Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC
Opinion
Court of Appeals
Tenth Appellate District of Texas
10-24-00350-CV
Mitchell Construction Company, Inc, Appellant
v.
Superior Commercial Concrete, LLC, Appellee
On appeal from the
170th District Court of McLennan County, Texas Judge Jim Meyer, presiding Trial Court Cause No. 2024-130-4
CHIEF JUSTICE JOHNSON delivered the opinion of the Court.
MEMORANDUM OPINION
Superior Commercial Concrete, LLC (Superior) sued Mitchell Construction Company, Inc. (Mitchell) and Messer, LLC (Messer) seeking payment for work performed by Superior on a construction project. Mitchell now brings this interlocutory appeal contending the trial court erred when it denied Mitchell’s motion to compel arbitration and subsequent motion to reconsider. We will reverse and remand.
A. Factual and Procedural Background Messer contracted with Mitchell to serve as general contractor on a commercial construction project. Mitchell apparently put the project out for bids and Superior’s bid to do the concrete work on the project was accepted. Mitchell then presented Superior with a draft of a proposed written contract (hereinafter “subcontract”) to memorialize their agreement regarding the project. Superior returned an unsigned redlined version of the proposed written subcontract to Mitchell that included some revisions and comments. Mitchell nor Superior ever signed a written subcontract. Despite that, the parties moved forward with the project.
Superior filed suit in January 2024 against Mitchell and Messer alleging that both defendants “failed and refused to compensate” Superior for its services. Superior’s claims against Mitchell included breach of contract, breach of fiduciary duty under the Texas Construction Trust Fund Act; conversion; and unjust enrichment. Superior’s claim against Messer included claims for quantum meruit and foreclosure of its statutory and constitutional liens.
In October 2024, Mitchell filed a motion to compel arbitration based on an arbitration clause within both the original draft and redlined draft of the proposed written subcontract. In support, Mitchell attached the redlined version of the draft of the proposed written subcontract. Superior filed a
response to the motion to compel arbitration in which it was Superior’s contention that the proposed written subcontract was never formalized because the parties never signed the proposed written subcontract. Superior argued that because of Mitchell’s failure to establish the existence of a valid arbitration agreement the trial court should deny the motion to compel arbitration. During the hearing in the trial court, Superior reiterated that the parties never signed the proposed written subcontract, so there was no formal finalized agreement. Mitchell argued that if the parties acted in accordance with the proposed written subcontract, then the lack of signatures does not bar enforcement of an arbitration provision. The trial court denied Mitchell’s motion to compel arbitration.
Next, Mitchell requested that the trial court reconsider its denial of the motion to compel arbitration asserting that (1) because Superior is seeking benefits under the contract it is estopped from avoiding arbitration, and (2) `Superior’s act of signing change orders that referenced the unsigned subcontract resulted in the incorporation by reference of all terms of the subcontract. In support, Mitchell presented eight change orders signed by a representative of Superior; seven invoices from Superior; and eight bids from
Superior that correspond with the change orders. 1 Each change order included language as follows:
Except for such CHANGES as are set forth herein, all of the terms and conditions of your SUBCONTRACT, and as it may have been heretofore modified in writing, shall be and remain the same.
Unless specifically provided for herein, no extension of time for the completion of this SUBCONTRACT by reason of this CHANGE ORDER is allowed.
Near the bottom, the change order stated that the “foregoing CHANGE ORDER is ACCEPTED upon the terms and conditions above stated and those in the original SUBCONTRACT.” Both parties signed each of the change orders.
In Superior’s response to Mitchell’s motion to reconsider, it argued that “directs-benefits estoppel” is a narrow exception that does not apply here. Superior argued that it was not suing under the unsigned draft of the proposed written contract but was suing for breach of an implied or oral contract. After a hearing on the motion to reconsider, the trial court denied Mitchell’s motion.
B. Standard of Review
We review interlocutory orders denying motions to compel arbitration for abuse of discretion—deferring to the trial court’s factual determinations if they are supported by the evidence—and reviewing questions of law de novo. Henry v. Cash Biz, LP, 551 S.W.3d 111, 115 (Tex. 2018). A trial court abuses
1 Mitchell also supplied an affidavit certifying the exhibits.
its discretion if it acts in an arbitrary or unreasonable manner or acts without reference to any guiding rules and principles. Cire v. Cummings, 134 S.W.3d 835, 838–39 (Tex. 2004). When a trial court improperly denies a party’s right to arbitrate based on a valid and enforceable arbitration agreement, the court has abused its discretion. In re Whataburger Restaurants LLC, 645 S.W.3d 188, 194 (Tex. 2022) (orig. proceeding). Whether an arbitration agreement is valid and enforceable is a legal question subject to de novo review. Baby Dolls Topless Saloons, Inc. v. Sotero, 642 S.W.3d 583, 586 (Tex. 2022) (per curiam).
C. Issue Two
Mitchell contends the trial court erred in denying its motion to compel arbitration because the terms of the proposed written subcontract were referenced, incorporated, and affirmed by Superior. 1. Authority To compel arbitration, a party must first prove that a valid arbitration agreement exists. Aerotek, Inc. v. Boyd, 624 S.W.3d 199, 204 (Tex. 2021). To do so, courts apply state contract law principles. Cerna as Next Friend of R.W. v. Pearland Urban Air, LLC, 714 S.W.3d 585, 589 (Tex. 2025). Under the incorporation by reference doctrine, a later signed agreement may incorporate a referenced unsigned agreement. See Owen v. Hendricks, 433 S.W.2d 164, 166 (Tex. 1968); In re D. Wilson Const. Co., 196 S.W.3d 774, 781 (Tex. 2006). No “magic word” requirement exists to incorporate extrinsic terms or
documents into a contract. See In re Deepwater Horizon, 470 S.W.3d 452, 460 (Tex. 2015), opinion after certified question answered, No. 12-30230, 2015 WL 13918242 (5th Cir. June 9, 2015); see also Castillo Info. Tech. Services, LLC v. Dyonyx, L.P., 554 S.W.3d 41, 47–48 (Tex. App.—Houston [1st Dist.] 2017, no pet.). Rather, the later agreement needs to only manifest an intent to include the extrinsic terms, documents, or agreements. See In re Deepwater Horizon, 470 S.W.3d at 460. Any description or reference to other documents places a duty to inquire on a party to an agreement. See Westland Oil Dev. Corp. v. Gulf Oil Corp., 637 S.W.2d 903, 908 (Tex. 1982). This duty to inquire requires a party to follow up from one instrument to another, until the party obtains complete knowledge of all matters referenced. Id. However, it is a requirement that the contract reference the incorporated document by name. Gray & Co. Realtors, Inc. v. Atl. Hous. Found., Inc., 228 S.W.3d 431, 436 (Tex. App.— Dallas 2007, no pet.). This is because contract law obligates contracting parties to read what they sign to protect themselves, “and [they] are presumed, as a matter of law, to know the contract’s terms.” Id. (quoting Castroville Airport, Inc. v. City of Castroville, 974 S.W.2d 207, 211 (Tex. App. —San Antonio 1998, no pet.)). 2. Discussion We must first consider whether the parties entered into a valid contract.
Free access — add to your briefcase to read the full text and ask questions with AI
Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC (Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.