Millgard Corp. v. McKee/Mays

49 F.3d 1070, 1995 WL 141176
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 3, 1995
Docket94-10066
StatusPublished
Cited by10 cases

This text of 49 F.3d 1070 (Millgard Corp. v. McKee/Mays) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Millgard Corp. v. McKee/Mays, 49 F.3d 1070, 1995 WL 141176 (5th Cir. 1995).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This Texas diversity case raises the familiar question of a price adjustment to a construction contract. Here a subcontractor encountered wet soil while sinking piers for a foundation. A soil report accompanying, the bid documents signaled dry soil, but the bid documents stated that this soil report was not part of the contract documents. A provision in the subcontract allowed for price adjustment if the subcontractor encountered conditions at variance with those indicated in the subcontract or those ordinarily encountered. Another clause disclaimed all responsibility for the accuracy of the soils investigation. We hold that the subcontract provided for adjustment of contract price in two circumstances and neither was present. We reverse the judgment of the district court entered upon a jury verdict and vacate a judgment against the owner that passed the price increases through to the owner.

I.

On April 5,1978, Dallas County contracted with McKee/Mays for the construction of a new county jail and courthouse, called the Lew Sterrett Justice Center. In November 1978, McKee/Mays solicited bids to subcontract the pier drilling for caisson foundations for the project. McKee/Mays gave Millgard a packet of information about the project, including a set of instructions to bidders, the project specifications, and a copy of some soil boring logs. Mason-Johnston & Associates had conducted the soils investigation at Dallas County’s request. Section 1.21(b)(8) of the instructions to bidder warned that the soil “[rjeport and log of borings is available for Bidders’ information only. • The report is not a warranty of subsurface conditions, nor is it a part of the Contract Documents.” Section 1.21(c) continued:

1. Bidders are expected to examine the site and the subsurface investigation reports and then decide for themselves the character of the materials to be encountered.
2. The Owner, Architect and Construction Manager disclaim any responsibility for the accuracy, true location and extent- of the soils investigation that has been prepared by others. They further disclaim responsibility for interpretation of that data by Bidders, as in projecting soil-bearing values, rock profiles, soil stability arid the presence, level and extent of underground water.

On January 10 and 11, 1979, Millgard’s officials met in Dallas with MeKee/Mays’s officials and discussed the project, including subsurface conditions. McKee/Mays’s officials gave them a copy of the soil report written by Mason-Johnston. Millgard’s officials visually inspected the site, examined soil samples, and spoke with Bill Howard, one of the authors of the soil report. Millgard iri-terpreted. the data to indicate no problem water in the soil, and Howard concurred. At the scheduled pre-bid conference on January 11, Howard told bidders that the driller would encounter dry, cohesive soil that was probably clay, except in the fill and shale layers. He stated that there was no reason to anticipate problem water, and told bidders to look at the soil report and samples. Though one other bidder drilled its own test hole, Millgard did not do so.

On January 18, 1979, Millgard submitted a winning bid of $2,987,000. Millgard then submitted proposed drilling plans to McKee/ Mays for approval. Millgard proposed to insert temporary casings through the fill layer. These casings would clear the way for drilling through the dry clay until the drill reached the sand and gravel layer above the shale, at which point Millgard would insert another casing. The plan reiterated Howard’s statement that “problem volumes of water would not be expected.” McKee/ Mays, Dallas County, and Mason-Johnston reviewed and approved the plans.

*1072 McKee/Mays signed the subcontract with Millgard on March 6, 1979, Section 12.2.1 of the subcontract contained a clause entitled “CONCEALED CONDITIONS”:

Should concealed conditions encountered in the performance of the Work below the surface ... be at variance with the conditions indicated by the Contract Documents, or should unknown physical conditions below the surface of the ground ¡.. differing materially from those ordinarily encountered ... be encountered, the Contract Sum shall be equitably adjusted by Change Order....

Millgard began work in late June 1979. It encountered a layer of quicksand-like material, between five and fifteen feet thick, between the fill area and the sand and gravel layer. These conditions affected seventy-four percent of the holes drilled and made the drilling plans impractical. Millgard spent more money than it expected, completing the work in early January 1980. Mill-gard sought its additional costs, and McKee/ Mays forwarded its claim to Dallas County. Dallas County decided that the conditions were not materially different from those indicated by the contract documents and refused to adjust the contract price.

Millgard brought this diversity suit in federal district court to recover its additional costs. McKee/Mays filed a third-party claim for indemnity from Dallas County. A jury trial followed. The district court redacted section 1.21(b)(3) of the instructions to bidders in the version of the contract that was introduced into evidence. The deleted language read: “nor is [the soil report] a part of the Contract Documents.” The court also excised section 1.21(c)(2), which stated that the owner, architect, and McKee/Mays “disclaim any responsibility for the accuracy ... of the soils investigation [and] interpretation of that data.” The court forbade McKee/ Mays and Dallas County to mention this language or to elicit it at trial. The jury was asked whether Millgard “reasonably relied on the subsurface information furnished to it in its preparation of its bid” and whether conditions “differed materially from those conditions indicated by the subsurface information.” The jury answered “yes" to both questions. The court denied defendants’ motions to set aside the verdict and for. judgment as a matter of law, entered judgment for Millgard, and ordered Dallas County to indemnify McKee/Mays for the full amount of the judgment. McKee/Mays and Dallas County appeal, and Millgard cross-appeals the rate of prejudgment interest.

II.

The district court reasoned that all of the parties “relied on the accuracy of the soil report” and that the disclaimers did not “preclude, for all purposes, reliance on the soil report.” Instead, the court interpreted the disclaimers as insuring “that any inaccuracies in the soil report would be inadequate grounds to rescind, or excuse nonperformance of, [Millgard’s] contractual obligation to construct the caissons.” The district court therefore redacted the disclaimers and phrased the jury instructions to allow Mill-gard to recover an equitable adjustment based’ on its reliance on the soil reports.

Millgard does not rely upon the second half of the concealed conditions clause, dealing with conditions not “ordinarily encountered.” Its sole theory of liability is a breach of contract claim resting on the first half of the clause, which permits a price adjustment if conditions are “at variance with the conditions indicated by the Contract Documents.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
49 F.3d 1070, 1995 WL 141176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/millgard-corp-v-mckeemays-ca5-1995.