Miller & Long, Inc. v. Intracoastal Living, LLC

2011 NCBC 16
CourtNorth Carolina Business Court
DecidedJune 21, 2011
Docket07-CVS-1760
StatusPublished

This text of 2011 NCBC 16 (Miller & Long, Inc. v. Intracoastal Living, LLC) is published on Counsel Stack Legal Research, covering North Carolina Business Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller & Long, Inc. v. Intracoastal Living, LLC, 2011 NCBC 16 (N.C. Super. Ct. 2011).

Opinion

Miller & Long, Inc. v. Intracoastal Living, LLC, 2011 NCBC 16.

STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION COUNTY OF BRUNSWICK 07 CVS 1760

MILLER & LONG, INC., ) Plaintiff ) ) v. ) ORDER ON MOTION TO STAY ) AND COMPEL ARBITRATION INTRACOASTAL LIVING, LLC, SUPERIOR ) CONSTRUCTION CORPORATION, ) WESTERN SURETY, ET AL., ) Defendants )

THIS CAUSE, designated an exceptional case by Order of the Chief Justice of

the North Carolina Supreme Court, pursuant to Rule 2.1 of the General Rules of

Practice for the Superior and District Courts, and assigned to the undersigned Chief

Special Superior Court Judge for Complex Business Cases, comes before the court

upon Defendants Superior Construction Corporation’s (“Superior” or “Contractor”) and

Western Surety Company’s (“Western”) (collectively, “Movants”) Motion to Stay and

Compel Arbitration of Claims (the “Motion”). Superior has requested that the court issue

an order staying the relevant claims and compelling Plaintiff to proceed with arbitration

under the terms of the contracts between the parties.

After considering the arguments of counsel and all appropriate matters of record,

the court FINDS:

[1] On January 21, 2005, Superior entered into a written contract with

Intracoastal Living, LLC (“Intracoastal” or “Owner”), the owner of The Preserve Project

(the “Project”), for the construction of Buildings Two and Three and the Clubhouse of the Project. 1 Superior subsequently entered into contracts with Intracoastal for the

construction of Buildings Four and Five of the Project.2

[2] On or before April 11, 2005, 3 Superior, as general contractor, entered into

a written subcontract agreement with Miller and Long, Inc. (“Miller & Long”), pursuant to

which Miller & Long was to furnish and install “all concrete, post-tensioning materials

and accessories, reinforcing steel and accessories, and the placement of all other sub

trade embeds required to construct these concrete frame buildings from the stone

columns (by others) up through and including the roofs” in connection with the

construction of Buildings Two and Three of the Project (the “Buildings Two and Three

Subcontract”). 4 This subcontract is identified with the number 04MBD006-S01 and is in

the amount of $5,825,000. 5 It was signed by both Miller & Long and Superior. 6

[3] On October 14, 2005, Superior sent Miller & Long a Letter of Intent

regarding a subcontract for Building Four (the “Building Four Subcontract”) in the

amount of $1,860,000 for concrete foundations, columns, slab and elevated post-

tensioned decks. 7 In compliance with this letter, Miller & Long obtained a certificate of

insurance, dated October 18, 2005, which identifies Miller & Long as the insured party,

Superior as an additional insured party, the covered operation as Building Four and

1 See 2d Am. Compl. ¶ 44, Superior Constr. Corp. v. Intracoastal Living, LLC, Brunswick Co., 07 CVS 2806. 2 Id. ¶ 61, citing a date of October 14, 2005. But see Br. Supp. Mot. Stay Comp. Arb. Section I (A), suggesting the January contract also included work for Building Four. The AIA contract for Building Four suggests a date of October 14, 2005, consistent with the 2d Am. Compl. ¶ 61. See Rep. Br. Supp. Mot. Stay Comp. Arb. Ex. B. 3 See Compl. ¶ 16 and Am. Compl. ¶ 46; but see Clardy Aff., Ex. A, Building Two and Three Subcontract, dated March 6, 2005. 4 Clardy Aff. Ex. A. 5 Id. 6 Id. 7 May 22, 2008 Dickman Aff. Ex. A. Superior as the certificate holder. 8 Miller & Long has secured payment and

performance bonds, both dated October 13, 2005, and in the amount of $1,860,000 for

Building Four. 9 On these bonds, Miller & Long is named as the contractor, and Superior

is named as the owner. 10

[4] A document purporting to be the Building Four Subcontract, dated October

13, 2005, 11 was generated by Superior, but was never signed by the parties. 12 The

subcontract number associated with this agreement is 05MBD014-S01. 13

[5] Miller & Long submitted Application for Payment forms that reflect the

original contract sum of $1,860,000 and which reference Building Four. 14 These forms

state:

The undersigned Contractor certifies that to the best of the Contractor’s knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.

