Mississippi Valley Structural Steel Co. v. Huber, Hunt & Nichols Co.

295 F. Supp. 139, 1969 U.S. Dist. LEXIS 10517
CourtDistrict Court, S.D. Illinois
DecidedJanuary 7, 1969
DocketNo. P-2990
StatusPublished
Cited by2 cases

This text of 295 F. Supp. 139 (Mississippi Valley Structural Steel Co. v. Huber, Hunt & Nichols Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mississippi Valley Structural Steel Co. v. Huber, Hunt & Nichols Co., 295 F. Supp. 139, 1969 U.S. Dist. LEXIS 10517 (S.D. Ill. 1969).

Opinion

DECISION AND ORDER ON MOTION TO DISMISS

ROBERT D. MORGAN, District Judge.

The complaint here contains two counts. Count I involves both plaintiffs and seeks damages from defendant for alleged breach of contract. Count II, involving only plaintiff Mississippi Valley and defendant, seeks payment of an alleged unpaid contract balance. The matter is before the Court on motion to dismiss Count I.

Plaintiffs are both alleged to be Illinois corporations with principal places of business in Illinois; and defendant is alleged to be an Indiana corporation with principal place of business at Indianapolis, but licensed to do business in Illinois, and doing business in this district. The amount in controversy exceeds $10,000, and there is no dispute over jurisdiction or venue.1

Based upon the allegations of Count I (and exhibits attached to the complaint), which are accepted as true for the purposes of this motion, the following facts appear. Defendant was general contractor for the construction of a large, new administration building for Caterpillar Tractor Co. at Peoria, Illinois. Plaintiff, ' Mississippi Valley, was a subcontractor for fabricating and erecting the structural steel for that building. The price and basic terms of this subcontract were established December 8, 1964 by Mississippi Valley directly with Caterpillar, the owner. It included a schedule for erection of the structural steel between May 1 and Sep[140]*140tember 1, 1965, which was prepared by Caterpillar and which was amended by Caterpillar, with Mississippi Valley approval, to require that erection be begun on or about May 17, 1965, and be completed by September 17, 1965. Thereafter, a detailed schedule (Exhibit B to the complaint) “was prepared by Ken-wood and Mississippi Valley,” which was delivered to and approved by Caterpillar, calling for start of erection work on May 10, 1965.

On or about March 19, 1965, Caterpillar entered into the general construction contract with defendant, and prior to that date defendant had received from Caterpillar a copy of the final approved steel erection schedule.

Under date of May 11, 1965 (signed June 2, 1965), pursuant to provisions in the prior contracts each had with Caterpillar, defendant and Mississippi Valley entered into a Subcontract Agreement (Group Exhibit C to the complaint) whereby the fabrication and erection of the structural steel for the said Caterpillar building was formally let to Mississippi Valley by defendant on the same terms as Mississippi Valley had previously agreed upon with Caterpillar.

It is alleged that both plaintiffs spent substantial sums in reliance upon said contracts, including said final erection schedule, in order to prepare for and to perform their obligations thereunder; that by virtue of said agreements defendant was obligated to both plaintiffs to be ready for the start and continuation of steel erection in accordance with said final approved erection schedule, but that defendant- “wholly failed” in such obligation, whereas both plaintiffs “fully performed their respective obligations” to defendant with respect to said agreements, and as a result of defendant’s breaches and failure both plaintiffs have sustained damages of $250,-000, for which judgment is prayed.

The name of plaintiff Kenwood does not appear in any of the contract documents attached to the complaint and there is no actual allegation that either defendant or Caterpillar had even ever heard of plaintiff Kenwood until the complaint was filed. It seems apparent, however, and appears to be acknowledged in argument, that Kenwood was a second-tier subcontractor for the erection of the steel which was to be fabricated by Mississippi Valley. There apparently was a contract of some kind between Kenwood and Mississippi Valley. Neither the form nor the terms of that contract are alleged in the complaint. There is no room for real doubt, however, that defendant is informed of the nature of the charges against it so as to be able to prepare any defense which it may have. It makes no contrary contention in that regard.

It is clear that facts well pleaded are to be taken as true; legal conclusions are not. The important issue of law on this motion is whether a cause of action upon which relief can be granted has been stated on behalf of plaintiff Kenwood. That question has been forcefully argued by both sides and thorough briefs have been submitted.

Defendant contends that plaintiff Kenwood has no standing to sue it because there is no privity of contract between them; that there was clearly no intention within Caterpillar’s or defendant’s contract to benefit plaintiff Ken-wood, and hence, at best, it can be only an incidental beneficiary of those contracts, to which no cause of action as a third-party beneficiary is afforded in law. Defendant asserts that any claim by Kenwood must be against Mississippi Valley, with whom it had a contract. It is not asserted or argued that Mississippi Valley, which is a party-plaintiff to Count I, could have no claim against defendant on the basis alleged; but presumably defendant believes that such a claim or cause of action cannot arise until Mississippi Valley has suffered some damages through successful suit against it by Kenwood. While presumably that has not taken place, it cannot be overlooked that Mississippi Valley does allege contract breaches by defendant to its present damage. The Court is not [141]*141advised of any defect in Count I, so far as plaintiff Mississippi Valley is concerned.

Plaintiffs jointly argue that Kenwood is in the position of a creditor-beneficiary of the contract here between defendant and Mississippi Valley, that such a third-party beneficiary has a cause of action against the promisor directly, and that the promisee (here Mississippi Valley) of defendant’s contract likewise has a cause of action against the promisor for failure to perform duties due the creditor-beneficiary.

It seems apparent that if either actual privity of contract between Kenwood or a classic third-party beneficiary position for Kenwood is required, Kenwood states no cause of action here.

Defendant relies on the case of International Erectors v. Wilhoit Steel Erectors, 400 F.2d 465 (1968), very recently decided by the Court of Appeals for the Fifth Circuit. There a third-tier subcontractor for the erection of structual steel, who had a contract only with a second-tier subcontractor for such erection, sued the first-tier subcontractor, who had contracted to fabricate and erect, for damages caused by delays. The claim was almost identical to the suit of Kenwood here, except that the whole set of parties was simply one tier further removed from the owner. It cannot be doubted that, under the law of Florida there applicable, and the reasoning of the Court of Appeals for the Fifth Circuit there applied, plaintiff Kenwood here would be found to be only an incidental beneficiary of the defendant’s contract with Mississippi Valley, without privity of contract with defendant, and hence to have no standing to sue. There the Court of Appeals rejected the third-party beneficiary theory and sustained dismissal of a fourth amended complaint filed against the defendant with whom there was no contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South v. Rowe
102 F.R.D. 152 (N.D. Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
295 F. Supp. 139, 1969 U.S. Dist. LEXIS 10517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mississippi-valley-structural-steel-co-v-huber-hunt-nichols-co-ilsd-1969.