Mistry Prabhudas Manji Eng. Pvt. Ltd. v. Raytheon Engineers & Constructors, Inc.

213 F. Supp. 2d 20, 2002 U.S. Dist. LEXIS 14395, 2002 WL 1793251
CourtDistrict Court, D. Massachusetts
DecidedAugust 6, 2002
DocketCIV.A.00-11060-PBS
StatusPublished
Cited by2 cases

This text of 213 F. Supp. 2d 20 (Mistry Prabhudas Manji Eng. Pvt. Ltd. v. Raytheon Engineers & Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mistry Prabhudas Manji Eng. Pvt. Ltd. v. Raytheon Engineers & Constructors, Inc., 213 F. Supp. 2d 20, 2002 U.S. Dist. LEXIS 14395, 2002 WL 1793251 (D. Mass. 2002).

Opinion

MEMORANDUM AND ORDER

SARIS, District Judge.

Plaintiff Mistry Prabhudas Manji Engineering Pvt, Ltd. (“MPM”) and defendant Raytheon Engineers & Constrictors, Inc. (“REC”), through its subsidiary United Engineers, International (“UEI”), entered into two contracts for licensing and technology transfer agreements for the design and construction of a processing plant for sodium hydroxide, more commonly known as caustic soda. Plaintiffs plans for the plants corroded, they allege, when the plant failed to produce caustic soda at the required purity.

Plaintiff brings claims for breach of contact, misrepresentation, and fraud. Defendants move for partial summary judgment, claiming that plaintiffs fraud and misrepresentation claims are barred by the statute of frauds or, in the alternative, the “gist of the action” or economic loss doctrines. They also argue that the liquidated damages and consequential damages limitation clauses of each contract bar the bulk of plaintiffs claim for damages.

Defendants’ Motion for Partial Summary Judgment (Docket No. 38) is ALLOWED.

*22 BACKGROUND

MPM is a privately held engineering and construction company located in Mumbai, India. REC is an engineering and construction company located in Pennsylvania. REC assumed the contract obligations of UEI, including the two contracts at issue here.

In 1992 and 1993, MPM and UEI entered into two licensing and technology transfer agreements, requiring defendants to supply MPM with *‘Basic Engineering Packages” for caustic soda processing plants. Caustic soda is used as a cleaner and solvent. The 1992 contract concerned technology for a caustic concentration unit (“CCU”), designed to concentrate liquid caustic soda to a 99.5% concentration. The 1993 contract transferred technology for the creation of a caustic prilling unit (“CPU”), used to create “prills,” tiny balls of caustic soda.

For present purposes, the two contracts were quite similar. Each contained a choice of law provision providing that the agreement, “and the legal relationship between the parties,” would be governed by Pennsylvania law. Each contained a liquidated damages clause that capped UEI’s liability (and REC’s by extension) at 10% of the amount MPM paid. Each contained a waiver of “special, indirect, incidental, or consequential damages of any kind” for contract, warranty, and tort claims. Finally, each required a 72-hour performance test to be conducted by MPM within three months of the mechanical completion of the unit. These performance-test clauses provided that if such a performance test could not be conducted within the three-month time limit, through no fault of UEI, the unit would be deemed accepted by MPM.

In 1993, defendants delivered the CCU package to MPM. MPM proceeded to construct the CCU for its client through the remainder of 1993 and beginning of 1994. In April 1994, REC conducted the performance test for the CCU, and MPM’s client certified that the performance test was satisfactory.

In 1994, defendants gave the CPU package to MPM. Again, MPM used the package to construct a CPU for its client, completing the plant in early 1995. The CPU reached mechanical completion in April 1995, but did not achieve “start-up” at that time. Several further attempts at achieving start-up took place (in August 1995, December 1995, early January 1996 and November 1998), with corresponding attempts to correct problems. To this date, the CPU plant has not achieved “commercial production.” Nor has there been a successful 72-hour performance test.

MPM submitted a formal bill of claims to REC on December 8, 1997. MPM requested $4.65 million, “in connection with the failure of the technology.” REC responded by letter on December 31, 1997, rejecting MPM’s claims. MPM reasserted its position in a January 9, 1998 letter, which stated that, “MPM ... reserves the right to all its claims at a later date due to complete failure of Raytheon to supply suitable Technology, Software, Hardware, and Technical Services...” MPM’s chief executive officer, Nandlal Gothi, agreed at deposition that this “complete failure” stemmed from the technology’s inability to produce caustic soda at greater than 99% concentration. (Salon Aff. at Tab 5 (Gothi Depo. Vol. 1 at p. 215)).

MPM filed this action on May 31, 2000, asserting breach of contract (Counts I and II), misrepresentation (Counts III and IV), and fraud (Counts V and VI) by UEI and REC, respectively.

SUMMARY JUDGMENT STANDARD

“Summary judgment is appropriate when ‘the pleadings, depositions, answers to interrogatories, and admissions on file, *23 together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.’ ” Barbour v. Dynamics Research Corp., 63 F.3d 32, 36 (1st Cir.1995) (quoting Fed. R.Civ.P. 56(c)). “To succeed [in a motion for summary judgment], the moving party must show that there is an absence of evidence to support the nonmoving party’s position.” Rogers v. Fair, 902 F.2d 140, 143 (1st Cir.1990); see also Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).

“Once the moving party has properly supported its motion for summary judgment, the burden shifts to the non-moving party, who ‘may not rest on mere allegations or denials of his pleading, but must set forth specific facts showing there is a genuine issue for trial.’ ” Barbour, 63 F.3d at 37 (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)). “There must be ‘sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party. If the evidence is merely colorable or is not significantly probative, summary judgment may be granted.’ ” Rogers, 902 F.2d at 143 (quoting Anderson, 477 U.S. at 249-50, 106 S.Ct. 2505) (citations and footnote in Anderson omitted). The Court must “view the facts in the light most favorable to the non-moving party, drawing all reasonable inferences in that party’s favor.” Barbour, 63 F.3d at 36.

APPLICABLE LAW

The parties agree that Pennsylvania law applies to this action, based on the express choice of law provision of the CCU and CPU contracts.

Under Pennsylvania law, “contractual choice of law provisions [only] govern tort claims between contracting parties [if] the fair import of the provision embraces all aspects of the legal relationship. Courts analyze choice of law provisions to ‘determine, based on their narrowness or breadth, whether the parties intended to encompass all elements of their association.’ ” Jiffy Lube Intn’l, Inc. v. Jiffy Lube of Pennsylvania, Inc., 848 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
213 F. Supp. 2d 20, 2002 U.S. Dist. LEXIS 14395, 2002 WL 1793251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mistry-prabhudas-manji-eng-pvt-ltd-v-raytheon-engineers-constructors-mad-2002.