorson projects” or “the 12 projects”). Dkt. # 1 at ¶¶ 8-10. 13 On or about November 16, 2016, Halvorson entered into a lump sum electrical 14 contract with CEC in connection with the construction of an apartment building in 15 Redmond, Washington in the amount of $3,150,511. Id. ¶ 8. On or about February 7, 16 2017, Halvorson entered into a lump sum electrical construction contract with CEC in 17 connection with the construction of a hotel in Redmond, Washington in the amount of 18 $3,814,962. Id. ¶ 9. On or about April 3, 2017, Halvorson entered into a lump sum 19 electrical construction contract with CEC for the renovation of a senior living facility in 20 Seattle, Washington in the amount of $1,262,862. Id. ¶ 10. 21 On May 10, 2017, CEC executed a promissory note in favor of Plaintiff in the 22 amount of $1,904,761.91 (“Note”). Id. ¶ 21. CEC also executed a security agreement on 23 the same day (“Security Agreement”), as security for the Note. Id. ¶ 22. CEC granted 24 Plaintiff a security interest in all of CECs inventory, equipment, personal property, and 25 accounts, which included accounts-receivable under CEC’s contracts with Halvorson 26 (“Collateral”). Id. On October 17, 2017, Plaintiff filed a UCC Financing Statement with 27 the Washington Department of Licensing identifying CEC as the debtor and describing 1 its Collateral. Id. ¶ 23. After CEC executed the Note and Security Agreement, Plaintiff 2 made several advances of funds to CEC in the total amount of $1,904,761.91. Id. ¶ 24. 3 In May 2017, Plaintiff and CEC notified Halvorson that Plaintiff held a security 4 interest in the accounts receivable under Halvorson’s agreements with CEC. Id. ¶ 25. On 5 May 15, 2017, Plaintiff, CEC, and Halvorson executive a document entitled “Directive of 6 Funds for CEC Electrical Contracting, Inc.,” (“Directive of Funds”), in which Halvorson 7 agreed to pay the accounts receivable directly to Plaintiff on account of its security 8 interest. Id. ¶ 26. In compliance with the Directive of Funds, Halvorson made 18 9 payments to Plaintiff between June 2017 and April 2018 in the total amount of 10 $1,061,003.74. Id. ¶ 27. 11 Between March 2018 and June 2018, Halvorson loaned funds to CEC to fund 12 CEC’s operating expenses despite being on notice that Halvorson’s receivables were 13 assigned to Plaintiff. Id. ¶ 33. In May through July 2018, CEC submitted applications 14 for payment to Halvorson (“Disputed Pay Applications”). Id. ¶ 34. Instead of paying 15 Plaintiff the amounts due pursuant to the Disputed Pay Applications, Halvorson retained 16 the funds and applied proceeds in satisfaction of its own loans to CEC. Id. ¶ 35. 17 Plaintiff alleges that Halvorson then attempted to induce Plaintiff to provide 18 additional funding to CEC and to refrain from taking steps to protect its interests. Id. ¶ 19 36. Specifically, Plaintiff claims that Halvorson represented to Plaintiff that the amounts 20 CEC would be paid on account of its pay applications materially exceeded the amounts 21 payable to CEC on account of the same pay applications. Id. Plaintiff states that 22 Halvorson represented to Plaintiff that CEC’s April 2018 pay applications related to its 23 projects with Halvorson would total at least $920,000. Id. After accounting for 24 payments to third parties, this amount would result in a sizable payment to CEC, and in 25 turn, to Plaintiff, according to Halvorson. Id. Halvorson’s representations proved false, 26 however, as the amount actually deemed payable to CEC on account of its April 2018 27 pay applications was significantly less than $920,000, and Halvorson did not pay any 1 portion of the amount payable on account of CEC’s April 2018 pay applications to 2 Plaintiff. Id. ¶ 37. 