MMR Constructors, Inc. v. the Dow Chemical Company

CourtCourt of Appeals of Texas
DecidedDecember 3, 2020
Docket01-19-00039-CV
StatusPublished

This text of MMR Constructors, Inc. v. the Dow Chemical Company (MMR Constructors, Inc. v. the Dow Chemical Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MMR Constructors, Inc. v. the Dow Chemical Company, (Tex. Ct. App. 2020).

Opinion

Opinion issued December 3, 2020

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-19-00039-CV ——————————— MMR CONSTRUCTORS, INC., Appellant V. THE DOW CHEMICAL COMPANY, Appellee

On Appeal from the 412th Judicial District Court Brazoria County, Texas Trial Court Case No. 97962-CV

MEMORANDUM OPINION

MMR Constructors, Inc. sued The Dow Chemical Company for breach of

contact, quantum meruit, and statutory prompt payment violations related to

construction services that MMR provided to Dow on a project. MMR claims that

Dow owes it an additional $17 million above the agreed fixed-contract price of $40 million because MMR incurred increased costs when it was directed by Dow to

accelerate its work after Dow’s other contractors caused the work schedule to be

delayed.

The trial court granted Dow’s traditional motion for summary judgment,

which MMR now appeals. Based on the record, we hold that Dow proved, as a matter

of law, that (1) MMR released its breach-of-contract claim; (2) the express contract

between the parties precludes MMR’s quantum meruit claim; and (3) MMR’s

statutory prompt pay claim fails without a valid contract claim. Accordingly, we

affirm the trial court’s summary judgment.

Background

On February 4, 2016, Dow and MMR entered into a contract (“the Contract”)

for MMR to provide electrical and instrumentation construction work on Dow’s

Power, Utilities, and Infrastructure Project in Freeport, Texas. The Contract

specified that MMR would begin its work on March 1, 2016 and complete it by

March 3, 2017. The work to be provided by MMR was specified in the Contract.

Dow agreed to pay MMR the fixed price of $40,407,604 for the work. MMR

achieved mechanical completion of its work on March 10, 2017.

The Contract contemplated that it could be modified if the scope or timing of

MMR’s work changed during the project. The Contract also contemplated that it

could be modified to provide MMR with additional compensation if changes

2 affecting its work caused MMR to incur extra costs above the agreed fixed-contract

price. Parts III and IV of the Contract included provisions addressing when MMR

was entitled to additional compensation and set out the process by which MMR

could obtain additional compensation.

Part III of the Contract contained “General Terms,” and Part IV of the

Contract contained “Special Terms.” The Contract stated that Part IV–Special Terms

“set[s] forth herein modifications to specific Terms and Conditions that are

contained in Part III–General Terms. Such modifications take precedence over Part

III–General Terms.” The modifications made in the “Special Terms” are italicized

in the Contract to denote the modifications. The Contract provisions cited by the

parties relevant to issues in this case are as follows:

TIMING OF WORK

10.0 SCHEDULING, REPORTING AND COORDINATION

....

10.2 During the performance of Work, Contractor [MMR] shall submit to Company [Dow] periodic progress reports on the actual progress and updated schedules as may be required by this Contract or requested by Company. In the event Contractor’s performance of the Work is not in compliance with the schedule established for such performance, Company may, in writing, require the Contractor to submit its plan for schedule recovery, or specify in writing the steps to be taken to achieve compliance with such schedule, and/or exercise any other remedies under this Contract. Contractor shall thereupon take such steps as may be directed by Company or otherwise necessary to improve its progress without additional cost to Company or Owner. 3 Notwithstanding the sentence above, if Contractor’s performance of Work is delayed by Company, Owner, or other contractors, vendors or suppliers for which Company is responsible, then Contractor shall be compensated for such steps directed by Company to recover the schedule.

WORK CHANGES

15.0 CHANGES

15.1 The Scope of Work shall be subject to change by additions, deletions or revisions thereto by Company. Contractor will be notified of such changes by receipt of additional and/or revised drawings, specifications, exhibits or other written notification.

15.2 If, upon receipt of any notification, Contractor considers that a change is involved that could affect its costs of performing the Work or upon the schedule for performance of the Work, Contractor is obligated to inform Company within five (5) working days of Contractor receiving the notification. Unless Contractor notifies Company in accordance with this Section, Contractor is obliged to perform the Work in accordance with the change and will have no entitlement to any additional compensation or to any change to the schedule.

