Miller v. Simons

59 N.W.2d 837, 239 Minn. 523, 1953 Minn. LEXIS 657
CourtSupreme Court of Minnesota
DecidedJuly 3, 1953
Docket35,931
StatusPublished
Cited by13 cases

This text of 59 N.W.2d 837 (Miller v. Simons) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Simons, 59 N.W.2d 837, 239 Minn. 523, 1953 Minn. LEXIS 657 (Mich. 1953).

Opinion

*524 Dell, Justice.

This is an appeal from orders granting the separate motions of plaintiff and defendant Eichard Miller to strike a portion of the joint answer of defendants Perry Simons and Bryan Construction Company.

On December 19, 1950, a collision occurred between two trucks about two miles east of the city of Northfield, in Eice county, Minnesota, on the Wall Street road. One truck, owned by defendant Bryan Construction Company, was being driven in an easterly direction by defendant Simons. The other truck, owned by plaintiff,, was being driven in a westerly direction by defendant Eichard Miller, and plaintiff was riding in this truck. Plaintiff instituted this action against the defendants to recover for personal injuries resulting from the collision. In his complaint he alleged that defendant Simons was negligent in operating the truck at the time of the collision and that Simons, in driving said truck, was the agent of defendant Bryan Construction Company. The defendants Simons and Bryan Construction Company in their answer admitted that at the time of the collision Simons was driving the truck as. the agent of Bryan Construction Company. They denied that they were negligent and alleged that the collision occurred because of the negligence of plaintiff and the negligence of defendant Eichard Miller who they alleged was the agent of plaintiff in the operation of his truck. As an affirmative defense, they alleged facts which they claim set forth the defense of estoppel by verdict. The allegations' are in paragraph VIII of the answer. 2

*525 Issue having been joined, plaintiff and defendant Richard Miller made separate motions to strike paragraph VIII of the answer of the defendants Simons and Bryan Construction Company upon the ground that it was insufficient to constitute a defense. The court granted the motions and the paragraph was stricken.

From the record it appears undisputed that the action instituted by the Bryan Construction Company referred to in paragraph VIII of the answer was tried and resulted in a verdict against both the plaintiff in this action and defendant Richard Miller for the sum of $1,800, the verdict being returned on May 23, 1951. On June 1 the attorneys for the Millers wrote a letter to the attorneys for Bryan Construction Company informing them that they did not anticipate making a motion for a new trial and requesting information as to the amount required in order to close out the case. On June 4 the attorneys for the Bryan Construction Company wrote to the attorneys for the Millers stating that the amount of the verdict and costs was $1,374.05. The letter itemized the costs, including witness, clerk, and sheriff fees. On June 7 the attorneys for the Millers sent a letter to the attorneys for the Bryan Construction Company and enclosed a draft of the Mutual Service Casualty Insurance Company, the Millers’ insurer, for $1,374.05 in full payment of the verdict and costs. Also enclosed was a re *526 lease and stipulation of dismissal with prejudice for execution. The letter requested that the release, together with the original and one copy of the dismissal, be returned to them before the draft was presented for payment. Compliance was made with this request, and the action was terminated by filing the stipulation of dismissal with prejudice with the clerk of court. No judgment was entered on the verdict.

From the record it is clear that the verdict returned in the case of Bryan Construction Company v. Herbert G-. Miller and Richard Miller determined that neither the Bryan Construction Company nor its employee, Simons, were guilty of negligence. The issue of their negligence was not only litigated in that action but its determination was necessary to warrant the verdict. It is not disputed, nor could it be, that, if judgment had been entered on the verdict, the issue of Bryan Construction Company’s negligence could not be litigated again. 3

The appeal raises two questions: (1) Can a verdict upon which judgment has not been entered ever operate as an estoppel? (2) If the verdict in the former case is operative as an estoppel here, is the defense available to defendant Simons, the employee of the Bryan Construction Company, even though he was not a party to the former action?

It is the general rule of law that a verdict does not operate as an estoppel until it has passed into a judgment. 4 The reason for the rule is that there must be proof of the finality of the adjudi *527 cation in order to constitute an estoppel and ordinarily a verdict is not such an adjudication since it may be set aside upon a motion for a new trial or upon a motion for judgment notwithstanding the verdict. Where the reason for this rule has ceased to exist, it would seem that there is no sound basis for refusal to give conclusive effect to the verdict.

An exception to the general rule that a verdict does not operate as an estoppel until it has passed into a judgment exists in a number of jurisdictions in cases where the parties have acquiesced in the verdict; where, through the lapse of time or other cause, a motion for a new trial or arrest of judgment cannot be granted; where the jurisdiction of the court to set aside or impair the force of the verdict rendered on the merits has come to an end; or where the parties have agreed to let the verdict stand in place of a judgment. 5

While this question has not been squarely before this court until now, we have nevertheless recognized the soundness of the exception by citing opinions of other jurisdictions approving the same. 6

*528 The allegations of the paragraph stricken from the answer, as well as the facts presented in the record before us, bring this case within the ambit of this exception. The manner in which the parties treated the verdict, their acquiesence in it, the payment of the full amount of it together with the taxable costs and disbursements, and the execution and filing of the stipulation of dismissal with prejudice clearly establish the conclusive force and effect of the verdict. Moreover, because of the lapse of time and the procedure followed by the parties, a motion for a new trial or for judgment notwithstanding the verdict could not be granted. Under the circumstances here, to refuse to give the verdict the force and effect of a judgment would be inequitable and unjust. The doctrine of estoppel by verdict is established in the interest of public policy There must be an end to litigation sometime. Where a party has litigated an issue in a former action in a court of competent jurisdiction, he should not be permitted to litigate the issue again to the harassment and vexation of his opponent. Paragraph VIII of the answer was sufficient to permit the proof by the Bryan Construction Company of an estoppel by verdict, and the court erred in striking it as to that defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan v. State Farm Mutual Automobile Insurance
45 A.3d 936 (Court of Special Appeals of Maryland, 2012)
Cenveo Corp. v. Celumsolutions Software Gmbh & Co. Kg
504 F. Supp. 2d 574 (D. Minnesota, 2007)
Moodie-Yannotti v. Swan (In Re Swan)
156 B.R. 618 (D. Minnesota, 1993)
Ellis v. Minneapolis Commission on Civil Rights
319 N.W.2d 702 (Supreme Court of Minnesota, 1982)
Liberty Mutual Insurance Co. v. District of Columbia
316 A.2d 871 (District of Columbia Court of Appeals, 1974)
Lustik v. Rankila
131 N.W.2d 741 (Supreme Court of Minnesota, 1964)
Brooks Realty, Inc. v. Aetna Insurance Co.
128 N.W.2d 151 (Supreme Court of Minnesota, 1964)
Hill v. Stokely-Van Camp, Inc.
109 N.W.2d 749 (Supreme Court of Minnesota, 1961)
Gollner v. Cram
102 N.W.2d 521 (Supreme Court of Minnesota, 1960)
Davis v. Perryman
286 S.W.2d 844 (Supreme Court of Arkansas, 1956)
Gammel v. Ernst & Ernst
72 N.W.2d 364 (Supreme Court of Minnesota, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
59 N.W.2d 837, 239 Minn. 523, 1953 Minn. LEXIS 657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-simons-minn-1953.