Mitchell v. Dougherty

90 F. 639, 33 C.C.A. 205, 1898 U.S. App. LEXIS 1721
CourtCourt of Appeals for the Third Circuit
DecidedDecember 6, 1898
DocketNo. 18
StatusPublished
Cited by13 cases

This text of 90 F. 639 (Mitchell v. Dougherty) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Dougherty, 90 F. 639, 33 C.C.A. 205, 1898 U.S. App. LEXIS 1721 (3d Cir. 1898).

Opinion

DALLAS, Circuit Judge.

This case is before us on writ of error to the judgment of the circuit court for the Eastern district of Pennsylvania in an action by Frank A. Mitchell, plaintiff in error, against William R. Dougherty, defendant in error. Dougherty on May 15, 1896, had contracted with Archbishop Ryan for the erection of a certain building; and on May 22, 1896, the plaintiff, Mitchell, agreed with the defendant, Dougherty, to do a certain portion of the work, and furnish the materials therefor. Both contracts were in writing. The one between Archbishop Ryan and William R. Dougherty provided as follows:

“It is mutually agreed between the parties to this agreement that if any alterations, additions, or omissions are made in the work during its progress, the value of the same shall be decided by the engineers and architects, who shall make an equitable allowance therefor, and shall add the amount of said allowance to the contract price if the cost of the work has been increased, or shall deduct the amount from the contract price if the cost of the work has been lessened, as they, the said engineers and architects, may deem just and equitable. And it is mutually agreed and distinctly understood that the decision of the engineers and architects shall be final and conclusive in any dispute which may arise between the parties to this agreement relative to or touching the same; and each and every of said parties do hereby waive any right of action, suit or suits, or other remedy, in law or otherwise, by virtue of said covenants, so that the decision of the said engineers and architects shall, in the nature of an award, he final and conclusive on the rights and claims of said parties.”

The contract between the plaintiff and the defendant recited and provided as follows:

“Whereas, the said Dougherty has entered into articles of agreement with his (trace. Most Reverend P. J. Iiyan, hearing date the fifteenth day of May, 189(>, for the erection of certain brick buildings at Eatland, Pa., known as the ‘R. C. Protectory,’ according to certain plans and specifications therein re[640]*640ferred to, .which said articles of agreement, plans, and specifications are to be considered as if hereto attached, and made as much a part of this contract as if specially recited herein, all information concerning same being known to the said Frank A. Mitchell; and whereas, the said Frank A. Mitchell has agreed to subcontract with the said Dougherty for a certain portion of the work and materials necessary to be'supplied by him in the erection and completion of the said building; and whereas, it has been agreed that, as to so much hereof as has been thus subcontracted for, the said Frank A. Mitchell, for the consideration hereinafter named, is, as between himself and the said Dougherty, to stand in the place of the latter, and to do everything in, about, and concerning the same as is provided in said Dougherty’s contract with said Archbishop P. J. 'Ryan, subject to all its terms and restrictions, so that the said Dougherty shall be indemnified and saved harmless from all loss, costs, and charges in and about said portion of work and materials: Now, this agreement witnesseth that the said parties do hereby, in consideration of the premises, and of the mutual covenants herein contained, covenant, promise, and agree to and. with each other, each binding himself, his heirs, executors, and administrators and assigns, to the other, his heirs, executors, administrators, or assigns, as follows: (1) The said Frank A. Mitchell further agrees to furnish all the labor and material necessary to complete all the roof work, galvanized iron, copper, tile, and tin, etc., in strict accordance with plan and specifications prepared and shown by Wilson Bros. & Co., and to their entire satisfaction. * * * The said Archbishop J. Ryan having the right to add to, change, or modify any part of the plans of aforesaid building during its progress, the said Frank A. Mitchell will do what shall thus in the above-specified matters be entailed upon the said Dougherty; and any such modifications shall not affect this contract, in regard to the considerations, the time for completion, or other matter, unless a specified agreement making provision for the same shall be reduced to writing, and signed by the parties hereto.”

