Miller & Long, Inc. v. Intracoastal Living, LLC

2011 NCBC 17
North Carolina Business Court·Decided June 21, 2011·No. 07-CVS-1760·Published

Opinion

Miller & Long, Inc. v. Intracoastal Living, LLC, 2011 NCBC 17.

STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION COUNTY OF BRUNSWICK 07 CVS 1760

MILLER & LONG, INC., ) Plaintiff ) ) v. ) OPINION AND ORDER ON ) PLAINTIFF’S MOTION FOR INTRACOASTAL LIVING, LLC, SUPERIOR ) PARTIAL SUMMARY JUDGMENT CONSTRUCTION CORPORATION, ) WESTERN SURETY, ET AL., ) Defendants )

THIS CAUSE, designated an exceptional case by Order of the Chief Justice of

the North Carolina Supreme Court, pursuant to Rule 2.1 of the General Rules of

Practice for the Superior and District Courts, and assigned to the undersigned Chief

Special Superior Court Judge for Complex Business Cases, now comes before the

court upon Plaintiff Miller & Long Co., Inc.’s (“Miller & Long”) Amended Motion for Partial

Summary Judgment (the “Motion”), pursuant to Rule 56, North Carolina Rules of Civil

Procedure ("Rule(s)"); and

THE COURT, after considering the arguments, briefs, affidavits, other

submissions of counsel and appropriate matters of record, as discussed infra,

CONCLUDES that the Plaintiff's Motion should be GRANTED in part and DENIED in

part, as reflected herein.

Jordan Price Wall Gray Jones & Carlton by Brian S. Edlin, Esq. for Plaintiff Miller & Long Co. Inc.

Jolly, Judge. FACTUAL AND PROCEDURAL BACKGROUND

[1] Unless otherwise indicated herein, the material facts reflected in

paragraphs 2 through 16 of this Opinion and Order exist, are undisputed 1 and are

pertinent to the issues raised by the Motion.

[2] Plaintiff filed its verified Complaint on August 13, 2007, and its Amended

Complaint in this civil action on October 27, 2008. In its Amended Complaint, Plaintiff

alleges seven claims for relief (“Claim(s)”): First Claim for Relief (breach of contract

against Superior for Buildings Two and Three); Second Claim for Relief (breach of

contract against Superior for Building Four); Third Claim for Relief (breach of contract

against Superior for Building Five); Fourth Claim for Relief (quantum meruit against

Superior, Intracoastal and Preserve Holdings); Fifth Claim for Relief (constructive

trust/equitable lien on Buildings Four and Five); Sixth Claim for Relief (enforcement of

lien on funds against Superior and Intracoastal) and Seventh Claim for Relief (attorney

fees against Intracoastal and Superior).

[3] Plaintiff filed the Motion against Defendants Superior Construction

Corporation (“Superior”) and Western Surety Company (“Western”) on April 5, 2008.

[4] On May 21, 2008, Plaintiff withdrew the Motion as to Western because the

parties reached a settlement of all Claims against Western. Pursuant to the terms of

the settlement, Western made payment in full with respect to Plaintiff’s principal Claims

on Buildings 2 and 3. 2 On July 14, 2008, Plaintiff dismissed Western from this action

1 It is not proper for a trial court to make findings of fact in determining a motion for summary judgment under Rule 56. However, it is appropriate for a Rule 56 Order to reflect material facts that the court concludes exist and are not disputed, and which support the legal conclusions with regard to summary judgment. Hyde Ins. Agency v. Dixie Leasing, 26 N.C. App. 138 (1975). 2 Pl. Reply Br. Mot. Summ. J. 1. Plaintiff preserves its Claims for interest and attorney fees against Superior with respect to Buildings Two and Three. pursuant to Rule 41. Therefore, the court will consider Plaintiff’s Motion only as to

Superior.

[5] Plaintiff, a Delaware corporation authorized to do business in North

Carolina, is a full-service, turn-key subcontractor that supplies all reinforced concrete

elements necessary for a total structural frame for large construction projects.

