ANR Pipeline Co. v. Federal Energy Regulatory Commission

988 F.2d 1229, 300 U.S. App. D.C. 271
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 26, 1993
DocketNo. 91-1386
StatusPublished
Cited by1 cases

This text of 988 F.2d 1229 (ANR Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR Pipeline Co. v. Federal Energy Regulatory Commission, 988 F.2d 1229, 300 U.S. App. D.C. 271 (D.C. Cir. 1993).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

ANR Pipeline Co. and Colorado Interstate Gas Co., here referred to collectively as ANR, petition for review of the Federal Energy Regulatory Commission’s Orders No. 500-K and 500-L, FERC Stats. & Regs. 11 30,917 (1991) and 55 FERC H 61,489 (1991), objecting that those orders arbitrarily and capriciously ended petitioners’ ability to “apply” previously earned “take-or-pay credits”. The Commission says that in fact it resolved that issue no later than its Order No. 500-1, FERC Stats. & Regs. H 30,880 (1990); as ANR failed to file a timely petition for rehearing of that order (let alone a timely appeal), FERC says our jurisdiction is barred by Sections 19(a) and (b) of the Natural Gas Act, 15 U.S.C. §§ 717r(a), (b). We do not find Order No. 500-1 to be a model of clarity by a long shot; however, because we believe that an ordinary reader familiar with the industry background would have recognized a very substantial likelihood that the order meant what the Commission ultimately said it meant, we agree with the Commission that we have no jurisdiction over ANR’s challenge.

The background is well known in the industry. In 1985 FERC issued its Order No. 436, which established powerful incentives for pipelines to transport gas sold by producers in direct competition with gas sold by the pipelines themselves. Because Order No. 436 enabled producers to undercut the pipelines' own gas sales, it tended to increase the pipelines’ liability under take-or-pay clauses, which require them to pay producers even for volumes of gas [273]*273they do not take. In Associated Gas Distributors v. FERC, 824 F.2d 981 (D.C.Cir. 1987), this court vacated Order No. 436 and ordered FERC in any repromulgation of open access to address its effect on pipelines’ take-or-pay liability. Id. at 1021-30, 1044.

FERC responded with a succession of orders establishing a crediting system to mitigate the effects of open access. The orders in essence required producers that used the Commission’s open-access rules to agree to credit the volumes to be transported against the transporting pipeline’s take- or-pay liability. Order No. 500-H, FERC Stats. & Regs. ¶ 30,867 (1989), which made final the open access regulations that the Commission had previously issued on an interim basis, added what the Commission called a “sunset provision”:

Until the earlier of December 31,1990, or the date on which an interstate pipeline accepts a gas inventory charge certificate, natural gas is eligible for transportation by interstate pipelines under this part only if [the crediting system explained in the rest of the regulation is applied],

18 C.F.R. §§ 284.8(f)(1), 284.9(f)(1) (1991). On its face, the passage appears to mean no more than that transportation provided after December 31, 1990 cannot generate credits.

Numerous parties sought rehearing of Order No. 500-H, including a group called “Indicated Producers”, which sought clarification of the sunset clause. In answering the latter’s request, in Order No. 500-1, the Commission stated the producers’ question and its answer as follows:

Finally, Indicated Producers ask for clarification of Order No. 500-H to make clear that from and after the termination of crediting under the rule, a pipeline can no longer apply credits previously earned to relieve it of take- or-pay obligations which are then in existence or which may thereafter accrue. The Commission clarifies that this was its intent.

FERC Stats. & Regs. ¶ 30,880 at 31,710 (emphasis added).

On April 4,1991, FERC issued Order No. 500-K, which among other things provided that the take-or-pay crediting regulations, 18 C.F.R. §§ 284.8(f) and 284.9(f), would be deleted, and explained that Order No. 500-1 meant

not only that pipelines cannot seek credits for transportation performed after December 31, 1990, but also that they may not after December 31, 1990 apply against any take-or-pay liability previously unused credits generated■ by transportation performed before December 31, 1990.

FERC Stats. & Regs. ¶ 30,917 at 30,191-92 (emphasis added). This made unequivocally clear that pipelines could not apply credits after December 31, 1990 (or earlier receipt of a gas inventory charge certificate).

We note that even now the Commission appears not to have defined the meaning of “apply”. Its lawyers here say that a pipeline applies a credit at the point where it “announc[es] that the volumes it had transported would be treated as purchases under a specific contract and contract year.” Commission Supplemental Brief at 6. If the pipelines so specified before January 1, 1991, delay due to haggling between the parties over the amounts, or other causes, would not make the credits evaporate.

The petitioners sought clarification or rehearing of Order No. 500-K, which the Commission denied in Order No. 500-L. In so doing, it said that the time limit on application had been addressed in Order No. 500-1, that pipelines and producers were thus on notice that earned but unapplied credits could not be applied after that date, and that therefore it would not be “appropriate” for the Commission to revisit the issue. See 55 FERC at 62,695. ANR sought review in this court, contending that the Commission’s refusal to allow application of credits earned but not applied before December 31, 1990 was arbitrary and capricious.

Section 19(a) of the Natural Gas Act authorizes persons aggrieved by an order of the Commission to seek rehearing within 30 days, and further provides that no pro[274]*274ceeding to review a Commission order may be brought by any person who has failed to apply for such rehearing. Section 19(b) allows judicial review on filing a petition within 60 days of the Commission’s disposition of the application for rehearing, and adds that no objection may be considered on review unless it has been urged on the Commission in that application, unless there was “reasonable ground for failure to do so.” Thus, if Orders No. 500-K and 500-L merely repeated or slightly clarified what Order No. -500-1 had established, ANR’s failure to seek rehearing of Order No. 500-1 bars its petition here. See RCA Global Communications, Inc. v. FCC, 758 F.2d 722, 730 (D.C.Cir.1985) (prior order would bar review if it “disposed of the question with sufficient clarity to put [petitioner] on notice that failure to pursue its claim would bar” later review).

On its face and in hindsight it may seem plain that Order No. 500-1 barred application after December 31, 1990 of credits earned before that date. ANR argues, however, that that meaning is absolutely contradictory of other statements made by the Commission, statements that Order No. 500-1 made no effort to explain away; moreover, because of the character of producer-pipeline contractual relations, a December 31, 1990 time bar on applications of credits would sharply reduce the value of credits accrued during 1990. Accordingly, ANR says, a reader could not be expected to detect so bizarre a meaning.

Indeed, Order No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
988 F.2d 1229, 300 U.S. App. D.C. 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-pipeline-co-v-federal-energy-regulatory-commission-cadc-1993.