Mitten v. Caswell-Runyan Co.

99 N.E. 47, 52 Ind. App. 521, 1912 Ind. App. LEXIS 257
CourtIndiana Court of Appeals
DecidedJune 28, 1912
DocketNo. 7,615
StatusPublished
Cited by15 cases

This text of 99 N.E. 47 (Mitten v. Caswell-Runyan Co.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitten v. Caswell-Runyan Co., 99 N.E. 47, 52 Ind. App. 521, 1912 Ind. App. LEXIS 257 (Ind. Ct. App. 1912).

Opinion

Felt, J.

This was an action brought by the Caswell-Runyan Company against Lewis C. Mitten and his sureties upon a certain contractor’s bond, given for the construction of certain buildings. •

[522]*522From a judgment for $2,000 this appeal was taken. The errors assigned are: (1) The overruling of appellants’ demurrer to the amended complaint; (2) the overruling of appellants’ demurrer to' the second paragraph of appellee’s reply to the second and third paragraphs of appellants’ answer; (3) error in the conclusion of law; (4) error in overruling appellants’ motion for a venire de novo; (5) overruling the motion for a new trial.

Appellants, other than Mitten, also made the same assignments of error, and each appellant separately excepted to each conclusion of law and separately assigned error thereon.

The complaint sought a recovery on a contractor’s bond, and alleged a breach thereof in suffering and permitting certain mechanics’ liens to be filed against the buildings erected for appellee by appellant Mitten. The complaint states a cause of action against all the appellants. To this complaint all the appellants answered by general denial. They also filed second and third paragraphs of answer as pleas of former adjudication. The second was a partial answer, in which the execution of the building contract and the bond sued on was admitted, but it was further averred, in substance, that on or about January 23, 1908, appellant Mitten sued appellee on said contract, and alleged full performance therof on his part and the furnishing to appellee of a large amount of extra labor and material not covered by the original contract; that in said action appellee filed an answer in seven paragraphs, the last of which was by way of counterclaim and set-off; that in said answer it made said contract and the bond here sued on exhibits, and alleged that said Mitten had violated said contract and bond in this, that he had failed to pay for the labor and material used in the construction'of the buildings covered by the contract; that he had not kept the same free from mechanics’ liens, but had suffered bills to be and remain unpaid, and liens therefor in the sum of $1,500 to be filed against said prop[523]*523erty. It is also averred that the contract and bond mentioned in this suit are the identical contract and bond set out in and made a part of said counterclaim in said other suit, and the liens mentioned and described in said counterclaim are the identical liens and claims mentioned and described in the complaint in this suit; that appellant Mitten demurred to said counterclaim filed in said former suit; that his demurrer was overruled, and he thereupon filed a reply in general denial; that said cause ivas thereafter duly tried in the Huntington Circuit Court, and on June 17, 1908, the court made a general finding against said Mitten on his complaint and for said Caswell-Runyan Company on its special answer in the sum of $184.57, and accordingly rendered judgment in its favor against said Mitten for that amount; that said judgment was never appealed from and is in full force and effect, and is res judicata of the claim sued on in this action.

The third paragraph of answer set up the plea of former adjudication in general terms, and averred the identity of the parties and the subject-matter of the two suits.

The sureties on said bond — appellants other than said Mitten — set up a special paragraph of answer, in which they admitted the execution of said bond to secure the performance of said builder’s contract by 'said Mitten, but alleged that thereafter and without their consent the buildings were materially changed by alterations and additions, and the cost thereof materially increased, so that the same were wholly different from the buildings for which* said contract was executed and for which they became bondsmen; that by reason thereof they are released from liability on said bond.

