Mitchell v. Davis

80 S.E. 491, 73 W. Va. 352, 1913 W. Va. LEXIS 199
CourtWest Virginia Supreme Court
DecidedDecember 9, 1913
StatusPublished
Cited by6 cases

This text of 80 S.E. 491 (Mitchell v. Davis) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Davis, 80 S.E. 491, 73 W. Va. 352, 1913 W. Va. LEXIS 199 (W. Va. 1913).

Opinion

Williams, Judge:

Plaintiffs, A. B. Mitchell and A. E. Adkins, partners in a logging contract, recovered a judgment against H. A. Davis, [353]*353W. H. Muth and L. S. Davis, partners trading as the Gem Lumber Company, for the sum of $260.34, and they were awarded this writ of error. Defendants were engaged in the manufacture and sale of lumber, and had constructed a tram-road extending from their sawmill, up- a stream into some standing timber which they had purchased. They employed A. B. Mitchell and Joseph McNeeley on April 21, 1910, to cut, haul and place the timber on sfeids at their mill, at the price of $5.00 per thousand feet, log scale. Mitchell and McNeeley were to use the tramroad over which to haul the logs.. It was also mutually agreed that, if they should fail to place on skids, at the mill, at least 8,000 feet per day, or if defendants should fail to saw that much per day, the party so failing should forfeit to the other seventy-five cents per 1,000 feet for the shortage, but that said forfeit was not to apply in case of any hinderance in the work beyond the control of the party. By consent of all parties, McNeeley retired from the contract about the last of November, 1910, and A. E. Adkins took his place. Payments were to be made on the 15th of the month following that in which the work was done.

This action was brought on 6th April, 1911, to recover the price claimed for logs delivered in December, 1910, and in January and February, 1911. Plaintiffs had delivered 139,191 feet in those months. The action was brought in a justice’s court and, after judgment by the justice, appealed to the circuit court. Summons was issued for $300.00, and plaintiffs’ account filed showed a balance due them of $318.70. It is argued that this fact shows that the amount was beyond the jurisdiction of a justice. Defendants moved to dismiss the action on this ground, and the court overruled the motion. This was not error. In civil actions, the amount demanded by the summons determines the justice’s jurisdiction. Moore v. Harper, 42 W. Va. 39; Todd v. Gates, 20 W. Va. 464. Plaintiffs had a right to release a part of their claim, which they did, in order to bring it within the jurisdiction of a justice. Richmond v. Henderson, 48 W. Va. 389.

Defendants sought to recoup damages on account of plaintiffs’ shortage in delivery of logs, and filed a claim of recoupment and offsets amounting to-more than plaintiffs’ demand, [354]*354but the jury found against them. The principal assignment of error urged by their counsel, both in brief and in oral argument, is that the court erred in overruling defendants’ motion to set aside the verdict and grant them a new trial, on the ground that the verdict is against the evidence.

Plaintiffs stipulated in writing what they should forfeit for failing to deliver 8,000 feet of logs per day. It is virtually admitted by plaintiffs’ counsel that this was intended by the parties as liquidated damages, and was not a penalty to secure performance of the contract, in which latter case defendants’ recovery would be limited to a less sum than that stipulated, provided their actual damages were less. That plaintiffs failed to deliver 8,000 feet per day is admitted. There are seventy-seven work days in the three months covered by plaintiffs’ claim, and if they had delivered an average of 8,000 feet per day for that number of days, the total amount would have been 616,000 feet; whereas they delivered only 139,190 feet, thus falling short 476,810 feet. That quantity, at seventy-five cents per thousand, would amount to $357.60, which is more than plaintiffs demand; and, unless plaintiffs have proven, to the satisfaction of the jury, a lawful excuse for their failure to comply with that part of their contract, the verdict should have been for defendants, and they should have been discharged. The principal question is: Does the evidence justify the jury in concluding that plaintiffs’ failure was due to the acts and conduct of defendants, or their agents and employees? It is not claimed that plaintiffs were providentially hindered. But there is evidence tending to prove that a sufficient quantity of logs were cut and placed on the skids along the tramroad; that the man employed to truck them to the mill failed to deliver them; and that this trucker was employed and paid by defendants.

By the terms of the agreement plaintiffs were to use defendants’ tramroad to get the logs to the mill; defendants also used it, at the same time, to haul their lumber from the mill to market. They trucked the lumber up the tramroad to a point where it was carried over the mountain by an hoisting engine to a railroad on another stream. There being but one line of tramroad, it was impracticable to have two men trucking over it in opposite directions at the same time. One trucker would [355]*355save time and expense, as it would not be necessary for him to haul an empty truck either way. Consequently it was mutually agreed, after the original contract was made, that one man should do all the trucking. Different men were employed at different times to do this, the last one being a man named Linkous. The jury could properly infer from the evidence that he was the servant of defendants. He was paid sixty cents per thousand feet for trucking logs to the -mill, and a certain other price per thousand for trucking the lumber to the hoisting engine. • With the exception of one time when Mitchell sent him a check, Linkous was paid by defendants and the amount.paid him on plaintiffs’ account, to-wit sixty cents per thousand, charged against them. Mr. Mitchell swears: “We took their man to do our trucking by agreement with them, ” # * * # “Mr. Davis paid him and charged us up with it.” A man named Woodyard seems to have had the contract to do the trucking at one time, and he employed other men to do the work. L. S. Davis admits, in his testimony, that they had a contract with Wood-yard to do the trucking, but says he did not employ Linkous. But he is here evidently testifying to a conclusion, which he has incorrectly drawn, for he admits that Linkous took over the Woodyard contract, with defendants’ consent. It also appears that, before plaintiffs quit the job, defendants bought Linkous’ teams and undertook to do the trucking themselves and charged plaintiffs seventy-five cents per thousand feet. The exact terms of the Woodyard contract do not appear, but that it was made between him and defendants, the’ jury could well believe. Defendants admit that Linkous had acquired Woodyard’s rights under that contract, with their assent, and that he was operating under it. Such arrangement was carried on with the tacit consent, if not expressed agreement, of all parties, and amounted to a modification, pro tanto, of the original contract" between plaintiffs and defendants. Inasmuch as defendants had employed Linkous, and were paying him for all his services, they had a right to discharge him, if his work was not satisfactory. Plaintiff® had no right to discharge him; neither was it practicable, so long as he was retained by defendants, to employ a different man to haul the logs to the mill. In view of these facts and circumstances, [356]*356the jury were justified in believing that plaintiffs were prevented from performing their contract, according to its terms,.' by the acts of defendants, their agents and servants. This being true, the law does- not hold plaintiffs liable in damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crawford v. Taylor
75 S.E.2d 370 (West Virginia Supreme Court, 1953)
State Ex Rel. Shawver v. Casto
68 S.E.2d 673 (West Virginia Supreme Court, 1952)
Reynolds v. Miller
135 S.E. 280 (West Virginia Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
80 S.E. 491, 73 W. Va. 352, 1913 W. Va. LEXIS 199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-davis-wva-1913.