These Application for Payment forms are signed by Plaintiff.

[6] When relevant, the Buildings Two and Three Subcontract and the Building

Four Subcontract are collectively referred to herein as the “Subcontract(s).”

8 Id. Ex. B. 9 Id. Exs. C, D, respectively. 10 Id. 11 Id. Ex. F. The court notes the cover page of Ex. F describes the project as “7th Avenue South Condominiums, Bali Bay,” with a contracted amount of $587,000 and a subcontract number of 05MBD005-S01. Further internal pages, however, describe the project as one for Building Four, a contracted amount of $1,860,000 and a subcontract number of 05 MBD014-S01. The court concludes the title page affixed to Ex. F was erroneously included in the exhibit. 12 Id. See also Compl. ¶ 25. 13 Dickman Aff. Ex. F, sub-exhibit A. 14 Id. Ex. E. [7] Article 14 of the Buildings Two and Three Subcontract is identical to that

of the Building Four Subcontract, excepting one revision in the first subcontract

regarding the stated location of arbitration proceedings. 15

[8] Paragraph 14.1 16 of each Subcontract provides:

AGREEMENT TO ARBITRATE. All claims, disputes and matters in question arising out of, or relating to, this Agreement or the breach thereof, except for claims which have been waived by the making or acceptance of final payment, and the claims described in Article 14.7, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. (emphasis in original.)

[9] Miller & Long sent Superior a bid proposal for Building Five, dated April

20, 2006, 17 and a request for a letter of intent, dated May 9, 2006. 18 The bid proposal

included a bid amount of $3,503,000 and expressly “assumes that the Inclusions,

Exclusions and Qualifications noted on the Bid Proposals for Buildings 2 and 3 . . . are

applicable to [Miller & Long]’s scope of work unless noted otherwise within this

proposal.” 19 An attachment to Miller & Long’s request for a letter of intent also indicated

a total contract amount of $3,503,000. 20 Superior replied with at least two letters of

intent, dated May 11 and May 23, 2006, respectively, advising Miller & Long of

Superior’s intent to issue Miller & Long a subcontract in the amount of $3,503,000 for

15 Cf. Clardy Aff. Ex. A (Buildings Two and Three Subcontract) and Dickman Aff. Ex. F (Building Four Subcontract). 16 Article 14 specifically addresses the topic of arbitration. The provisions therein are hereinafter referred to as the “arbitration provisions.” 17 July 2, 2008 Dickman Aff. Ex. J. 18 Id. Ex. K. 19 Id. Ex. J. 20 Id. Ex. K (“Schedule of Values”). Defendant argues that Miller & Long submitted this Schedule of Values in accordance with § 16.2 of Superior’s standard written subcontract. See Br. Supp. Mot. Stay Comp. Arb. Section II (E).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cyclone Roofing Co. v. David M. LaFave Co.
321 S.E.2d 872 (Supreme Court of North Carolina, 1984)
Industrial & Textile Piping, Inc. v. Industrial Rigging Services, Inc.
317 S.E.2d 47 (Court of Appeals of North Carolina, 1984)
Branch Banking & Trust Co. v. Kenyon Investment Corp.
332 S.E.2d 186 (Court of Appeals of North Carolina, 1985)
Carteret County v. United Contractors of Kinston, Inc.
462 S.E.2d 816 (Court of Appeals of North Carolina, 1995)
Real Color Displays, Inc. v. Universal Applied Technologies Corp.
950 F. Supp. 714 (E.D. North Carolina, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
2011 NCBC 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-long-inc-v-intracoastal-living-llc-ncbizct-2011.