Milner Hotels, Inc. v. Norfolk & Western Railway Co.

822 F. Supp. 341, 1993 U.S. Dist. LEXIS 7035, 1993 WL 183096
CourtDistrict Court, S.D. West Virginia
DecidedMay 20, 1993
DocketCiv. A. 1:91-1078
StatusPublished
Cited by10 cases

This text of 822 F. Supp. 341 (Milner Hotels, Inc. v. Norfolk & Western Railway Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milner Hotels, Inc. v. Norfolk & Western Railway Co., 822 F. Supp. 341, 1993 U.S. Dist. LEXIS 7035, 1993 WL 183096 (S.D.W. Va. 1993).

Opinion

OPINION

FABER, District Judge.

I.

The Milner Hotel, constructed near the turn of the century, is located directly across Princeton Avenue from the Norfolk Southern railroad yard in downtown Bluefield, West Virginia. In 1977, the Norfolk & Western Railway Company (“N & W” or “railroad”), now a subsidiary of Norfolk Southern, 1 entered into a contract with Milner Hotels, Inc. (“the Milner”) to house and feed its transient train crews and other nonresident employees. This contract, as most recently amended in 1989, required the N & W to pay to the Milner $20.25 per day for each room occupied by a railroad employee, but not less than an amount sufficient to cover sixty room occupancies or $1,215.00 per day. This contract with the N & W provided essentially all of the Milner’s business. The hotel had 102 rooms and approximately ninety of these were set aside at all times for the railroad’s use. The hotel appears to have actually discouraged other business.

In exchange for the N & W guaranteeing occupancy, the hotel agreed to provide certain services as set forth in section 1 of the contract which reads, in pertinent part:

The services to be performed at said Hotel by the Operator for Railroad’s employees include the following----
(d) Maintaining at all times good, clean and sanitary conditions throughout the said hotel;
(e) Observing and complying with all local, state or federal laws and regulations pertaining to the operation of the said Hotel____

Section 10 of the contract was its termination clause. Section 10, as amended, provided:

This agreement shall continue in full force and effect from month to month until ter *343 minated by either party giving.to the other party at least thirty (30) days prior written notice. However, in the event of any default by either party hereto in the performance of its obligations hereunder which is not cured within 30 days of receipt of notice thereof, the other party may, in addition to other remedies available, terminate this agreement.

At about 7:30 a.m. on March 10, 1991, a Sunday morning, a fire broke out on the second floor of the Milner, apparently caused by an electrical malfunction in an oil heater. The fire was quickly contained and damage from the blaze was limited to a few rooms on the second floor. Smoke damage, however, permeated the entire building and there was extensive water damage from efforts to put out the fire.

The railroad removed all of its employees from the hotel pending repair of the damage. The Milner immediately began to clean and deodorize the building and told the railroad it would be available for reoccupancy in a few days. The railroad had received complaints from its employees about the condition of the Milner and these complaints escalated after the fire. The railroad insisted on a thorough inspection of the building before it would allow reoecupancy by its employees.

This inspection was conducted on March 15, 1991, by representatives of the railroad and of the Milner and by Chief R.M. Poe of the Bluefield Fire Department. A detailed written memorandum of the inspection was prepared which documents numerous violations of electrical and fire codes and identifies the presence of crumbling, friable asbestos at several locations in the hotel. G.O. Turner, Pollution Control Coordinator for Norfolk Southern, who was present for the inspection, advised that airborne transmission or tracking by service personnel and occupants could spread fibrous particles of asbestos from virtually any area where it was located to all other areas of the hotel. The general manager and resident manager of the hotel were informally advised by F.A. Williams, Jr., Superintendent of Terminals for Norfolk Southern, that these conditions would have to be remedied before the railroad would allow its employees to reoccupy the hotel. A written copy of the memorandum of the inspection setting out the railroad’s position with regard to reoccupancy was provided to Derek Arbogast, General Manager of the Milner, within a week of the inspection... Admitting that it was not in compliance with the codes and that the. repair work needed to be done, the Milner obtained several estimates from contractors for completion of the electrical repairs and removal of the asbestos. Estimates of the total cost of this work ranged from $60,000 to $120,000. The estimates themselves reflect the extent of work necessary to bring the hotel up to applicable code standards and to remove or otherwise abate the asbestos problem. An estimate obtained from Hieo Specialty Contractors refers to asbestos pipe insulation in the fifth floor hallway, in the basement mechanical room and in a basement room adjacent to the mechanical room; it also refers to boiler insulation and ceiling-plaster which may contain asbestos. An estimate obtained from Allied Refrigeration, Inc. to complete the electrical repairs stated: “[Tjhis is a very difficult job to estimate because of the magnitude of upgrading necessary.”

Before it undertook to have the work done, the hotel asked the railroad for assurances that the railroad would reoccupy the building upon completion of the work. The railroad refused to give such assurances and, on April 9, 1991, mailed written notice to the hotel that it was terminating the Agreement. In its Complaint, the Milner admits receiving this written notice on April 11, 1991. The notice complies in all respects with the notice provisions of the contract. Thereafter, the Hotel’s owners elected not to complete the repairs, but instead sold the hotel and its contents at public auction. The auction was held on April 26, 1.991, and realized the total sum of $56,000 for the building and its contents. 2

In this civil action, originally filed in the Circuit Court of Mercer County, West Virginia, -and removed by defendants to this court, *344 plaintiff Milner Hotel seeks damages for breach of contract. The Milner first maintains that the contract obligates the railroad to pay for rental of rooms at the contract rate and to compensate Milner for lost revenues from food service and concessions from the date of the fire until May 11, 1991, the date the termination was effective, regardless of the fact that the hotel was not occupied by the railroad’s employees at any time after the March 10, 1991 fire.

Second, the Milner charges that the railroad wrongfully terminated the contract, causing the plaintiff a loss of revenues for food, lodging and concessions, and forcing the Milner to sell the hotel at a significant loss. The Milner maintains that the fire damage was corrected by April 1, 1991, at which time the hotel was restored to habitability in spite of continuing code violations and the presence of friable asbestos. The Milner contends that there was no indication that the hotel would have to be closed because of the code violations and that it would have made the necessary repairs if the defendant had returned its personnel to the hotel. The Milner also contends that the railroad had been planning to terminate the contract for some time prior to the fire and seized upon the fire as an excuse to do what it wanted to do all along.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re ASPC Corp.
601 B.R. 766 (S.D. Ohio, 2019)
Rullan v. Goden
134 F. Supp. 3d 926 (D. Maryland, 2015)
Benson v. AJR, INC.
698 S.E.2d 638 (West Virginia Supreme Court, 2010)
Hyperlogistics Group, Inc. v. Kraton Polymers U.S. LLC
437 F. Supp. 2d 735 (S.D. Ohio, 2006)
Cabro Foods, Inc. v. Wells Fargo Armored Service Corp.
962 F. Supp. 75 (S.D. West Virginia, 1997)
Watts v. Butte School District No. 5
939 F. Supp. 1418 (D. Nebraska, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
822 F. Supp. 341, 1993 U.S. Dist. LEXIS 7035, 1993 WL 183096, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milner-hotels-inc-v-norfolk-western-railway-co-wvsd-1993.