Milcor I v. Luers

CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 28, 2019
Docket18-8000
StatusUnpublished

This text of Milcor I v. Luers (Milcor I v. Luers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milcor I v. Luers, (10th Cir. 2019).

Opinion

FILED United States Court of Appeals UNITED STATES COURT OF APPEALS Tenth Circuit

FOR THE TENTH CIRCUIT February 28, 2019 _________________________________ Elisabeth A. Shumaker Clerk of Court MILCOR I, LLC,

Plaintiff - Appellant,

v. No. 18-8000 (D.C. No. 2:16-CV-00163-NDF) SANDY K. LUERS, individually; ERIC (D. Wyoming) CARR in his official capacity as Riverton Community Development Director; DAVE PASKETT, individually and in his official capacity as Riverton Building Inspector; GARY W. BURNETTE, individually; TERRY BETTS in his official capacity as Riverton Construction Board of Appeals Chairman; JOHN L. BAKER, individually; RICHARD P. GARD in his official capacity as Riverton Mayor; MARTIN CANNAN, LEE MARTINEZ, HOLLY JIBBEN, SEAN PETERSON, individually; MIKE BAILEY individually and in his official capacity as Riverton City Council Member; KYLE LARSON, REBECCA SCHATZA, KARLA BORDERS, TIM HANCOCK, in their official capacities as Riverton City Council Members,*

Defendants - Appellees. _________________________________

* When a public officer who is a party to an appeal ceases to hold office, “[t]he public officer’s successor is automatically substituted as a party.” Fed. R. App. P. 43(c)(2). For those Defendants-Appellees who no longer hold office, we have substituted their successors as to the official-capacity claims. ORDER AND JUDGMENT** _________________________________

Before LUCERO, McHUGH, and MORITZ, Circuit Judges. _________________________________

Milcor I, LLC (“Milcor”) seeks damages from the City of Riverton, Wyoming

(“City”) and several City officials under 42 U.S.C. § 1983 for violations of

procedural and substantive due process, and a state breach-of-contract claim. The

district court granted summary judgment for the defendants on Milcor’s due process

claims and dismissed the state contract claim without prejudice. Milcor now

challenges the district court’s grant of summary judgment, which we affirm.

I. BACKGROUND

Milcor owned and operated a Days Inn in Riverton, Wyoming. In 2013, Milcor

proposed to remodel the hotel—at that time a single two-story structure where all the

doors to motel rooms opened directly to the outside—by adding an adjacent two-

story structure that would connect to the original structure by an enclosed corridor.1

In support of the proposed renovations, Milcor submitted building plans to the City.

Citing § 903.3.1 of the 2006 International Building Code (“IBC”), these plans stated

that a fire sprinkler system would be installed consistent with National Fire

Protection Association (“NFPA”) Standard 13. The plans also stated, pursuant to IBC

** This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. It may be cited, however, for its persuasive value consistent with Federal Rule of Appellate Procedure 32.1 and Tenth Circuit Rule 32.1. 1 The proposed renovations also included the addition of a business area. 2 907.2.2, that no fire alarm system would be installed in the business area; however,

the plans did not say whether a fire alarm system would be installed in the new

guestrooms.

The City granted Milcor a building permit for the renovations, along with a

“plan review report” advising that “[f]ire sprinkler system plans shall be submitted

for review prior to installation” and that “[s]moke alarms shall be installed per IBC

Section 907.2.10.” Suppl. App. at 105–07. The report also stated that the “plan

review . . . represents a list of corrections necessary to comply with the requirements”

of the relevant building codes, that “[t]he approval of plans and specifications does

not permit the violation of any section of federal, state, or local regulations,” and that

[t]he issuance of a permit based on plans, specifications, and other data shall not prevent the City of Riverton from thereafter requiring the correction of errors in said plans, specifications and other data, or from preventing building operations being carried on when in violation of any federal, state or local ordinance, rule or regulation.

Id. at 107. But the report neither mentioned the need to install a fire alarm system nor

referenced any section of the IBC governing fire alarm systems.