15.3 Contractor shall submit to Company within ten (10) working days after submission of the notification from Contractor required under Section 15.2, above, a detailed takeoff with supporting calculations and pricing for the change, together with any requested adjustments in the schedule. The pricing shall be itemized as required by Company and shall be in sufficient detail to permit an analysis of all labor, material and equipment and shall cover all work involved in the change, whether such work was deleted, added or modified. Amounts related to subcontracts shall be supported in similar detail. Any

4 adjustments to the schedule must be accompanied by a revised version of the detailed schedule, agreed in accordance with Section 10.1 demonstrating that any proposed changes to the schedule have been caused by the change and have affected a critical path on such previously agreed detailed schedule.

15.4 If Contractor does not provide the detailed take-off to Company, within the time allowed by Section 15.3, Contractor will have waived any right to additional compensation or to a change to the schedule, in respect of the change and will proceed with the work in accordance with the change notification issued pursuant to Section 15.1, above.

15.5 Contractor shall not perform changes in the Work in accordance with Section 15.1 until Company and Owner have approved in writing the pricing for the change and any adjustment in the schedule for performance of the Work, except as set forth in Sections 15.4 and 15.6. Upon receiving such written approval from Company and Owner, Contractor shall diligently perform the change in strict accordance with this Contract.

15.6 Notwithstanding Section 15.5 Company may expressly authorize Contractor in writing to perform the change prior to such approval by Company and Owner. Contractor shall not suspend performance of this Contract during the review and negotiation of any change, except as may be directed by Company pursuant to Article 16.0, Suspension of Work. In the event Company, Owner and Contractor are unable to reach timely agreement regarding any change, Contractor shall then comply with Article 18.0, Claims.

18.0 CLAIMS

5 18.1 If, for any reason, Contractor considers that an event has occurred pursuant to which it has a right to claim compensation from Owner or an extension to the schedule, Contractor shall notify Owner in writing of the existence of such claim within five (5) working days of the Parties’ failure to reach a timely agreement pursuant to Section 15.6 for changes or from Contractor learning of the occurrence of the event in question for other claims. Within ten (10) days of giving such a notification, or at a mutually agreed reasonable time, Contractor shall submit to Company the proposed cost and schedule effect of the change. In this respect, Contractor shall comply with the provisions of Section 15.3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Manufacturers Mutual Insurance Co. v. Schaefer
124 S.W.3d 154 (Texas Supreme Court, 2003)
Western Investments, Inc. v. Urena
162 S.W.3d 547 (Texas Supreme Court, 2005)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding
289 S.W.3d 844 (Texas Supreme Court, 2009)
Baty v. ProTech Insurance Agency
63 S.W.3d 841 (Court of Appeals of Texas, 2002)
Williams v. Glash
789 S.W.2d 261 (Texas Supreme Court, 1990)
Houston First American Savings v. Musick
650 S.W.2d 764 (Texas Supreme Court, 1983)
Centeq Realty, Inc. v. Siegler
899 S.W.2d 195 (Texas Supreme Court, 1995)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Victoria Bank & Trust Co. v. Brady
811 S.W.2d 931 (Texas Supreme Court, 1991)
State Farm Life Insurance Co v. Beaston
907 S.W.2d 430 (Texas Supreme Court, 1995)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
Lenape Resources Corp. v. Tennessee Gas Pipeline Co.
925 S.W.2d 565 (Texas Supreme Court, 1996)
HOLY CROSS CHURCH OF GOD IN CHRIST v. Wolf
44 S.W.3d 562 (Texas Supreme Court, 2001)
Memorial Medical Center v. Keszler
943 S.W.2d 433 (Texas Supreme Court, 1997)
Doe v. TEXAS ASS'N OF SCHOOL BOARDS, INC.
283 S.W.3d 451 (Court of Appeals of Texas, 2009)
Union Pacific Railroad v. Novus International, Inc.
113 S.W.3d 418 (Court of Appeals of Texas, 2003)
Dardas v. Fleming, Hovenkamp & Grayson, P.C.
194 S.W.3d 603 (Court of Appeals of Texas, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
MMR Constructors, Inc. v. the Dow Chemical Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mmr-constructors-inc-v-the-dow-chemical-company-texapp-2020.