MidAmerica C2L Incorporated v. Siemens Energy Incorporated

CourtCourt of Appeals for the Eleventh Circuit
DecidedMarch 31, 2023
Docket20-11266
StatusUnpublished

This text of MidAmerica C2L Incorporated v. Siemens Energy Incorporated (MidAmerica C2L Incorporated v. Siemens Energy Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MidAmerica C2L Incorporated v. Siemens Energy Incorporated, (11th Cir. 2023).

Opinion

USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 1 of 46

[DO NOT PUBLISH]

In the

United States Court of Appeals For the Eleventh Circuit

____________________

No. 20-11266 ____________________

MIDAMERICA C2L INCORPORATED, a Nevada corporation, Plaintiff- Counter Defendant- Appellant, SECURE ENERGY, INC., a Nevada Corporation, Plaintiff-Appellant, versus SIEMENS ENERGY INC., a Delaware corporation, USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 2 of 46

2 Opinion of the Court 20-11266

Defendant- Counter Claimant- Appellee.

Appeal from the United States District Court for the Middle District of Florida D.C. Docket No. 6:17-cv-00171-PGB-LRH ____________________

Before NEWSOM, BRANCH, and LAGOA, Circuit Judges. LAGOA, Circuit Judge: We GRANT IN PART Secure Energy, Inc.’s petition for panel rehearing, vacate our prior opinion in this appeal, and substi- tute in its place the following opinion. This case is about a business relationship gone bad. In 2006, Secure Energy, Inc.—with the intention of opening a coal gasifica- tion plant in Illinois—approached Siemens Energy, Inc., about pur- chasing some gasifiers and other related equipment. By 2007, the parties had entered into a formal contract, under which Secure would buy the equipment on a payment plan and Siemens would continue to provide updates and repairs to the gasification reactors. USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 3 of 46

20-11266 Opinion of the Court 3

Two problems quickly arose. First, the price of natural gas fell in 2009. As a result, Secure had to change its business plan mul- tiple times and could not keep up with its payments to Siemens. Second, Siemens’s gasification equipment began having problems, as discovered by one of Siemens’s other clients in 2010. By 2012, Siemens began implementing several substantial modifications to its gasifiers in order to get them working properly, but, because Secure had never gotten its plant up and running, Siemens left Se- cure out of the loop. In 2015, Siemens decided to exit the gasifica- tion market entirely, but promised to continue supporting its exist- ing projects, including Secure’s. These problems created the perfect storm for litigation. Se- cure—never having opened, let alone used, its gasification equip- ment—was commercially failing. Secure still owed Siemens mil- lions of dollars for the equipment and had just become aware that the equipment it purchased years earlier had issues. In 2016, after Siemens decided to leave the gasification market, Secure and its subsidiary MidAmerica C2L Incorporated 1 sued Siemens, bringing various fraud- and contract-based claims. Siemens—which was still owed some thirteen million dollars under the contract and which had given Secure multiple payment extensions on that amount— filed a counterclaim against Secure for breach of contract.

1 Forpurposes of this opinion, we refer to MidAmerica as Secure unless oth- erwise expressly noted. USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 4 of 46

4 Opinion of the Court 20-11266

Years into the litigation, Secure sought leave to amend its complaint, which the district court denied due to its untimeliness. Later, the district court excluded Secure’s expert witness, Dr. Her- bert Kosstrin, for relying on an unreliable methodology, and granted summary judgment in Siemens’s favor on each of Secure’s affirmative claims. The case thus proceeded to trial only on Sie- mens’s counterclaim. Prior to trial, the district court excluded evi- dence Secure sought to introduce in support of its breach-of-con- tract affirmative defense. The jury returned a full verdict in Sie- mens’s favor on its counterclaim, and Secure timely appealed. On appeal, we are asked to determine four discrete issues: (1) whether the district court abused its discretion in excluding Se- cure’s expert witness; (2) whether the district court erred in enter- ing summary judgment in Siemens’s favor; (3) whether the district court abused its discretion in denying Secure leave to amend its complaint; and (4) whether the district court abused its discretion in excluding certain evidence at trial and afterwards denying Se- cure’s motion for a new trial. I. FACTUAL AND PROCEDURAL BACKGROUND Secure was formed in 2006 2 for the purpose of developing and constructing a facility in Decatur, Illinois, to convert coal into

2 Secure’s subsidiary, Secure Energy Decatur, LLC, was formed shortly after this time and was the original entity contracting with Siemens. USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 5 of 46

