Milcor I v. Luers

Court of Appeals for the Tenth Circuit·Decided February 28, 2019·No. 18-8000·Unpublished

Opinion

FILED

United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT February 28, 2019

Elisabeth A. Shumaker

Clerk of Court

MILCOR I, LLC,

Plaintiff - Appellant,

v. No. 18-8000 (D.C. No. 2:16-CV-00163-NDF)

SANDY K. LUERS, individually; ERIC (D. Wyoming) CARR in his official capacity as Riverton Community Development Director; DAVE PASKETT, individually and in his official capacity as Riverton Building Inspector; GARY W. BURNETTE, individually; TERRY BETTS in his official capacity as Riverton Construction Board of Appeals Chairman; JOHN L. BAKER, individually; RICHARD P. GARD in his official capacity as Riverton Mayor; MARTIN CANNAN, LEE MARTINEZ, HOLLY JIBBEN, SEAN PETERSON, individually; MIKE BAILEY individually and in his official capacity as Riverton City Council Member; KYLE LARSON, REBECCA SCHATZA, KARLA BORDERS, TIM HANCOCK, in their official capacities as Riverton City Council Members,*

Defendants - Appellees.

*

When a public officer who is a party to an appeal ceases to hold office, “[t]he public officer’s successor is automatically substituted as a party.” Fed. R. App. P. 43(c)(2). For those Defendants-Appellees who no longer hold office, we have substituted their successors as to the official-capacity claims.

ORDER AND JUDGMENT**

Before LUCERO, McHUGH, and MORITZ, Circuit Judges.

Milcor I, LLC (“Milcor”) seeks damages from the City of Riverton, Wyoming (“City”) and several City officials under 42 U.S.C. § 1983 for violations of procedural and substantive due process, and a state breach-of-contract claim. The district court granted summary judgment for the defendants on Milcor’s due process claims and dismissed the state contract claim without prejudice. Milcor now challenges the district court’s grant of summary judgment, which we affirm.

I. BACKGROUND

Milcor owned and operated a Days Inn in Riverton, Wyoming. In 2013, Milcor proposed to remodel the hotel—at that time a single two-story structure where all the doors to motel rooms opened directly to the outside—by adding an adjacent two- story structure that would connect to the original structure by an enclosed corridor.1 In support of the proposed renovations, Milcor submitted building plans to the City. Citing § 903.3.1 of the 2006 International Building Code (“IBC”), these plans stated that a fire sprinkler system would be installed consistent with National Fire Protection Association (“NFPA”) Standard 13. The plans also stated, pursuant to IBC

**

This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Federal Rule of Appellate Procedure 32.1 and Tenth Circuit Rule 32.1.

1 The proposed renovations also included the addition of a business area.

907.2.2, that no fire alarm system would be installed in the business area; however, the plans did not say whether a fire alarm system would be installed in the new guestrooms.

The City granted Milcor a building permit for the renovations, along with a “plan review report” advising that “[f]ire sprinkler system plans shall be submitted for review prior to installation” and that “[s]moke alarms shall be installed per IBC Section 907.2.10.” Suppl. App. at 105–07. The report also stated that the “plan review . . . represents a list of corrections necessary to comply with the requirements” of the relevant building codes, that “[t]he approval of plans and specifications does not permit the violation of any section of federal, state, or local regulations,” and that

[t]he issuance of a permit based on plans, specifications, and other data shall not prevent the City of Riverton from thereafter requiring the correction of errors in said plans, specifications and other data, or from preventing building operations being carried on when in violation of any federal, state or local ordinance, rule or regulation.

Id. at 107. But the report neither mentioned the need to install a fire alarm system nor referenced any section of the IBC governing fire alarm systems.

In June 2014, Milcor submitted fire sprinkler system plans to the City that the City approved. In the same month, Dave Paskett, a city inspector, performed a “rough-in inspection” and raised the need to install a fire alarm system. Afterwards, Mr. Paskett and Sandy Luers (the City’s Director of Community Development and Building Official) met with Kent Milligan, the hotel’s general manager. The parties dispute the nature of the meeting: Ms. Luers contends she advised Mr. Milligan of the need for a fire alarm system, while Mr. Milligan does not recall any discussion of

a fire alarm system. Milcor then completed construction without installing a fire alarm system.