In June 2014, Milcor submitted fire sprinkler system plans to the City that the

City approved. In the same month, Dave Paskett, a city inspector, performed a

“rough-in inspection” and raised the need to install a fire alarm system. Afterwards,

Mr. Paskett and Sandy Luers (the City’s Director of Community Development and

Building Official) met with Kent Milligan, the hotel’s general manager. The parties

dispute the nature of the meeting: Ms. Luers contends she advised Mr. Milligan of

the need for a fire alarm system, while Mr. Milligan does not recall any discussion of

3 a fire alarm system. Milcor then completed construction without installing a fire

alarm system.

On December 8, 2014, Milcor requested a final inspection of its renovations.

Mr. Paskett refused to perform the inspection until Milcor installed an operational

fire alarm system.2 Mr. Milligan sent Ms. Luers a letter protesting Mr. Paskett’s

refusal to perform a final inspection, contending that a fire alarm system was never

part of the building plans the City had approved and that the project’s architect had

concluded the IBC did not require installation of a fire alarm system. In a response to

Mr. Milligan’s letter, Ms. Luers stated that while the business section of the addition

did not need a fire alarm system, the new guestrooms did because they did not open

directly onto a public way, exit court, or yard.

On December 30, 2014, Milcor inquired in an email about formally contesting

the City’s decision, but did not actually request an appeal until more than six months

later, on July 8, 2015. Instead, Milcor began renting at least some of its newly-built

guestrooms without the required certificate of occupancy. On September 14, 2015,

the Riverton Board of Appeals (“Board”) dismissed Milcor’s appeal as untimely.

Milcor continued renting its rooms without a certificate of occupancy until

February 5, 2016, when the City advised Milcor by letter of the alleged code

2 Mr. Paskett contends he also refused to perform the inspection for another reason: because the addition lacked an operational fire suppression system. Milcor denies that Mr. Paskett cited the lack of a fire suppression system as a basis for refusing the inspection and contends that it had installed a fire suppression system. We need not resolve this factual dispute. 4 violation and ordered Milcor to either install a fire alarm system within thirty days

(during which period Milcor would have to perform hourly fire watches) or “cease

renting of all rooms.” App. at 213–214. Mr. Milligan requested a hearing to appeal

this letter, arguing the City was “attempt[ing] to strong arm [him] into submitting to

installation of a fire monitoring system that was never contemplated in the original

plans or building permit issued by the City”; he sought relief in the form of “an order

that the City immediately issue certificates of occupancy.” Suppl. App. at 182–83.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Ingraham v. Wright
430 U.S. 651 (Supreme Court, 1977)
Cleveland Board of Education v. Loudermill
470 U.S. 532 (Supreme Court, 1985)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Greene v. Barrett
174 F.3d 1136 (Tenth Circuit, 1999)
Hyde Park Co. v. Santa Fe City Council
226 F.3d 1207 (Tenth Circuit, 2000)
Hulen v. Yates
322 F.3d 1229 (Tenth Circuit, 2003)
Bronson v. Swensen
500 F.3d 1099 (Tenth Circuit, 2007)
Alpine Bank v. Hubbell
555 F.3d 1097 (Tenth Circuit, 2009)
Merrifield v. COUNTY COM'RS FOR COUNTY OF SANTA FE
654 F.3d 1073 (Tenth Circuit, 2011)
Elliott v. Martinez
675 F.3d 1241 (Tenth Circuit, 2012)
Snake River Venture v. Board of County Commissioners
616 P.2d 744 (Wyoming Supreme Court, 1980)
Patzer v. City of Loveland
80 P.3d 908 (Colorado Court of Appeals, 2003)
Cox v. Glanz
800 F.3d 1231 (Tenth Circuit, 2015)
Universal Underwriters Insurance v. Winton
818 F.3d 1103 (Tenth Circuit, 2016)
Lincoln v. BNSF Railway Company
900 F.3d 1166 (Tenth Circuit, 2018)
United States v. Botefuhr
309 F.3d 1263 (Tenth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Milcor I v. Luers, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milcor-i-v-luers-ca10-2019.