Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC

CourtCourt of Appeals of Texas
DecidedOctober 9, 2025
Docket10-24-00350-CV
StatusPublished

This text of Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC (Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC, (Tex. Ct. App. 2025).

Opinion

Court of Appeals Tenth Appellate District of Texas

10-24-00350-CV

Mitchell Construction Company, Inc, Appellant

v.

Superior Commercial Concrete, LLC, Appellee

On appeal from the 170th District Court of McLennan County, Texas Judge Jim Meyer, presiding Trial Court Cause No. 2024-130-4

CHIEF JUSTICE JOHNSON delivered the opinion of the Court.

MEMORANDUM OPINION

Superior Commercial Concrete, LLC (Superior) sued Mitchell

Construction Company, Inc. (Mitchell) and Messer, LLC (Messer) seeking

payment for work performed by Superior on a construction project. Mitchell

now brings this interlocutory appeal contending the trial court erred when it

denied Mitchell’s motion to compel arbitration and subsequent motion to

reconsider. We will reverse and remand.

Mitchell Const. Co. v. Superior Commercial Concrete, LLC Page 1 A. Factual and Procedural Background

Messer contracted with Mitchell to serve as general contractor on a

commercial construction project. Mitchell apparently put the project out for

bids and Superior’s bid to do the concrete work on the project was accepted.

Mitchell then presented Superior with a draft of a proposed written contract

(hereinafter “subcontract”) to memorialize their agreement regarding the

project. Superior returned an unsigned redlined version of the proposed

written subcontract to Mitchell that included some revisions and comments.

Mitchell nor Superior ever signed a written subcontract. Despite that, the

parties moved forward with the project.

Superior filed suit in January 2024 against Mitchell and Messer alleging

that both defendants “failed and refused to compensate” Superior for its

services. Superior’s claims against Mitchell included breach of contract,

breach of fiduciary duty under the Texas Construction Trust Fund Act;

conversion; and unjust enrichment. Superior’s claim against Messer included

claims for quantum meruit and foreclosure of its statutory and constitutional

liens.

In October 2024, Mitchell filed a motion to compel arbitration based on

an arbitration clause within both the original draft and redlined draft of the

proposed written subcontract. In support, Mitchell attached the redlined

version of the draft of the proposed written subcontract. Superior filed a

Mitchell Const. Co. v. Superior Commercial Concrete, LLC Page 2 response to the motion to compel arbitration in which it was Superior’s

contention that the proposed written subcontract was never formalized

because the parties never signed the proposed written subcontract. Superior

argued that because of Mitchell’s failure to establish the existence of a valid

arbitration agreement the trial court should deny the motion to compel

arbitration. During the hearing in the trial court, Superior reiterated that the

parties never signed the proposed written subcontract, so there was no formal

finalized agreement. Mitchell argued that if the parties acted in accordance

with the proposed written subcontract, then the lack of signatures does not bar

enforcement of an arbitration provision. The trial court denied Mitchell’s

motion to compel arbitration.

Next, Mitchell requested that the trial court reconsider its denial of the

motion to compel arbitration asserting that (1) because Superior is seeking

benefits under the contract it is estopped from avoiding arbitration, and

(2) `Superior’s act of signing change orders that referenced the unsigned

subcontract resulted in the incorporation by reference of all terms of the

subcontract. In support, Mitchell presented eight change orders signed by a

representative of Superior; seven invoices from Superior; and eight bids from

Mitchell Const. Co. v. Superior Commercial Concrete, LLC Page 3 Superior that correspond with the change orders. 1 Each change order included

language as follows:

Except for such CHANGES as are set forth herein, all of the terms and conditions of your SUBCONTRACT, and as it may have been heretofore modified in writing, shall be and remain the same. Unless specifically provided for herein, no extension of time for the completion of this SUBCONTRACT by reason of this CHANGE ORDER is allowed.

Near the bottom, the change order stated that the “foregoing CHANGE

ORDER is ACCEPTED upon the terms and conditions above stated and those

in the original SUBCONTRACT.” Both parties signed each of the change

orders.

In Superior’s response to Mitchell’s motion to reconsider, it argued that

“directs-benefits estoppel” is a narrow exception that does not apply here.

Superior argued that it was not suing under the unsigned draft of the proposed

written contract but was suing for breach of an implied or oral contract. After

a hearing on the motion to reconsider, the trial court denied Mitchell’s motion.

B. Standard of Review

We review interlocutory orders denying motions to compel arbitration

for abuse of discretion—deferring to the trial court’s factual determinations if

they are supported by the evidence—and reviewing questions of law de novo.

