Missouri v. Westinghouse Elec., LLC

487 F. Supp. 2d 1076, 2007 U.S. Dist. LEXIS 36965, 2007 WL 1378408
CourtDistrict Court, E.D. Missouri
DecidedJanuary 22, 2007
Docket4:05 CV 0315 SNL
StatusPublished
Cited by2 cases

This text of 487 F. Supp. 2d 1076 (Missouri v. Westinghouse Elec., LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Missouri v. Westinghouse Elec., LLC, 487 F. Supp. 2d 1076, 2007 U.S. Dist. LEXIS 36965, 2007 WL 1378408 (E.D. Mo. 2007).

Opinion

487 F.Supp.2d 1076 (2007)

State of MISSOURI, Plaintiff,
v.
WESTINGHOUSE ELECTRIC, LLC, Defendant.

No. 4:05 CV 0315 SNL.

United States District Court, E.D. Missouri, Eastern Division.

January 22, 2007.

*1077 *1078 Shelley A. Woods, Assistant Attorney General of Missouri, Jefferson City, MO, for Plaintiff.

C. Shawn Dryer, Babst and Calland, Pittsburgh, PA, for Defendant.

ORDER

LIMBAUGH, Senior District Judge.

This case is one of two actions before the Court involving the cleanup of environmental contamination at the Hematite Nuclear Facility. Westinghouse Electric Company purchased the Hematite Site in 2000, and shortly thereafter began to decommission the facility. However, the Hematite Site had operated as a nuclear fuel processing plant for upwards of forty years, and is contaminated with radiological and chemical wastes. Therefore, Westinghouse has been working with the United States Nuclear Regulatory Commission (NRC), and the Missouri Department of Natural Resources (MDNR) in an attempt to decontaminate the site.

In February of 2005, the State of Missouri filed suit against. Westinghouse under Section 107 of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. § 9607, the Missouri Hazardous Waste Management Law, Mo.Rev.Stat. § 260.350 et seq, and the Missouri Clean Water Law, Mo.Rev.Stat. § 644.006 et seq. In the Complaint, Missouri requested injunctive relief, requiring that Westinghouse perform a Remedial Investigation/Feasibility Study (RI/FS) to determine the nature and extent of the contamination and develop a plan to decontaminate the area. Missouri also demanded that Westinghouse implement the remedy selected through the RI/FS process and reimburse the MDNR for any past or future response costs incurred at the Hematite Site.

*1079 In May of 2006, the State of Missouri and Westinghouse entered, into a Consent Decree and submitted it to the Court for approval. This Consent Decree was crafted pursuant to Section 107 of CERCLA, and includes a detailed plan for the decontamination of Hematite Site. Generally, a Court gives deference to a Consent Decree, and should issue its approval if the Decree is "fair, reasonable, and faithful to the objectives of CERCLA. United States v. Cannons Eng'g Corp., 899 F.2d 79, 84 (1st Cir.1990). However, this is not a general case.

As previously stated, there are two actions before this Court involving the Hematite site. The related cause of action was brought by Westinghouse against the United States of America and several other corporate Defendants, all of whom formerly owned the Hematite property and may be liable for the expenses incurred during the decontamination process. For reasons not pertinent to the Court's analysis, the Defendants in the second suit intervened in this action to protect their interests. In addition, the NRC, which is the federal agency charged with regulating the civilian use of nuclear materials, takes issue with the State of Missouri's attempt to regulate radiological waste. Accordingly, there are a multitude of parties advancing a multitude of theories as to why this Consent Decree should not be approved.[1]

I. Case & Controversy

As a preliminary manner, the Court must address the case or controversy issue raised by the Non-Governmental Intervenors. If there is no genuine case or controversy, this Court lacks jurisdiction to determine the validity of the Consent Decree.

A cause of action that lacks "truly adverse parties," is considered a collusive action and must be dismissed. Honig v. Doe, 484 U.S. 305, 340, 108 S.Ct. 592, 98 L.Ed.2d 686 (1988). However, consent decrees necessarily require a certain amount of compromise and cooperation. Otherwise, it could never be formed. As stated by the Supreme Court:

Consent decrees are entered into by parties to a case after careful negotiation has produced agreement on their precise terms. The parties waive their right to litigate the issues involved in the case and thus save themselves the time, expense, and inevitable risk of litigation. Naturally, the agreement reached normally embodies a compromise; in exchange for the saving of cost and elimination of risk, the parties each give up something they might have won had they proceeded with the litigation.

United States v. Armour & Co., 402 U.S. 673, 681, 91 S.Ct. 1752, 29 L.Ed.2d 256 (1971).

The Non-Governmental Intervenors suggest that the State of Missouri and Westinghouse colluded in fashioning this Consent Decree. This collusion is allegedly evidenced by the fact that much of the work to be performed under the Consent Decree has already been completed. The Proponents vehemently disagree with this characterization, arguing that the Consent Decree was the result of intense arms-length negotiations between the parties. The completed work was performed pursuant to a Letter Agreement, the substance of which was to be finalized upon entry of this Consent Decree.

Upon review, the Court finds nothing that would render this Consent Decree collusive. "The Supreme Court has long *1080 endorsed the propriety of the use and entry of consent judgments." S.E.C. v. Randolph, 736 F.2d 525, 528 (9th Cir.1984) (citing United States v. Armour & Co., 402 U.S. 673, 681, 91 S.Ct. 1752, 29 L.Ed.2d 256 (1971); Pope v. United States, 323 U.S. 1, 12, 65 S.Ct. 16, 89 L.Ed. 3 (1944); Swift & Co. v. United States, 276 U.S. 311, 325-326, 48 S.Ct. 311, 72 L.Ed. 587 (1928)). And a certain amount of cooperation between the parties is to be expected. Accordingly, there is a genuine case and controversy, and the Court has jurisdiction over this action.

II. Consent Decree

In the Consent Decree, the State of Missouri seeks reimbursement for past and future costs incurred by the State in connection with the Hematite Site. Pursuant to Sections 107(a) and 113(f) of CERLA, the State is vested with the right to pursue this monetary recovery. However, the Consent Decree also requires that Westinghouse "finance and perform the Work in accordance with the Consent Decree." Consent Decree, at ¶ 11. The term "Work" encompasses:

all work and other activities [Westinghouse] is required to perform under this Consent Decree including, but not limited to, the activities set out in the RI/FS Work Plan . . . implementation of the Removal Action for Duel's Mountain and the Site Buildings and Equipment and any additional response actions agreed to by the parties.

Consent Decree at ¶ 9. The MDNR is "responsible for overseeing the proper and complete implementation of the Work under this Consent Decree" and has "the authority to halt, conduct or direct any action required by this Consent Decree, or to direct any other response action undertaken by MDNR or [Westinghouse] at the Site." Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Church v. State of Missouri
W.D. Missouri, 2020
Pennsylvania v. Lockheed Martin Corp.
684 F. Supp. 2d 564 (M.D. Pennsylvania, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
487 F. Supp. 2d 1076, 2007 U.S. Dist. LEXIS 36965, 2007 WL 1378408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/missouri-v-westinghouse-elec-llc-moed-2007.