Mission1st Group, Inc.

CourtArmed Services Board of Contract Appeals
DecidedAugust 16, 2021
DocketASBCA No. 62461, 62646
StatusPublished

This text of Mission1st Group, Inc. (Mission1st Group, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mission1st Group, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Mission1st Group, Inc. ) ASBCA Nos. 62461, 62646 ) Under Contract No. W52P1J-13-F-0031 )

APPEARANCES FOR THE APPELLANT: Joshuah R. Turner, Esq. Elizabeth J. Cappiello, Esq. Jason N. Workmaster, Esq. Miller & Chevalier Chartered Washington, DC

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney Zachary F. Jacobson, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS

In September 2013, the Army Contracting Command – Rock Island Arsenal (Army or government) awarded appellant, Mission1st Group, Inc. (M1), a task order against M1’s General Services Administration (GSA) Information Technology (IT) Schedule 70 Contract. The task order provided for a base period and, pursuant to Federal Acquisition Regulation (FAR) 52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000), two option periods. In addition, pursuant to FAR 52.217-8, OPTION TO EXTEND SERVICES (NOV 1999), the task order contained an option to extend the contract for a period of up to six months. M1 encountered problems retaining staff at the labor rates it proposed in the task order, and discussed with the Army terminating the contract. After the Army indicated that it planned to exercise the first option period, M1 indicated that it would challenge the exercise of the option unless the government agreed to reprice certain contract line items. M1 also opposed the Army’s suggestion that the parties agree to a reduced duration three-month option period. The Army then exercised its right to extend services for a three-month period, pursuant to FAR 52.217-8. The task order was subsequently bilaterally modified twice to extend the period of performance.

M1 contends that the Army improperly exercised the option to extend services out-of-sequence, entitling it to a contractual price adjustment. According to M1, the option to extend services is really an option period 3 that can only be exercised following option periods 1-2. Additionally, M1 argues that the Army’s exercise of the option four days before expiration of the base period of performance was not “within 90 days before the expiration of the contract.” We hold that the language of the task order permitted the Army to exercise the option to extend services after the base period, and that the option was timely exercised. Additionally, we note that, even if the Army’s exercise of the option was defective, M1 waived its right to a contractual adjustment through a subsequent bilateral modification.

FINDINGS OF FACT

The Army Contracting Command – Rock Island Arsenal awarded Task Order No. W52P1J-13-F-0031 to Mission1st Group, Inc. on September 24, 2013, for Network and Communications, Engineering and Installation Support pursuant to M1’s GSA IT Schedule 70 Contract No. GS35F0199Y, Special Item No. 132 51, IT Professional Services contract (R4, tab 1 at 1, 4).1 Under the task order, M1 provided theater communications and networking infrastructure and subject matter experts to perform project management and information assurance in support of the Army primarily in Afghanistan and Kuwait (R4, tab 1 at 4).

The Army awarded the task order as a firm-fixed price contract, with some contract line items (CLINs) such as overtime and travel paid at cost (id.). The task order provided:

This is a Firm-Fixed Price (FFP) task order with a base period and three evaluated option periods.

Base Period: 24 September 2013 to 23 June 2014

Option Period One: 24 June 2014 to 23 March 2015

Option Period Two: 24 March 2015 to 23 December 2015

Option to Extend Services: Six Month Maximum to be completed no later than 23 June 2016

(Id.). The performance work statement “Period of Performance” provides that there is a nine-month base period and “two (2) nine (9) month options” (R4, tab 2 at 51). The prices proposed by M1 and accepted by the Army included $5,355,900.79 for the nine-month base period (R4, tab 1 at 4). The Army also accepted M1’s proposed prices for two nine-month option periods, priced at $5,382,254.68 and $5,417,880.85,

1 We have dropped all leading zeros from the Bates numbers used by the government. For documents that were not Bates numbered, we used the document’s internal page numbers. Appellant’s opposition and reply brief was not paginated so we used the PDF page numbers. 2 respectively (id.). In addition to the option years, M1 proposed a price not to exceed $3,743,169.77 for up to a total of six months of extended services, to be completed no later than June 23, 2016 (id.).

Noting that M1’s price quote offered a significant discount from the approved GSA Schedule rates, the contracting officer noted that M1 had expressly indicated in its quote that the discount was intentional, and determined that M1’s quote was still responsible (gov’t supp. R4, tab 7 at 1-3). The task order’s clause addendum included the following standard clauses from the FAR:

52.217-8, OPTION TO EXTEND SERVICES (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 90 days before the expiration of the contract.[2]

(End of Clause)

52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within the term of the contract prior to contract expiration; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 90 days before the contract expires. The preliminary notice does not commit the Government to an extension.

2 Relevant to the jurisdiction of the Board, but not relevant to our interpretation of the contract, the last sentence of this clause in the FAR provides: “The Contracting Officer may exercise the option by written notice to the Contractor within _____ [insert the period of time within which the Contracting Officer may exercise the option].” FAR 52.217-8. M1’s GSA schedule provides: “The Contracting Officer may exercise the option by written notice to the Contractor within 30 days” (gov’t supp. R4, tab 10b at 46). 3 (b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 33 months.[3]

(R4, tab 3 at 123)

On March 25, 2014,4 91 days prior to the end of the base period of performance, the Army provided M1 with its notice of intent to exercise the first option period in accordance with the terms and conditions of the contract and FAR 52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT (gov’t supp. R4, tab 3). On April 25, 2014 and April 28, 2014, M1 alerted the government that it would have difficulty continuing performance on some of its contract line items unless the government obligated an additional 25 percent of the estimated not-to-exceed price (R4, tab 15 at 489-90).

The government offered M1 a draft partial option period for the task order on June 10, 2014, which, if executed, would have only required M1 to perform for three-months, rather than the full nine-months contained in the contractual option period (gov’t supp. R4, tab 4 at 1). Having received no comments from M1, the government followed-up with M1 on June 17, 2020 (R4, tab 19 at 760). In response, M1 asserted that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Mission1st Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mission1st-group-inc-asbca-2021.