3 On or about June 25, 2018, Halvorson terminated CEC on all of the projects for 4 which CEC had been contracted. Id. ¶ 39. As of the of termination date, the unpaid 5 balance under the contracts was “more than sufficient to cover the costs of the remaining 6 electrical work to be performed on the projects.” Id. ¶ 42. Following the termination 7 date, Halvorson retained control of CEC’s personal property used at the locations of the 8 projects. Id. ¶ 44. 9 On September 25, 2018, Plaintiff brought suit against CEC and Halvorson 10 alleging, among other things, conversion, replevin, and fraud and requesting a declaratory 11 judgment regarding Plaintiff’s priority over CEC’s contract receivables. Dkt. #1. 12 Halvorson was properly served with the complaint on October 1, 2018. Dkt. # 8. Three 13 weeks later, Halvorson filed an answer, cross claim, and third party complaint against 14 CEC for breach of contract and fraud. Dkt. # 9. CEC did not file any response despite 15 being properly served. Dkt. # 22. On August 8, 2019, Plaintiff filed a motion for default 16 against CEC. Id. The Court granted the motion. Dkt. # 25. 17 On August 19, 2019, Halvorson petitioned King County Superior Court for the 18 appointment of a general receiver. Dkt. # 28 at 2. The petition was granted and a general 19 receiver (“Receiver”) was appointed. Id. All of Halvorson’s real and personal property 20 was assigned to the Receiver. Id. Based on the appointment of a Receiver and, 21 effectively, a change in who controls and directs Halvorson’s decisions, Halvorson’s 22 counsel moved to withdraw as counsel from this matter. Id. at 3. 23 On March 6, 2020, the Court granted Halvorson’s counsel’s motion to withdraw as 24 counsel in this matter. Dkt. # 34. However, no substitute counsel had appeared for 25 Halvorson. Id. at 2. Noting that “a corporation may appear in the federal courts only 26 through licensed counsel,” the Court ordered Halvorson to have new counsel enter an 27 appearance on its behalf by March 20, 2020. Id. (citing Rowland v. California Men’s 1 Colony, 506 U.S. 194, 201–02 (1993)). The Court advised Halvorson that if it failed to 2 obtain substitute counsel by that date, “the Court may strike the answer and claims of 3 Halvorson and enter default.” Id. 4 Halvorson failed to have substitute counsel appear on its behalf in this matter by 5 the March 20, 2020 deadline or anytime thereafter. Consequently, on August 10, 2020, 6 the Court struck Halvorson’s answer and claims and entered default against Halvorson. 7 Dkt. # 36. On September 10, 2020, Plaintiff filed the pending motion for default 8 judgment against Halvorson.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lomont, Kent A. v. O'Neill, Paul H.
285 F.3d 9 (D.C. Circuit, 2002)
Alvera M. Aldabe v. Charles D. Aldabe
616 F.2d 1089 (Ninth Circuit, 1980)
Gary R. Eitel v. William D. McCool
782 F.2d 1470 (Ninth Circuit, 1986)
Alan Neuman Productions, Inc. v. Jere Albright
862 F.2d 1388 (Ninth Circuit, 1989)
Westchester Fire Insurance v. Mendez
585 F.3d 1183 (Ninth Circuit, 2009)
Pepsico, Inc. v. California Security Cans
238 F. Supp. 2d 1172 (C.D. California, 2002)
Dr. JKL Ltd. v. HPC IT EDUCATION CENTER
749 F. Supp. 2d 1038 (N.D. California, 2010)
Alhadeff v. Meridian
220 P.3d 1214 (Washington Supreme Court, 2009)
Adams v. King County
192 P.3d 891 (Washington Supreme Court, 2008)
Curtis v. Illumination Arts, Inc.
33 F. Supp. 3d 1200 (W.D. Washington, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Mobilization Funding, LLC v. Halvorson Construction Group, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mobilization-funding-llc-v-halvorson-construction-group-llc-wawd-2021.