Million v. Metropolitan Casualty Insurance

172 N.E. 569, 95 Ind. App. 628, 1930 Ind. App. LEXIS 184
CourtIndiana Court of Appeals
DecidedJuly 3, 1930
DocketNo. 13,886.
StatusPublished
Cited by14 cases

This text of 172 N.E. 569 (Million v. Metropolitan Casualty Insurance) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Million v. Metropolitan Casualty Insurance, 172 N.E. 569, 95 Ind. App. 628, 1930 Ind. App. LEXIS 184 (Ind. Ct. App. 1930).

Opinions

Enloe, J.

— The appellants furnished sand and gravel to the Highways Improvement Company, contractors, for the construction of a portion of State Road 30— Valparaiso-Plymouth Road — in Starke County, Indiana. The contract for the building of said road was made by the Highways Improvement Company with the State of Indiana, acting by and through the State Highway Commission, by John D. Williams, Director. To secure the performance of its said contract, said contractor, agreeable to §8285 Burns 1926, executed its bond with the appellee, the Metropolitan Casualty Insurance Company of New York, as surety thereon, conditioned, inter alia, that the said contractor would pay all lawful claims of materialmen, for materials furnished in the carrying forward and completing said contract, and expressly agreeing that said bond should be for the benefit of any materialman having a just claim against said contractor. This bond was duly approved and accepted by John D. Williams as Director said Commission.

This contract was let and said bond given under and in accordance with the provisions of §8285 Burns 1926, (§18 of the Highway Commission Act), in which section it is among other things provided: . . . Any person, firm or corporation to whom any money shall be due on *630 • account of having performed any labor or furnished any material in the construction of such highway, within one year after the acceptance thereof by the duly authorized board of officers shall furnish the sureties on said bond a statement of the amount due to any such person, firm or corporation. No suit shall be brought against the sureties on said bond until the expiration of sixty days after the furnishing of said statement. If said indebtedness shall not be paid in full at the expiration of said sixty days, said person, firm or corporation may bring an action in his own name upon such bond, said action to be commenced within one year from the date of the acceptance of said highway.” (Our italics.)

It appears from the averments of the complaint, that the said construction contract was entered into in March, 1927, and the bond given as before noted; that the appellants furnished materials — sand and gravel- — used in the construction of said road; that said road had been fully completed and had been accepted by the State, on December 15, 1928, and the final estimate thereon paid on that date. It also appears from said averments that the materials for which this suit was brought, were furnished in July and August of 1927, and that in February, 1928, the appellants filed with the State Highway Commission, in duplicate, a verified statement of their account, and that on March 20, 1928, a copy of the claim so filed was given to the said surety. The complaint, the basis of this suit, was filed February 11, 1929. A demurrer thereto for want of facts was sustained, hence this appeal. The only question to be considered is the sufficiency of the complaint.

The contention of the appellees is embodied in their memorandum filed with their said demurrer, one of the specifications of which is as follows: “Each paragraph of said complaint shows on its face that the plaintiffs herein were subcontractors who furnished materials en *631 tering into the construction of said highway, but that the plaintiffs failed to comply with the terms of the statutes in said cases made and provided, in that the plaintiffs failed, within sixty days after the last item of material had been furnished by them, to file with the State Highway Commission duplicate verified statements of the amount due and owing by the contractor to them; the said plaintiffs, in failing to file such duplicate verified statements of the amount owing them, within the time required by statute, lost the right to proceed against the surety upon said contractor’s bond.”

In short, it is the contention of the appellees that the remedy given by section 2 of the act of 1911 (Acts 1911, p. 437) as amended by the act of 1925 (Acts 1925, p. 130), the same being §6122 Burns 1926, is the sole and only remedy of which a subcontractor, laborer or materialman may avail himself, as against the surety on such bond. On the other hand, it is the contention of the appellants that the remedy given by said act is optional, and that the remedy, as the same existed prior to said amendment of 1925, for a breach of such bond, still remains to such creditor, upon his compliance with §8285, supra.

Before the amendment of said act of 1911 by the act of 1925, this court had held in the cases of Equitable Surety Co. v. Indiana Fuel Supply Co. (1919), 70 Ind. App. 75, 123 N. E. 22, and Illinois Surety Co. v. State, ex rel. (1919), 69 Ind. App. 450, 122 N. E. 30, that the remedy given by said act was cumulative; that the right of action on the bond, as at common law, still remained. The question therefore, which we are now called upon to answer is — Did the amendment of 1925 take from the subcontractors, materialmen, and those performing any service in relation to or in connection with such construction, alteration, etc., as mentioned in said section as amended (§6122 Burns 1926), their right to bring suit *632 upon a contractor’s bond, as such right then existed, for a breach thereof by failing to pay their just claim for labor performed or materials furnished?

It will be noted that by said act of 1911, it was provided in section 1, that the disbursing officer or officers should withhold full payment to the contractor, until such contractor had “paid to the subcontractor or subcontractors or laborers employed in such construction, all bills due and owing the same,” and providing that if the money so retained should not be sufficient to pay-claims in full, they should be prorated, and also providing that in cases where there was no dispute as to the amount of such claim the disbursing officer or officers should pay such claim, taking a receipt therefor, and that the amount so paid should be deducted from funds due the contractor. Said section also provided that said funds 'so held should be retained until such disputes as might arise as to amounts due were settled, when payment should be made.

By section 2 of said act it was provided that provision should be made in the construction contract for the withholding of funds to pay for labor, materials, and to subcontractors, and that the bond should be so conditioned as to render the sureties thereon liable for labor, materials, and to subcontractors, and said section then closed with a proviso, that laborers, materialmen and subcontractors should file their claims with the proper officer within 30 days after the labor was performed or materials furnished.

By section 3 of said act it was declared that said act should not be construed as repealing any other laws for the protection of laborers, subcontractors, or material-men, but as being supplemental thereto. Said sections 1 and 2 were amended in 1925 (Acts 1925, p. 129, §§6121-6122 Burns 1926), but section 3 of said act of 1911 remained as at the time of its passage in 1911.

*633 In Atz v. City of Indianapolis (1928), 87 Ind. App. 580, 158 N. E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monteville v. Terrebonne Par. Con. Gov't
567 So. 2d 1097 (Supreme Court of Louisiana, 1990)
Aetna Causualty & Surety Co. v. Geo. L. Mesker Steel Corp.
223 N.E.2d 768 (Indiana Court of Appeals, 1967)
Jensen v. Pritchard
90 N.E.2d 518 (Indiana Court of Appeals, 1950)
Gates v. Hickman
70 N.E.2d 441 (Indiana Court of Appeals, 1947)
London Lanc. I. Co. v. Comm. S. L. Assn.
4 N.E.2d 688 (Indiana Court of Appeals, 1936)
General Asbestos & Supply Co. v. Aetna Casualty & Surety Co.
198 N.E. 813 (Indiana Court of Appeals, 1935)
General Electric Supply Corp. v. Wiley Electric Co.
191 N.E. 706 (Ohio Court of Appeals, 1933)
Metropolitan Casualty Insurance Co. of New York v. W. Q. O'Neal Co.
174 N.E. 926 (Indiana Court of Appeals, 1930)
Natural Rock Asphalt Corp. v. Highways Improvement Corp.
173 N.E. 330 (Indiana Court of Appeals, 1930)
Concrete Steel Co. v. Metropolitan Casualty Insurance
173 N.E. 651 (Indiana Court of Appeals, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
172 N.E. 569, 95 Ind. App. 628, 1930 Ind. App. LEXIS 184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/million-v-metropolitan-casualty-insurance-indctapp-1930.