MMM Electric Inc. v. EMF Electric Co.

2020 IL App (1st) 182499-U
Appellate Court of Illinois·Decided March 5, 2020·No. 1-18-2499·Unpublished

Opinion

2020 IL App (1st) 182499-U No. 1-18-2499

Order filed March 5, 2020 Fourth Division

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST DISTRICT

MMM ELECTRIC INC., ) Appeal from the ) Circuit Court of

Plaintiff-Appellee, ) Cook County.

)

v. ) No. 16 L 3938 )

EMF ELECTRIC COMPANY, ) Honorable ) Daniel J. Kubasiak,

Defendant-Appellant. ) Judge, presiding.

JUSTICE LAMPKIN delivered the judgment of the court.

Presiding Justice Gordon and Justice Burke concurred in the judgment.

ORDER

¶1 Held: The trial court’s determination that the defendant contractor received and unjustly retained a $37,000 benefit from the work provided by the plaintiff electrical subcontractor was not against the manifest weight of the evidence.

¶2 After a bench trial, the trial court awarded a judgment of $37,000 in favor of plaintiff, MMM Electric Inc., on its unjust enrichment claim against defendant, EMF Electric Company.

¶3 On appeal, defendant argues the judgment must be reversed because the trial court erred as a matter of law by using an incorrect measure of damages to award plaintiff $37,000 on its unjust

enrichment claim. In the alternative, defendant argues that the $37,000 judgment should be reversed because the record is devoid of any evidence of the actual unpaid hours of labor plaintiff and its laborers provided to defendant.

¶4 For the reasons that follow, we affirm the judgment of the circuit court. 1

¶5 I. BACKGROUND

¶6 This dispute arose from an alleged agreement between defendant, an electrical subcontractor, and plaintiff, the sub-subcontractor, concerning electrical work plaintiff performed at a five-building residential project in Aurora, Illinois.

¶7 Plaintiff sued defendant for breach of contract and unjust enrichment. According to plaintiff’s 2018 third-amended complaint, it had a history of working with defendant since 2009. In February 2015, they entered into an oral contract for plaintiff to perform electrical work for the common areas and 417 units of the five buildings. Plaintiff alleged they agreed to an “equivalent hours” payment arrangement, whereby the completion of each unit would require an equivalent of 82 hours of work at the rate of $22 per equivalent hour, for a total of $752,268 based on 34,194 total equivalent hours. Regarding the common areas of the five buildings, the parties agreed to a sum of $528,000 based on 24,000 total equivalent hours of work at the rate of $22 per equivalent hour. Plaintiff also alleged the parties agreed to the same payment practice they had used on prior projects, whereby defendant would make monthly payments to plaintiff based upon the percentage of the project that plaintiff completed. Specifically, plaintiff would inform defendant of the

1 In adherence with the requirements of Illinois Supreme Court Rule 352(a) (eff. July 1, 2018), this appeal has been resolved without oral argument upon the entry of a separate written order.

percentage of the work plaintiff had completed, and then defendant would bill the general contractor and, upon receiving payment, pay plaintiff for the services provided.

¶8 Plaintiff alleged that it provided services on this project from February 5 to April 23, 2015, equivalent to 6,140 hours of work, totaling $135,080, and requested payment from defendant. However, defendant paid plaintiff a total of only $31,675 and retained the balance of the money defendant received from the general contractor. Despite plaintiff’s repeated demands, defendant refused, without any good faith basis, to pay the $103,405 balance due.

¶9 Plaintiff alleged that defendant (count I) breached its agreement by failing to pay the $103,405 balance due, (count II) breached its agreement by failing to pay plaintiff on a monthly basis so it could retain its workers and by refusing to allow plaintiff access to the worksite, which resulted in $364,783 in lost profits damages to plaintiff, and (count III) unjustly retained the $103,405 it had billed and received from the general contractor based on the work plaintiff had performed.

¶ 10 Plaintiff attached as an exhibit to its complaint the contract between defendant and the general contractor. According to this contract, defendant would be paid $3,750,000 in progress payments, whereby defendant would submit to the general contractor an application for payment for the value of the work completed and the percentage of completion of each portion of defendant’s work as of the end of the period covered by the application. The general contractor had the right to inspect the work. If defendant submitted the application by the 15th of the month, then the general contractor would include the work covered by that application in the next application for payment the general contractor was entitled to submit to the architect. If the architect issued a certificate for payment for work properly performed, then the general contractor

would pay defendant each progress payment no later than 10 working days after the general contractor received the payment from the owner.

¶ 11 Defendant denied any liability to plaintiff and filed a counterclaim that alleged (count I) plaintiff breached its agreement by failing to pay its subcontractor electricians, which resulted in defendant having to pay the electricians an additional $21,549; (count II) plaintiff was unjustly enriched by defendant’s $19,000 advance payments for labor, which plaintiff failed to use to pay its subcontractor electricians; (count III) plaintiff was liable for conversion because it failed to use the $19,000 advance payments for work at the Aurora project and instead used the money for its own purposes; and (count IV) plaintiff never intended to pay its electricians the $19,000 advance it fraudulently induced defendant to pay, and then defendant, under duress to ensure the timely completion of the electrical work on the project, had to directly pay the electricians $21,549.

¶ 12 Defendant moved the court for summary judgment, arguing that plaintiff had no evidence to support the value of its work or the percentage of the work it completed and could not pursue a claim for quantum meruit based on speculative evidence. Defendant contended that it was entitled to summary judgment because plaintiff could not prove the elements of its unjust enrichment claim.

¶ 13 Plaintiff responded that summary judgment was precluded by genuine issues of material fact regarding the existence of a contract between the parties and their agreement concerning advance payments.

¶ 14 The trial court denied defendant’s motion for summary judgment, finding that questions of fact existed regarding whether a handwritten memorandum constituted a written agreement that

preempted plaintiff’s unjust enrichment claim and whether plaintiff presented a reasonable basis for computing damages.

Free access — add to your briefcase to read the full text and ask questions with AI

MMM Electric Inc. v. EMF Electric Co., 2020 IL App (1st) 182499-U (Ill. Ct. App. 2020).

2020 IL App (1st) 182499-U (MMM Electric Inc. v. EMF Electric Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Raintree Homes, Inc. v. Village of Long Grove
807 N.E.2d 439 (Illinois Supreme Court, 2004)
Gass v. Anna Hospital Corp.
911 N.E.2d 1084 (Appellate Court of Illinois, 2009)
Alliance Acceptance Co. v. Yale Insurance Agency, Inc.
648 N.E.2d 971 (Appellate Court of Illinois, 1995)
Eychaner v. Gross
779 N.E.2d 1115 (Illinois Supreme Court, 2002)
Rutledge v. Housing Authority
411 N.E.2d 82 (Appellate Court of Illinois, 1980)
Perez v. Citicorp Mortgage, Inc.
703 N.E.2d 518 (Appellate Court of Illinois, 1998)
Martis v. Grinnell Mutual Reinsurance Co.
905 N.E.2d 920 (Appellate Court of Illinois, 2009)
Hayes Mechanical, Inc. v. First Industrial, L.P.
812 N.E.2d 419 (Appellate Court of Illinois, 2004)