On December 8, 2014, Milcor requested a final inspection of its renovations.

Mr. Paskett refused to perform the inspection until Milcor installed an operational fire alarm system.2 Mr. Milligan sent Ms. Luers a letter protesting Mr. Paskett’s refusal to perform a final inspection, contending that a fire alarm system was never part of the building plans the City had approved and that the project’s architect had concluded the IBC did not require installation of a fire alarm system. In a response to Mr. Milligan’s letter, Ms. Luers stated that while the business section of the addition did not need a fire alarm system, the new guestrooms did because they did not open directly onto a public way, exit court, or yard.

On December 30, 2014, Milcor inquired in an email about formally contesting the City’s decision, but did not actually request an appeal until more than six months later, on July 8, 2015. Instead, Milcor began renting at least some of its newly-built guestrooms without the required certificate of occupancy. On September 14, 2015, the Riverton Board of Appeals (“Board”) dismissed Milcor’s appeal as untimely. Milcor continued renting its rooms without a certificate of occupancy until February 5, 2016, when the City advised Milcor by letter of the alleged code

2 Mr. Paskett contends he also refused to perform the inspection for another reason: because the addition lacked an operational fire suppression system. Milcor denies that Mr. Paskett cited the lack of a fire suppression system as a basis for refusing the inspection and contends that it had installed a fire suppression system. We need not resolve this factual dispute.

violation and ordered Milcor to either install a fire alarm system within thirty days (during which period Milcor would have to perform hourly fire watches) or “cease renting of all rooms.” App. at 213–214. Mr. Milligan requested a hearing to appeal this letter, arguing the City was “attempt[ing] to strong arm [him] into submitting to installation of a fire monitoring system that was never contemplated in the original plans or building permit issued by the City”; he sought relief in the form of “an order that the City immediately issue certificates of occupancy.” Suppl. App. at 182–83. The Board dismissed the appeal, holding that it addressed the same issues as the July 2015 appeal that the Board had already dismissed as untimely. Milcor appealed that dismissal to the Riverton City Council, which upheld the Board’s decision on March 16, 2016.

In June 2016, Milcor filed a complaint in the U.S. District Court for the District of Wyoming, naming the defendants in both their individual and official capacities. The complaint alleged due process violations and requested a temporary restraining order and a preliminary injunction ordering the City to issue a certificate of occupancy. The district court ordered the City to perform an inspection of the fire alarm and fire suppression systems and to issue a certificate of occupancy if the systems were “in compliance with the intent and purpose of the applicable codes.” App. at 29–30.

Free access — add to your briefcase to read the full text and ask questions with AI

Milcor I v. Luers, (10th Cir. 2019).

Milcor I v. Luers (Milcor I v. Luers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Ingraham v. Wright
430 U.S. 651 (Supreme Court, 1977)
Cleveland Board of Education v. Loudermill
470 U.S. 532 (Supreme Court, 1985)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Greene v. Barrett
174 F.3d 1136 (Tenth Circuit, 1999)
Hyde Park Co. v. Santa Fe City Council
226 F.3d 1207 (Tenth Circuit, 2000)
Hulen v. Yates
322 F.3d 1229 (Tenth Circuit, 2003)
Bronson v. Swensen
500 F.3d 1099 (Tenth Circuit, 2007)
Alpine Bank v. Hubbell
555 F.3d 1097 (Tenth Circuit, 2009)
Merrifield v. COUNTY COM'RS FOR COUNTY OF SANTA FE
654 F.3d 1073 (Tenth Circuit, 2011)
Elliott v. Martinez
675 F.3d 1241 (Tenth Circuit, 2012)
Snake River Venture v. Board of County Commissioners
616 P.2d 744 (Wyoming Supreme Court, 1980)
Patzer v. City of Loveland
80 P.3d 908 (Colorado Court of Appeals, 2003)
Cox v. Glanz
800 F.3d 1231 (Tenth Circuit, 2015)
Universal Underwriters Insurance v. Winton
818 F.3d 1103 (Tenth Circuit, 2016)
Lincoln v. BNSF Railway Company
900 F.3d 1166 (Tenth Circuit, 2018)
United States v. Botefuhr
309 F.3d 1263 (Tenth Circuit, 2002)