MiScott Corp. v. Zaremba Walden Co. (In re MiScott Corp.)

49 B.R. 893, 1985 Bankr. LEXIS 6025
CourtUnited States Bankruptcy Court, S.D. Florida.
DecidedJune 3, 1985
DocketBankruptcy Nos. 84-01235-BKC-SMW, 84-0647-BKC-SMW-A
StatusPublished
Cited by3 cases

This text of 49 B.R. 893 (MiScott Corp. v. Zaremba Walden Co. (In re MiScott Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, S.D. Florida. primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MiScott Corp. v. Zaremba Walden Co. (In re MiScott Corp.), 49 B.R. 893, 1985 Bankr. LEXIS 6025 (Fla. 1985).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

SIDNEY M. WEAVER, Bankruptcy Judge.

THIS CAUSE having come before the Court as an adversary proceeding by the Debtor on a Complaint to Foreclose Mechanics’ Lien and Collect Monies Due, and the Court having heard the testimony and examined the evidence presented; observed the candor and demeanor of the witnesses; considered the arguments of counsel; reviewed the post trial memoranda, and being otherwise fully advised in the premises, [895]*895does hereby make the following findings of fact and conclusions of law:

Debtor, MiSCOTT CORPORATION, a general contracting company, filed its voluntary petition under Chapter 11 of Title 11, United States Code, on July 3, 1984; thereafter the Debtor instituted this adversary proceeding against ZAREMBA WALDEN CO. and WALDEN COMMUNITIES, INC., d/b/a WALDEN DEVELOPMENT CO. (hereinafter referred to as “WALDEN”), and SAFECO INSURANCE COMPANY OF AMERICA (hereinafter referred to as “SAFECO”). The action was tried on the Debtor’s claim against WALDEN for breach of contract, the Debtor’s claim against WALDEN and SAFECO for recovery under a surety transfer bond, and on WALDEN’s counterclaim against the Debt- or for breach of contract.1

On June 22, 1983, WALDEN, as owner, and the Debtor, as general contractor, entered into a written contract consisting of an Agreement and General Conditions Between Contractor and Owner, and a Rider annexed to and expressly made a part of the Agreement and General Conditions, providing for the construction of a residential development known as McArthur Park at Misty Lake. The contract provided for a fixed sum of two million seven hundred fifty-four thousand one hundred forty-four dollars ($2,754,144.00), plus a bonus for early completion of the project. The fixed sum was to be paid in progress payments together with a retainage payment, denominated the “final payment”. It is undisputed that WALDEN paid the Debtor all the progress payments leaving the final payment of the fixed sum in an amount of one hundred forty-one thousand five dollars and forty cents ($141,005.40) unpaid to the Debtor. The Debtor’s claim for breach of contract seeks one hundred forty-one thousand five dollars and forty cents ($141,005.40) from WALDEN, as well as a bonus of two hundred ninety-one thousand dollars ($291,000.00) for early completion of the project. On June 28, 1984, the Debtor recorded a claim of lien against the project, which lien was transferred to a surety bond on August 6, 1984, pursuant to § 713.24, Florida Statutes.

WALDEN contends that the Debtor is entitled to a bonus of only thirty-eight thousand five hundred dollars ($38,500.00), and that the Debtor is not entitled to the final payment under the contract. Further, WALDEN seeks damages against the Debtor in the amount of seventeen thousand four hundred seventy-two dollars and fifty cents ($17,472.50), incurred as a result of the Debtor’s failure to pay its subcontractors.

The provision in the contract dealing with final payment reads as follows:

Final payment shall be made to CONTRACTOR within thirty (30) days after the completion of the Work covered by this Agreement, provided the CONTRACTOR has given to OWNER satisfactory evidence that the premises are free from all liens or other claims chargeable to the premises or the CONTRACTOR and has obtained a Certificate of Occupancy or other such document establishing that the Work has been completed.

The parties agree that the work was completed by the Debtor; the factual issue to be resolved by the Court is whether the Debtor gave WALDEN satisfactory evidence that the premises were free from all liens or other claims chargeable to the premises. The Court finds that the Debtor failed to meet its burden of proof on this issue.

In accordance with Florida law, the owner is entitled to retain final payment until such time as the general contractor furnishes the owner with a contractor’s affidavit. §§ 713.06(3)(d)l; 713.06(3)(d)5; 713.-06(3)(f), Fla.Stat. Upon completion of the work, the Debtor supplied WALDEN with [896]*896a contractor’s affidavit which established that as of July 9, 1984, the Debtor owed its subcontractors two hundred forty-two thousand four hundred ninety-seven dollars and ninety-three cents ($242,497.93). These debts constituted claims chargeable to the premises and, in fact, liens totalling one hundred seventy-five thousand forty-two dollars and fifty cents ($175,042.50) were ultimately filed by subcontractors against the project. WALDEN’s testimony indicated that the custom established between the parties, from prior projects, was that the Debtor was to furnish final releases of lien from all subcontractors before it was entitled to receive final payment from the owner. Similarly, in this instance, upon request for final payment, WALDEN demanded final releases of liens from all subcontractors before making final payment. It was undisputed that the Debtor failed to furnish WALDEN with final releases of lien from all subcontractors. After obtaining relief from stay, WALDEN dealt directly with the subcontractors and paid their claims in order to obtain final releases and satisfactions of lien.

Therefore, this Court finds that the Debtor is not entitled to the one hundred forty-one thousand five dollars and forty cents ($141,005.40) final payment sought from WALDEN.

Next, the Court turns to the Debtor’s claim for a bonus. The provision in the contract dealing with the bonus is found in Rider Section 27 and reads as follows:

Owner agrees that, if Contractor completes all Work contemplated by the Contract Documents ahead of schedule, Contractor shall be entitled to the sum of FIVE HUNDRED AND 00/100 ($500.00) DOLLARS per day for each day that all of the Work contemplated by the Contract Documents is completed prior to the time required by the Contract Douc-ments (sic).

The Debtor asserts that the language of Rider Section 27 is ambiguous and, consequently, extrinsic evidence is admissible to clarify the intent of the parties. WALDEN contends that Section 27 is clear and unambiguous and, accordingly, the language of the contract itself is controlling regarding the intention of the parties. The Debtor interprets Section 27 to mean that the Debtor is to be paid five hundred dollars ($500.00) a day for each day that it delivers each individual building early. WALDEN interprets Section 27 to mean that the Debtor is entitled to five hundred dollars ($500.00) per day from the date that the entire project is completed early.

This Court finds that Section 27 is susceptible to several interpretations, and, therefore, extrinsic evidence must be considered in conjunction with the language of the contract in determining the intention of the parties. Ocean Reef Club, Inc. v. UOP, Inc., 554 F.Supp. 123 (S.D.Fla.1982). After careful consideration of the extrinsic evidence, this Court finds that the Debtor failed to carry its burden of proof in demonstrating that the Debtor is entitled to a bonus of two hundred ninety-one thousand dollars ($291,000.00). In fact, the Court’s interpretation of Section 27 is contrary to the position assumed by the Debtor.

The project consisted of Phases I and II — Buildings 1 through 8. The parties agree upon the scheduled completion date of each building of the project, and the actual dates of completion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miscott Construction Corp. v. Zaremba Walden Co.
848 F.2d 1190 (Eleventh Circuit, 1988)
In Re Miscott Corporation
848 F.2d 1190 (Eleventh Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
49 B.R. 893, 1985 Bankr. LEXIS 6025, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miscott-corp-v-zaremba-walden-co-in-re-miscott-corp-flsb-1985.