Appellee’s second paragraph of reply to the second and third paragraphs of answer admits that in the suit by said Mitten against appellee mentioned in said paragraphs of answer, it did file the answer as alleged, and that in said suit there was a finding and judgment for said Caswell-[524]*524Runyan Company, but it further avers that there was a large number of other issues in said cause, including answers by general denial and payment, paragraphs of set-off and counterclaim, besides the paragraph of set-off and counterclaim described in the answer as aforesaid; that said finding and judgment in favor of said company were on said other issues and not on the answer referred to as aforesaid ; that the court which tried said former cause expressly refused to receive any evidence on any of the matters set forth in said counterclaim and in the complaint herein, and refused to pass on, consider or decide any of said matters, but on the contrary said cause was decided "by said court wholly upon the evidence adduced by plaintiff under its other answers in said cause, as to the value of the labor and material furnished by said Lewis O. Mitten to the plaintiffs and the payments made to him thereon by the plaintiffs. And the plaintiff further avers that the judgment in said former cause does not show, on its face, upon what issues in the cause it was rendered and what issues the court considered and adjudicated. And so the plaintiff says that none of the matters set forth in the complaint in this cause were heard, tried, determined or adjudicated in said former cause.”

A demurrer for want of sufficient facts was overruled to said paragraph of reply. The court heard evidence in support thereof and made a special finding of facts, in which it found the facts to be substantially as therein alleged. The finding states in detail facts showing a breach of the bond, failure to pay hills and certain mechanics’ liens on the buildings for which said contract was executed and said bond given; that liens for labor and material amounting to $1,579.89 have been foreclosed, and said Mitten has paid no part thereof; hut has himself filed a lien on said buildings for $3,200. The court also found that changes were made in said building, but were immaterial matters of detail; that in said former suit said Mitten sought to recover the con [525]*525tract price aforesaid and additional compensation for labor and material made necessary by said changes and alterations; that the issues in said former suit were tried by the lion. Samuel E. Cook, judge of the Huntington Circuit Court; that both parties adduced evidence on the subject of the alterations and changes aforesaid; that as a result of such trial judgment was rendered for Caswell-Runyan Company against said Mitten for $184.57, which is unreversed and unappealed from. On .the facts so found the court stated its conclusions of law in favor of said appellee, and gave judgment in this suit in its favor for $1,579.89.

The controlling question, raised in different ways by the several assignments of error, is that of former adjudication. Put in another form the question is, May a trial court, where matter is plainly in issue by unambiguous pleadings, make a general finding on all the issues, so far as shown by the record, and render judgment accordingly, and in a subsequent suit the same matter be put in issue by pleadings, and parol testimony be admitted to show that the matter though in issue in the first suit was not in fact adjudicated, and that the judgment so rendered was on other issues, and the matter so in issue was not in fact considered and adjudicated?

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gescheidler v. National Casualty Co.
96 N.E.2d 123 (Indiana Court of Appeals, 1951)
Lagura v. Deutsch
176 N.E. 39 (Indiana Court of Appeals, 1931)
City of Bridgeport v. United States Fidelity & Guaranty Co.
134 A. 252 (Supreme Court of Connecticut, 1926)
Grabowski v. Benzsa
80 Ind. App. 214 (Indiana Court of Appeals, 1923)
Trook v. Crouch
137 N.E. 773 (Indiana Court of Appeals, 1923)
Knotts v. Clark Construction Co.
131 N.E. 921 (Indiana Supreme Court, 1921)
Williams v. Harrison
123 N.E. 245 (Indiana Court of Appeals, 1919)
Hedges v. Mehring
115 N.E. 433 (Indiana Court of Appeals, 1917)
Denney v. Reber
114 N.E. 424 (Indiana Court of Appeals, 1916)
Bump v. McGrannahan
111 N.E. 640 (Indiana Court of Appeals, 1916)
Hitt v. Carr
109 N.E. 456 (Indiana Court of Appeals, 1915)
Paul v. Barnbrook
106 N.E. 425 (Indiana Court of Appeals, 1914)
Town of Clarksville v. Ohio Falls Hydraulic Manufacturing Co.
105 N.E. 67 (Indiana Court of Appeals, 1914)
Larimer v. Krau
103 N.E. 1102 (Indiana Court of Appeals, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
99 N.E. 47, 52 Ind. App. 521, 1912 Ind. App. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitten-v-caswell-runyan-co-indctapp-1912.