[6] Defendant Intracoastal Living, LLC (“Intracoastal”) is a limited liability

company organized and existing under the laws of the State of North Carolina with its

principal office and place of business located in Southport, Brunswick County, North

Carolina. At all relevant times, Intracoastal was, and is, the owner of real property

known as The Preserve at Oak Island, located on Old Bridge Road, Oak Island,

Brunswick County (the “Project”). The Project was being developed by Intracoastal as a

multiple-building residential condominium community.

[7] Defendant Superior, a corporation organized and existing under the laws

of the State of North Carolina, is a general contractor.

[8] On January 21, 2005, Superior entered into a written contract with

Intracoastal for the construction of Buildings Two and Three and a Clubhouse for the

Project. 3 Superior subsequently entered into contracts with Intracoastal for the

construction of Buildings Four and Five of the Project.4

3 See 2d Am. Compl. ¶ 44, Superior Constr. Corp. v. Intracoastal Living, LLC, Brunswick Co., 07 CVS 2806. 4 Id. ¶ 61. Buildings Two and Three

[9] On or before April 11, 2005, 5 Superior, as general contractor, entered into

a written subcontract agreement with Plaintiff, as subcontractor, pursuant to which

Plaintiff was to furnish and install “all concrete, post-tensioning materials and

accessories, reinforcing steel and accessories, and the placement of all other sub trade

embeds required to construct these concrete frame buildings from the stone columns

(by others) up through and including the roofs” in connection with the construction of

Buildings Two and Three of the Project. This subcontract (the “Buildings Two and

Three Subcontract”) 6 is identified with the number 04MBD006-S01 and is in the amount

of $5,825,000. 7 It is signed by both Plaintiff and Superior. 8

Building Four

[10] On October 14, 2005, Superior sent Plaintiff a Letter of Intent regarding a

subcontract for Building Four (the “Building Four Subcontract”) in the amount of

$1,860,000 for concrete foundations, columns, slab and elevated post-tensioned

decks. 9 In compliance with this letter, Plaintiff obtained a certificate of insurance, dated

October 18, 2005, which identifies Plaintiff as the insured party, Superior as an

additional insured party, the covered operation as Building Four and Superior as the

certificate holder. 10 Plaintiff also secured payment and performance bonds, both dated

5 See Compl. ¶ 16 and Am. Compl. ¶ 46. 6 Clardy Aff. Ex. A. 7 Id. 8 Id. 9 May 22, 2008 Dickman Aff. Ex. A. 10 Id. Ex. B. October 13, 2005, and in the amount of $1,860,000 for Building Four. 11 On these

bonds, Plaintiff is named as the contractor, and Superior is named as the owner. 12

[11] A document purporting to be the Building Four Subcontract, dated October

13, 2005, 13 was generated by Superior, but was never signed by the parties. 14 The

subcontract number associated with this agreement is 05 MBD014-S01. 15

[12] Plaintiff submitted to Application for Payment forms to Superior that reflect

the original contract sum of $1,860,000 and which reference Building Four. 16 These

forms state:

The undersigned Contractor certifies that to the best of the Contractor’s knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.

The Application for Payment forms are signed by Plaintiff.

Building Five

Free access — add to your briefcase to read the full text and ask questions with AI

Miller & Long, Inc. v. Intracoastal Living, LLC, 2011 NCBC 17 (N.C. Super. Ct. 2011).

2011 NCBC 17 (Miller & Long, Inc. v. Intracoastal Living, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Industrial & Textile Piping, Inc. v. Industrial Rigging Services, Inc.
317 S.E.2d 47 (Court of Appeals of North Carolina, 1984)
Hyde Insurance Agency, Inc. v. Dixie Leasing Corp.
215 S.E.2d 162 (Court of Appeals of North Carolina, 1975)
Branch Banking & Trust Co. v. Kenyon Investment Corp.
332 S.E.2d 186 (Court of Appeals of North Carolina, 1985)
Grayson v. High Point Development Ltd. Partnership
625 S.E.2d 591 (Court of Appeals of North Carolina, 2006)
Sweeney Co. v. Engineers-Constructors, Inc.
823 F.2d 805 (Fourth Circuit, 1987)