Mike MacMann v. Mike Matthes

843 F.3d 770, 2016 U.S. App. LEXIS 21909, 2016 WL 7174117
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 9, 2016
Docket15-3400
StatusPublished
Cited by1 cases

This text of 843 F.3d 770 (Mike MacMann v. Mike Matthes) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mike MacMann v. Mike Matthes, 843 F.3d 770, 2016 U.S. App. LEXIS 21909, 2016 WL 7174117 (8th Cir. 2016).

Opinion

WOLLMAN, Circuit Judge.

Mike MacMann and' Betty Wilson (collectively, the residents) sued the City of Columbia, Missouri, and City Manager Mike Matthes (collectively, the City), alleging that the City violated their rights under the Columbia City Charter, the Missouri Constitution, and the First and Fourteenth Amendments to the U.S. Constitution by interfering with their participation in a municipal referendum process to repeal two ordinances passed by the City Council in connection with a student-housing development project proposed by Opus Development Company. The district court 1 rejected the residents’ arguments and granted summary judgment to the City. 2 The residents appeal, and we affirm.

*773 On March 19, 2014, the City Council approved an ordinance authorizing the City Manager to enter into a development agreement with Opus to construct a student-housing project in downtown Columbia (Ordinance A). The agreement noted that existing public-utility infrastructure was inadequate to serve the Opus project as proposed; that Opus would contribute $450,000 for infrastructure improvements in the area; and that the City would approve construction of the project, assuming “all requisite permits have been issued by the City.” Within a week after the development agreement was signed, opponents of the project, including the residents, initiated the referendum process under the City Charter and' began to obtain signatures on a referendum petition to repeal Ordinance A (Referendum A). On March 31, while the- Referendum A process was ongoing, the 1 City Manager signed the Opus development agreement authorized by Ordinance A. As required under the City Charter, Referendum A was submitted to the City Clerk on April 8 for certification that the required number of valid signatures had been obtained in support of the referendum.

On May 19, after Referendum A had been filed with the City Clerk, but before it had been certified, the City Council approved Ordinance B, which the district court found “was in all material ways the same as Ordinance A, the subject of the ongoing referendum process,” except that Ordinance B contained a contingency, which stated that if no referendum petition was filed to repeal Ordinance B, then Ordinance A would be automatically repealed. When Ordinance B was approved by the City Council, Ordinance A was still in effect. Opponents of the Opus project,, including the residents, immediately began gathering signatures on a second referendum petition to repeal Ordinance B (Referendum B).

The City Clerk certified the signatures on Referendum A on May 29. Pursuant to the City Charter, “further action [ junder” Ordinance A was “suspended” after certification of Referendum A. The Charter required the City Council to reconsider Ordinance A within thirty days and determine whether it should be repealed. Only if the City Council declined to repeal Ordinance A after reconsideration was the Council required under the Charter to submit the matter to City voters for a determination whether to repeal Ordinance A. On June 16, within the designated thirty-day period, the City Council reconsidered and repealed Ordinance A. At that time, Ordinance B was in effect, although Referendum B. had been submitted to.the City Clerk on June 9 for certification.

On July 7, while certification of the Referendum B signatures was still pending with the City Clerk, the City Council adopted a resolution authorizing temporary sidewalk and parking-lane closures around the Opus development site. 3 The City also began to issue permits for the Opus project under its administrative authority, including land-disturbance, demolition, footings-and-foundation, and building permits. According to the City, the various municipal departments issued these permits because updated building specifics submitted by Opus and infrastrueture-im- *774 provement plans devised by the City established that the affected infrastructure could now accommodate the Opus project.

In the meantime, the City Clerk certified the signatures on Referendum B on July 31. As it did with Ordinance A, the City Council reconsidered Ordinance B and on August 18, repealed the ordinance without submitting the matter to City voters. The City never signed the development agreement with Opus that had been authorized by Ordinance B.

On August 12, the residents filed suit in Missouri state court, alleging that the City had engaged in a “plan and scheme to deny [the residents] their rights under the City Charter and [had] thus violated their rights to free speech, to petition the government, all as protected by the First and Fourteenth Amendments.” They contended that once they initiated the referendum process under the City Charter to challenge Ordinance A, the City could not constitutionally interfere with that ongoing process, either by introducing Ordinance B — an ordinance that was materially identical to the ordinance they were seeking to repeal — or by authorizing permits for the Opus development project — the subject of the ongoing referendum process. The residents also argued that Ordinance B was an unconstitutional effort by the City Council to coerce the residents into giving up their right to participate in the referendum process by conditioning the repeal of Ordinance A on the residents’ capitulation to the adoption of Ordinance B. The City removed the case to federal court on August 21, asserting federal-question jurisdiction under 28 U.S.C. § 1331, and the residents did not seek to remand the case to state court. 4

The district court eventually granted the City’s motion for summary judgment. It concluded that the residents’ rights to participate in the referendum process were not unlimited but were defined and circumscribed by the City Charter,, that the City complied with all the provisions set forth in the City Charter, that the residents received all the process they were due under Missouri law and the City Charter, that the residents had not identified a First Amendment violation, and that the challenged contingency set forth in Ordinance B was not an unconstitutional condition because it did not extract a quid pro quo for citizen participation in the referendum process. The residents challenge each of these conclusions on appeal. 5

“We review the grant of summary judgment de novo, viewing the evidence in the light most favorable to the nonmoving party and drawing all justifiable inferences” in that party’s favor. Putman v. Unity Health Sys., 348 F.3d 732, 733 (8th Cir. 2003). Summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” *775 Celotex Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eggers v. Evnen
D. Nebraska, 2022

Cite This Page — Counsel Stack

Bluebook (online)
843 F.3d 770, 2016 U.S. App. LEXIS 21909, 2016 WL 7174117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mike-macmann-v-mike-matthes-ca8-2016.