20-11266 Opinion of the Court 5

synthetic natural gas using a process called coal gasification. 3 To that end, Secure began shopping around for a Basic Engineering Design Package (“BEDP”) and Product Design Package (“PDP”) from a coal gasification technology provider, eventually contacting Siemens. Lars Scott and Jack Kenny, the two founders of Secure, met with Rolf Rüsseler and Harry Morehead of Siemens. During these meetings, Siemens represented to Secure that Secure was purchasing a proven technology from Siemens, as it started the equipment’s design in the mid-1970s and it had over twenty years of experience in coal gasification. Additionally, Siemens repre- sented that its current 500-megawatt gasifiers—which Secure was interested in—employed a technologically advanced cooling- screen system that accepted a wide range of feedstock and could achieve “up to >99%” carbon conversion rates. And Siemens had already sold the 500-megawatt gasifiers to one customer in China. Impressed with these representations, Secure decided to use Siemens for its equipment and technology needs. On July 24, 2007, Secure and Siemens entered into a “Memorandum of Understand- ing” memorializing the parties’ intention for Secure to purchase

3 Gasification converts carbonaceous, fossil-fuel based material (e.g., coal) into gas (e.g., synthetic natural gas) by feeding pulverized coal (called feedstock) into large pieces of equipment called gasifiers. See Ronald W. Breault, Gasifi- cation Processes Old and New: A Basic Review of the Major Technologies; 3 Energies 216, 218 (2010), https://www.mdpi.com/1996-1073/3/2/216. USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 6 of 46

6 Opinion of the Court 20-11266

from Siemens two 500-megawatt gasifiers, associated equipment, engineering services, and a process license. On December 21, 2007, Secure and Siemens entered into a formal contract (the “2007 Contract”) whereby Secure would pur- chase Siemens’s products and services for €27,715,000 plus $1,717,000—in total, approximately $40 million. The 2007 Con- tract and every subsequent contract at issue here included a merger clause, which stated that neither “party will be bound by any prior obligations, conditions, warranties or representations.” Secure promptly paid to Siemens the $40 million called for in the 2007 Contract. Secure and Siemens also entered into a licensing agreement (the “2007 LSA”) whereby Secure licensed Siemens’s technology for approximately €11.7 million. Secure was to pay the €11.7 mil- lion licensing fee pursuant to an agreed upon fee schedule within the 2007 LSA. The burners—a core component of Siemens’s gasifiers— were delivered to Secure in Decatur, Illinois, in March 2009. Se- cure alleges that the pins in the cooling screen of the burners were too short and out of specification, although Siemens disputes this characterization. However, Secure only became aware of this al- leged defect during the litigation—it never actually opened or put into operation the Siemens gasifiers after it took possession of them. USCA11 Case: 20-11266 Document: 74-1 Date Filed: 03/31/2023 Page: 7 of 46

20-11266 Opinion of the Court 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guinn v. ASTRAZENECA PHARMACEUTICALS LP
602 F.3d 1245 (Eleventh Circuit, 2010)
City of Tuscaloosa v. Harcros Chemicals, Inc.
158 F.3d 548 (Eleventh Circuit, 1998)
Charles McCorvey v. Baxter Healthcare Corp.
298 F.3d 1253 (Eleventh Circuit, 2002)
Access Now, Inc. v. Southwest Airlines Co.
385 F.3d 1324 (Eleventh Circuit, 2004)
United States v. Richard Junior Frazier
387 F.3d 1244 (Eleventh Circuit, 2004)
Roderic R. McDowell v. Pernell Brown
392 F.3d 1283 (Eleventh Circuit, 2004)
Elsa Cabello v. Armando Fernandez-Larios
402 F.3d 1148 (Eleventh Circuit, 2005)
George v. Smith v. School Board of Orange County
487 F.3d 1361 (Eleventh Circuit, 2007)
Proctor v. Fluor Enterprises, Inc.
494 F.3d 1337 (Eleventh Circuit, 2007)
McCullough Ex Rel. McCullough v. Antolini
559 F.3d 1201 (Eleventh Circuit, 2009)
St. Luke's Cataract & Laser Institute. P.A. v. Sanderson
573 F.3d 1186 (Eleventh Circuit, 2009)
Mesa Air Group, Inc. v. Delta Air Lines, Inc.
573 F.3d 1124 (Eleventh Circuit, 2009)
Spring Co. v. Edgar
99 U.S. 645 (Supreme Court, 1879)
Keeton v. Hustler Magazine, Inc.
465 U.S. 770 (Supreme Court, 1984)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
General Electric Co. v. Joiner
522 U.S. 136 (Supreme Court, 1997)
Douglas C. Kilpatrick v. Breg, Inc.
613 F.3d 1329 (Eleventh Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
MidAmerica C2L Incorporated v. Siemens Energy Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midamerica-c2l-incorporated-v-siemens-energy-incorporated-ca11-2023.