Midwest Library Service, Inc. v. Structural Systems, Inc.

566 S.W.2d 249, 1978 Mo. App. LEXIS 2034
CourtMissouri Court of Appeals
DecidedApril 4, 1978
Docket38442
StatusPublished
Cited by13 cases

This text of 566 S.W.2d 249 (Midwest Library Service, Inc. v. Structural Systems, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Library Service, Inc. v. Structural Systems, Inc., 566 S.W.2d 249, 1978 Mo. App. LEXIS 2034 (Mo. Ct. App. 1978).

Opinion

STEPHAN, Judge.

Midwest Library Service, Inc., appeals from a judgment entered upon a jury verdict awarding it $1.00 on its claim for damages for breach of contract. The jury also found for Midwest and against respondent Structural Systems, Inc., on the latter’s counterclaim. Structural Systems did not appeal. We reverse and remand for a new trial. The parties will be referred to by names or as they were designated in the trial court.

Plaintiff is a book wholesaler which contracted with defendant for the construction of an addition to its existing warehouse facilities in St. Louis County. Plans and specifications were to be provided by defendant which is engaged in the business of designing and erecting pre-engineered metal buildings. Plaintiff moved into the addition early in October, 1973.

Problems were encountered with the addition from the beginning. In May of 1973, shortly after construction had begun, one of the foundation walls of the new building buckled and started to collapse; inspection by an independent consulting engineer, a Mr. Jay Lapin, revealed that the problem was caused by the omission of metal tie bars from those walls. Then, about the time plaintiff moved into the addition, leaks were noticed in the roof of the addition and around the guttering which joined the new building with the old one. In November, 1973, about a month after plaintiff had moved in, a heavy rain overflowed the guttering system* spilling into the addition near its juncture with the old building and causing damage to books and supplies stored in that area.

As a result of this overflow, plaintiff again engaged the services of Mr. Lapin, the engineer. Mr. Lapin was asked to check the guttering system and the rest of the addition to determine whether the plans and specifications agreed upon in the contract were satisfied. Based on the findings of that inspection, a reinspection in June of 1974 and a core sampling of the concrete floor taken by a testing laboratory, Midwest filed this action for breach of contract after a number of alleged defects in the building went unremedied by Structural Systems.

In its petition, Midwest charged that defendant breached its contract by constructing the addition in a “defective, unskillful and unworkmanlike manner.” Specifically, it alleged that defendant, inter alia, “designed and installed a defective and inferior guttering system, that it failed to install a *251 vapor barrier underneath the concrete slab of the warehouse, that it failed to provide a four inch rock fill under said slab and failed to install two concrete headwalls, that it failed to adequately fireproof the columns in the building so as to provide a two hour fire rating, and installed a metal inlet instead of concrete, all as required by the contract and specifications.” Midwest sought actual damages of $61,107.23. This figure was composed of $25,307.00 for the alleged defects and omissions in the addition, $26,079.40 for its costs in moving and storing its inventory while the defects were to be remedied and $9,720.83 for the damages to the books and supplies caused by the rain. The prayer was subsequently increased by $12,360.00 to a total of $73,467.23 to cover the cost of moving back into the addition.

Structural denied the essential allegations of the petition and filed a counterclaim for the $7,496.80 balance allegedly still due it under the contract. As noted, the jury returned a verdict for Midwest for $1.00 and found against Structural on its counterclaim.

On this appeal, Midwest claims that the trial court erred when it refused to permit Midwest’s counsel to discuss the issue of damages in detail in the concluding part of the closing argument. We agree and hold that such error warrants a new trial. In the opening part of that argument, plaintiff’s counsel had addressed only the issue of defendant’s liability under the contract, not mentioning either the total amount of damages claimed or any of the component elements of that claim. Defendant’s counsel objected when the attorney for plaintiff attempted in the concluding portion of the argument to discuss the claim of $25,370.00 for defects in the building. That objection was sustained by the trial court.

A plaintiff normally may not, in the second part of his closing argument, introduce an issue which he has not addressed in the opening part. Shaw v. Terminal Railroad Association of St. Louis, 344 S.W.2d 32, 36 (Mo.1961). Nevertheless, a defendant may waive this rule by introducing an issue himself in his closing argument, thereby opening up that issue and allowing plaintiff in the reply part of his argument the opportunity to respond on that point. Sullivan v. Hanley, 347 S.W.2d 710 (Mo.App.1961); Barrett v. Morris, 495 S.W.2d 100 (Mo.App.1973).

Defendant concedes that its counsel did, on several occasions in the closing argument, refer to the amounts plaintiff was claiming. However, this concession is qualified by the contention that such references did not constitute a waiver for the reason that counsel discussed damages only in broad, general terms and that plaintiff was therefore rightly foreclosed from going into a breakdown of the elements of his claim. We cannot agree.

Defendant’s counsel, on three separate occasions in his closing argument, mentioned the total dollar amount of plaintiff’s claim. Twice those comments came in the course of arguments to the effect that plaintiff’s case had focused on minutiae and that the numerous small alleged defects in the building could not possibly support a claim for over $73,000.00 when added together. Furthermore, defense counsel himself discussed one of the elements of that claim, the $9,720.83 sought by plaintiff for rain damage to its books.

We do not believe that plaintiff’s reply to these arguments is properly restricted to the mention of, and refutation of, only the precise damage amount brought up by defendant. The function of the theory of waiver is to permit reply to an issue raised by one’s adversary. The reply must be restricted to that issue, but there is no logical reason to restrict a party to the language in which the adversary frames it. When defense counsel questioned the likelihood that the cost of all the alleged defects could add up to over $73,000.00, plaintiff’s attorney should have been allowed in reply to explain what the elements of that claim were and to show how they could support a claim of that magnitude.

For example, in Sullivan v. Hanley, supra, a personal injury case, plaintiff’s coun *252 sel in the opening portion of the argument had discussed only defendant’s liability, not mentioning plaintiff’s injuries. Defense counsel then addressed principally the issue of liability but also commented on testimony that plaintiff’s doctor had seen him only thirteen times after he left the hospital. This, the court said, “certainly” entitled the plaintiff’s attorney to go into the subject of damages in the closing argument. And in Barrett v. Morris,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tune v. Synergy Gas Corp.
883 S.W.2d 10 (Supreme Court of Missouri, 1994)
Deck v. Kovac
864 S.W.2d 423 (Missouri Court of Appeals, 1993)
Kelly Ex Rel. Kelly v. Jackson
798 S.W.2d 699 (Supreme Court of Missouri, 1990)
Routh v. St. John's Mercy Medical Center
785 S.W.2d 744 (Missouri Court of Appeals, 1990)
Shapiro v. Kravitz
754 S.W.2d 44 (Missouri Court of Appeals, 1988)
State v. Smith
735 S.W.2d 41 (Missouri Court of Appeals, 1987)
Weinbaum v. Weinbaum
679 S.W.2d 384 (Missouri Court of Appeals, 1984)
Leehy v. Supreme Express & Transfer Co.
646 S.W.2d 786 (Supreme Court of Missouri, 1983)
Hart ex rel. Hart v. Forbes
633 S.W.2d 90 (Missouri Court of Appeals, 1982)
Weinbauer v. Berberich
610 S.W.2d 674 (Missouri Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
566 S.W.2d 249, 1978 Mo. App. LEXIS 2034, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-library-service-inc-v-structural-systems-inc-moctapp-1978.