Miller Lumber Industries, Inc. v. Brown

416 A.2d 302, 46 Md. App. 399, 1980 Md. App. LEXIS 333
CourtCourt of Special Appeals of Maryland
DecidedJuly 15, 1980
DocketNo. 1643
StatusPublished
Cited by2 cases

This text of 416 A.2d 302 (Miller Lumber Industries, Inc. v. Brown) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller Lumber Industries, Inc. v. Brown, 416 A.2d 302, 46 Md. App. 399, 1980 Md. App. LEXIS 333 (Md. Ct. App. 1980).

Opinion

Lowe, J.,

delivered the opinion of the Court.

This appeal is concerned with a performance bond securing to its owners and their mortgagee the cost of completing the construction of a home. Troubling in our deliberation is the fact that the defaulting builder has not been found in default by judgment or opinion; however, since the issue was not raised on appeal, nor raised as a defense by the surety, 72 C.J.S. Principal and Surety § 255 (1951), we will proceed on the presupposition that the building contract was breached. The evidence was certainly sufficient to so indicate.

On August 20, 1975, Marvin and Billie Brown contracted with White Point Construction Company, Inc., to build a house on land they had purchased in California, Maryland. Their construction lender, Maryland National Bank, required that White Point obtain a performance bond before [401]*401any money was advanced. Mr. Peter Rucker of Miller Lumber agreed to provide a performance bond with Miller Lumber as surety, with the understanding that all checks would include Miller Lumber as payee. Before signing the bond on behalf of Miller, Mr. Rucker wrote on the bottom of the bond just below the signature line, "All draw checks to be made jointly”. Maryland National Bank accepted the bond and began issuing checks payable to White Point and the Browns for the construction of the house, but without including Miller Lumber as payee on the checks. By the spring of 1976, White Point had gone out of business leaving the Brown’s house only partially completed. After making arrangements with another contractor (Cameron Construction Company) to complete the house, the Browns brought suit against White Point and Miller Lumber. Miller Lumber responded to the suit and filed a third party claim against Maryland National Bank alleging that the Bank’s failure to name Miller Lumber as a payee on the checks served to release Miller Lumber from its obligation as surety. The Browns then amended their declaration to include counts against the Bank based upon the allegations in the third party claim. Maryland National Bank moved for summary judgment alleging that it had not contracted and had never agreed to issue checks jointly to Miller. The Bank’s motion for summary judgment was granted at a hearing on February 17, 1978. The judge noted that there had admittedly been no communication directly between Miller and the Bank, and the phrase appended by Miller to the bond was too

"indefinite, vague, in that it doesn’t name what parties jointly it should be, it just says jointly. From the argument I assume the checks were made jointly to the Browns and the construction company.”

On February 23, 1978, at trial, judgment was entered in favor of the Plaintiffs, Marvin and Billie Brown, against Miller Lumber in the amount of $13,372.54. The court found that Miller had made it a condition precedent that draw [402]*402checks were to contain its name jointly, but the "vague” phrase by which it attempted to so indicate was not part of the contract because it appeared after the signatures.

"THE COURT: Well, the Court’s of the opinion that the performance bond, that all above the signatures is the bond. The Court finds that this bond was executed by Mr. White as principal and the Miller Lumber Company as surety. This was a condition placed upon the loan by the bank. The surety is made out to Miller Lumber Company and the Maryland National Bank. This bond was given to the bank, and upon its reliance thereon the money was loaned and disbursed.
I have no doubt that Mr. Rucker made it a condition precedent that the check was to be written in his name, which he testified to, but certainly it’s basic law that you can’t change a written instrument with a verbal contract. This was a verbal instruction to Mr. White. Whatever duty he breached to Mr. Rucker the Court is not here to decide; but when this instrument was executed, that is, Exhibit No. 12, it was relied upon and there was consideration for this loan. In other words, the bank loaned the money to the Browns and the Browns paid for it. But to rule that anything that’s written below the signatures of the people is just unconscienable [sic] to this Court. Anybody could have a contract or a contract could be entered into between two parties and one or the other party at a later date wrote something outside the signatures. I think it’s just unconscienable [sic] that anything some person would write below the signatures would be enforceable. It’s just not good law.
I don’t have any doubt, as I said, that Mr. Rucker placed this condition upon Mr. White. Mr. White by no stretch of the imagination was either the agent of the bank or the agent of the Plaintiffs, the Browns. Mr. White was looking out for himself. In [403]*403fact, there was a condition that he had to give this performance bond and it was for the benefit of the Browns. So, as I say, it’s very clear that certainly the contract, you have to look to the four corners of the contract, and this, in this Court’s opinion, the contract ends with the signatures and not what is placed thereunder. Had this been placed in the body of the contract above the signatures, there would be no dispute; but it was not put in there, and certainly the parties are not bound.
So, the Court feels it has no alternative but to grant the relief as prayed and judgment nisi will be entered up in favor of the Plaintiffs, Mr. and Mrs. Brown, against the Miller Lumber Company.”

From both of those judgments, Miller Lumber appealed on March 13, 1978. On March 28, 1979, we dismissed that appeal pursuant to Md. Rule 605 a. The claims in the action below which had not been adjudicated were the Browns’ claim against White Point and Miller Lumber’s cross-claim against White Point. In response to motions to modify decree and for final judgment on less than all claims, the court below entered a decree of December 7, 1979, and an order of January 2, 1980, making the express findings called for by Md. Rule 605 a, thereby permitting an appeal. Miller Lumber again noted its appeals propitiously.

— summary judgment —

In ruling on the Bank’s motion for summary judgment, the trial judge stated preliminarily:

"Very well. In ruling on the motion for summary judgment the Court must find that there’s no dispute as to a material fact raised relative to the issue of a contract between the Maryland National Bank and the Miller Lumber Company which would make them liable or, conversely so, if it does not find that, then there’s a disputed fact.”,

[404]*404and ultimately decided:

"So, for the reasons stated the Court finds that there is no dispute as to a material fact raised relative to the issue of contractural [sic] obligations between Miller Lumber and the bank which would make them liable, so therefore the Court must grant the motion for summary judgment.”

Because of the precise allegations set forth in the third party claim, that was the proper issue to be determined, i.e., whether there was a contractual obligation undertaken by the Bank under the contract between Miller and White.

". . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wildewood Operations v. WRV Holdings
Court of Special Appeals of Maryland, 2023

Cite This Page — Counsel Stack

Bluebook (online)
416 A.2d 302, 46 Md. App. 399, 1980 Md. App. LEXIS 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-lumber-industries-inc-v-brown-mdctspecapp-1980.