The plaintiff entered upon the work which he had undertaken to perform, but after he had been engaged in it for about six weeks he was required by the defendant to proceed no further until the owner should decide whether a sort of tile different from that named in the contract would not be used. The plaintiff was also requested to present an estimate of the cost of making the contemplated substitution, and in January, 1897, he did present such an estimate. The matter was then held under consideration until March 31, 1897, when the defendant addressed to the plaintiff a letter as follows;

“Philadelphia, March 31, 1897.
“Mr. Frank A. Mitchell, 104 West Fifth Street, Wilmington, Del.—Dear Sir: The architects have declined to consider at this time the question of what allowance is to be made for the placing of the Celadon tile, instead of the Ludowici, upon the Protectory buildings at Fatland. As matters present themselves to me to-day,' I find the condition to be that the change will have to be made immediately, and the work prosecuted. While I have received from them no direct statement that they will not pass upon the claim, they have intimated that the future will be the proper time for them to consider it, and are now engaged in getting estimates from other people for the purpose of having some one else do the work. It is necessary, therefore, thstt the work of laying the Celadon tile should be commenced at once. The Celadon people, — having knowledge for some time back, from Wilson Bros., that their tile was to be used, — I believe, are in shape to make an immediate shipment. I have therefore ordered to-night that some tile be shipped, so as to prevent Wilson Bros., if, possible, from taking the work out of our hands. The position in the matter is just this: That what, if anything, is to be allowed for the change, is to be fixed by the architects in the future. What I get, you are to receive; and, in presenting your claim to them, I let be distinctly known that, while adopting it as my claim, I did so as it was the amount you stated it would take to make the change. I have ordered from the Celadon people, feeling that in this matter I am protecting your in[641]*641terests as well as my own, brea use, as you know, your contract places you in your dealings with me in the position time 1 occupy with the owner.
‘•Yours, truly, William It. Dougherty.”

Plaintiff declined to proceed in accordance with the proposed substitution, without an agreement making provision for the same, and in this he was dearly justified by the express terms of his contract. The court below appears to have so under-stood the matter at the time of the trial, for the learned judge charged that:

“If the plaintiff was prevented going oil to complete the work by being required tu subsüuite a different description of tile, and the owner oí the property declining to agree upon the cost of this substitution, then the plaintiff was justiiied in discontinuing; the work, and was not required to proceed until the cost, had been agreed upon, and the agreement reduced to writing, because, if he had thus proceeded, he would have been precluded by the strict terms of his contract from recovering anything on that account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)
McCullough v. Clinch-Mitchell Const. Co.
71 F.2d 17 (Eighth Circuit, 1934)
Rae v. Luzerne County
58 F.2d 829 (M.D. Pennsylvania, 1932)
Martin Hotel Co. v. Commissioner
18 B.T.A. 826 (Board of Tax Appeals, 1930)
Tatsuuma Kisen Kabushiki Kaisha v. Prescott
4 F.2d 670 (Ninth Circuit, 1925)
State v. Kisselburg
233 P. 580 (Arizona Supreme Court, 1925)
Haskell v. McClintic-Marshall Co.
289 F. 405 (Ninth Circuit, 1923)
Hart v. American Concrete Steel Co.
278 F. 541 (E.D. New York, 1921)
Jefferson Fire Ins. v. Bierce & Sage, Inc.
183 F. 588 (U.S. Circuit Court for the District of Eastern Michigan, 1910)
Jonathan Clark & Sons Co. v. City of Pittsburgh
146 F. 441 (U.S. Circuit Court for the District of Western Pennsylvania, 1906)
City of Elizabeth v. Fitzgerald
114 F. 547 (Third Circuit, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
90 F. 639, 33 C.C.A. 205, 1898 U.S. App. LEXIS 1721, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-dougherty-ca3-1898.