Henry v. Cash Biz, LP, 551 S.W.3d 111, 115 (Tex. 2018). A trial court abuses

1 Mitchell also supplied an affidavit certifying the exhibits.

Mitchell Const. Co. v. Superior Commercial Concrete, LLC Page 4 its discretion if it acts in an arbitrary or unreasonable manner or acts without

reference to any guiding rules and principles. Cire v. Cummings, 134 S.W.3d

835, 838–39 (Tex. 2004). When a trial court improperly denies a party’s right

to arbitrate based on a valid and enforceable arbitration agreement, the court

has abused its discretion. In re Whataburger Restaurants LLC, 645 S.W.3d

188, 194 (Tex. 2022) (orig. proceeding). Whether an arbitration agreement is

valid and enforceable is a legal question subject to de novo review. Baby Dolls

Topless Saloons, Inc. v. Sotero, 642 S.W.3d 583, 586 (Tex. 2022) (per curiam).

C. Issue Two

Mitchell contends the trial court erred in denying its motion to compel

arbitration because the terms of the proposed written subcontract were

referenced, incorporated, and affirmed by Superior.

1. Authority

To compel arbitration, a party must first prove that a valid arbitration

agreement exists. Aerotek, Inc. v. Boyd, 624 S.W.3d 199, 204 (Tex. 2021). To

do so, courts apply state contract law principles. Cerna as Next Friend of R.W.

v. Pearland Urban Air, LLC, 714 S.W.3d 585, 589 (Tex. 2025). Under the

incorporation by reference doctrine, a later signed agreement may incorporate

a referenced unsigned agreement. See Owen v. Hendricks, 433 S.W.2d 164,

166 (Tex. 1968); In re D. Wilson Const. Co., 196 S.W.3d 774, 781 (Tex. 2006).

No “magic word” requirement exists to incorporate extrinsic terms or

Mitchell Const. Co. v. Superior Commercial Concrete, LLC Page 5 documents into a contract. See In re Deepwater Horizon, 470 S.W.3d 452, 460

(Tex. 2015), opinion after certified question answered, No. 12-30230, 2015 WL

13918242 (5th Cir. June 9, 2015); see also Castillo Info. Tech. Services, LLC v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Storage & Processors, Inc. v. Reyes
134 S.W.3d 190 (Texas Supreme Court, 2004)
Cire v. Cummings
134 S.W.3d 835 (Texas Supreme Court, 2004)
In Re D. Wilson Const. Co.
196 S.W.3d 774 (Texas Supreme Court, 2006)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
Hal Rachal, Jr. v. John W. Reitz
403 S.W.3d 840 (Texas Supreme Court, 2013)
Farmers Insurance Exchange v. Leonard
125 S.W.3d 55 (Court of Appeals of Texas, 2003)
Bynum v. Prudential Residential Services, Ltd. Partnership
129 S.W.3d 781 (Court of Appeals of Texas, 2004)
Urban Electrical Services, Inc. v. Brownwood Independent School District
852 S.W.2d 676 (Court of Appeals of Texas, 1993)
Owen v. Hendricks
433 S.W.2d 164 (Texas Supreme Court, 1968)
Westland Oil Development Corp. v. Gulf Oil Corp.
637 S.W.2d 903 (Texas Supreme Court, 1982)
Schriver v. Texas Department of Transportation
293 S.W.3d 846 (Court of Appeals of Texas, 2009)
Gray & Co. Realtors, Inc. v. Atlantic Housing Foundation, Inc.
228 S.W.3d 431 (Court of Appeals of Texas, 2007)
Castroville Airport, Inc. v. City of Castroville
974 S.W.2d 207 (Court of Appeals of Texas, 1998)
Sedona Contracting, Inc. v. Ford, Powell & Carson, Inc.
995 S.W.2d 192 (Court of Appeals of Texas, 1999)
in Re Deepwater Horizon
470 S.W.3d 452 (Texas Supreme Court, 2015)
BoRain Capital, LLC v. Syed Hashmi
533 S.W.3d 32 (Court of Appeals of Texas, 2017)
Castillo Information Technology Services, LLC v. Dyonyx, L.P.
554 S.W.3d 41 (Court of Appeals of Texas, 2017)
Peterson v. NCNB Texas National Bank
862 S.W.2d 182 (Court of Appeals of Texas, 1993)
Henry v. Cash Biz, LP
551 S.W.3d 111 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Mitchell Construction Company, Inc v. Superior Commercial Concrete, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-construction-company-inc-v-superior-commercial-concrete-llc-texapp-2025.