Mobil Exploration and Producing North America, Inc. v. Federal Energy Regulatory Commission

881 F.2d 193, 1989 U.S. App. LEXIS 12844
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 28, 1989
Docket88-4769
StatusPublished
Cited by10 cases

This text of 881 F.2d 193 (Mobil Exploration and Producing North America, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mobil Exploration and Producing North America, Inc. v. Federal Energy Regulatory Commission, 881 F.2d 193, 1989 U.S. App. LEXIS 12844 (5th Cir. 1989).

Opinion

CLARK, Chief Judge:

Petitioner Mobil Exploration and Producing North America Inc., (MEPNA) and in-tervenors Texaco Inc. and Texaco Producing Inc., and Oxy USA Inc. (collectively “petitioners”) each acquired leasehold interests in certain gas producing property. More than a year after the acquisitions, petitioners filed applications under section 7 of the Natural Gas Act (NGA), 15 U.S.C. § 717f, to succeed to a certificate of public convenience and necessity to sell gas from the property. The Federal Energy Regulatory Commission (FERC) issued the successor certificates, but based on a prior adjudication imposing a one-year filing deadline, FERC ordered petitioners to refund any rate increases collected between the time of acquisition and the time of filing. On petition for review of FERC’s order, we affirm in part but vacate the refund requirement because FERC failed to adequately notify petitioners of the one-year time limit for filing.

Background

In 1983 and 1984 petitioners acquired leasehold interests in property which was producing natural gas. The assignors of those interests had obtained certificates of public convenience and necessity from FERC to sell the natural gas and had on file rate schedules which governed the price of the gas. When a producer assigns an interest in gas producing property to another, the NGA and applicable regulations require the successor producer to obtain a new certificate of public convenience and necessity. 15 U.S.C. § 717f(c); 18 C.F.R. §§ 2.64(b), 154.92(d). Application *196 for the new certificate is made by filing the instruments of assignment, a summary of the gas contracts, and a request that the assignor’s rate schedule be redesignated as the successor’s rate schedule. 18 C.F.R. § 154.92(d). Neither the NGA nor the regulations impose any time limit for making this successor filing.

Prior to 1986, FERC had a policy of issuing certificates to successors even when the required filing was not made until several years after the acquisition. Under this policy, FERC allowed a successor in interest to receive and retain the predecessor’s rate including any rate increases collected from the time of transfer to the time the successor filing was made. See Plaquemines Oil & Gas Co. v. Federal Power Commission, 450 F.2d 1334 (D.C.Cir.1971).

In 1986 FERC changed its policy and imposed a one-year time limit for making the successor filing in Tenneco Oil Co., 34 F.E.R.C. ¶ 61,143 (Feb. 5, 1986). In Tenne-co, FERC issued a new certificate and allowed the successor in interest to retain all rate increases collected even though the required successor filing was not made until more than three years after the successor’s acquisition of the property. However, the order contained the following passage implementing the new time limit:

in the future, any applicant filing an application for a successor certificate more than one year after the date of transfer of the properties, absent a showing of good cause for the late filing, will be limited to the rate in effect on the date of transfer of the properties without escalations until the date the application is filed. This policy change does not affect successor applications already on file with the Commission.

34 F.E.R.C. 11 61,143 at 61,246.

Several months after the Tenneco order, the petitioners filed the applications for successor certificates that are at issue in this appeal. Each of the filings at issue relate to interests acquired by petitioners more than one year prior to the date petitioners made the filings.

On July 7, 1987 the director of FERC’s Office of Pipeline and Producer Regulation issued an order granting certificates to petitioners. In accordance with the Tenneco order, however, the director required petitioners to refund rate increases collected between the time they acquired the property and the time they filed their applications for successor certificates.

On review of the director’s order, FERC waived the Tenneco one-year filing requirement for a period of ninety (90) days following Tenneco. Petitioner’s filings at issue in this appeal were not made within the 90-day waiver period, and were made more than one year after the effective date of the property transfer. Accordingly, FERC applied the Tenneco policy and required the petitioners to refund any rate increases collected between the time of transfer and the time of filing. 44 F.E.R.C. II 61,100 (July 21,1988). FERC denied rehearing, 44 F.E.R.C. H 61,351 (Sept. 21, 1988), and petitioners seek review of FERC’s orders.

Substantive Issues

Petitioners challenge the merits of FERC’s decision to impose a one-year filing deadline and grant a 90-day waiver period following Tenneco. They correctly assert that FERC must provide a reasoned explanation to substantiate a change in policy. See Florida Gas Transmission Co. v. FERC, 876 F.2d 42 (5th Cir.1989). However, that explanation is not to be reversed unless it is arbitrary, capricious, or otherwise not in accordance with law. 5 U.S.C. § 706(2).

Petitioners also argue that FERC has not adequately explained its reasons either for the change in policy or for the 90-day waiver. We do not agree. FERC explained that in the absence of a deadline it must ignore or excuse sales by successors that are in violation of the NGA, and that its records remain inaccurate for lengthy periods of time. FERC further explained that the one-year time limit is consistent with 18 C.F.R. § 2.64(a), which provides that an assignor of non-producing property must obtain abandonment authorization from FERC unless the successor in *197 interest files an application for certificate authorization within one year from the date of the assignment. FERC explained that the 90-day waiver period following Tenne-co provides 30 days for rehearing in Tenne-co, 30 days for any FERC action on rehearing, and 30 days for successors to prepare and make the required filing. This reasoning supports FERC’s decisions to impose a one-year time limit for making successor filings and to grant a 90-day grace period following Tenneco. Neither is arbitrary or capricious.

Petitioners also argue that FERC impermissibly applied the change in policy retroactively. The Tenneco order on its face, however, only applies to future applicants who make late filings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
881 F.2d 193, 1989 U.S. App. LEXIS 12844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mobil-exploration-and-producing-north-america-inc-v-federal-energy-ca5-1989.