Mid-State Electric, Inc. v. H.L. Libby Corp.

787 F. Supp. 494, 18 U.C.C. Rep. Serv. 2d (West) 372, 1992 U.S. Dist. LEXIS 8516, 1992 WL 63198
CourtDistrict Court, W.D. Pennsylvania
DecidedMarch 11, 1992
DocketCiv. A. 88-1138
StatusPublished
Cited by1 cases

This text of 787 F. Supp. 494 (Mid-State Electric, Inc. v. H.L. Libby Corp.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-State Electric, Inc. v. H.L. Libby Corp., 787 F. Supp. 494, 18 U.C.C. Rep. Serv. 2d (West) 372, 1992 U.S. Dist. LEXIS 8516, 1992 WL 63198 (W.D. Pa. 1992).

Opinion

MEMORANDUM OPINION

LEWIS, District Judge.

This dispute arises from the renovation of a shopping center in LaValle, Maryland. Defendant H.L. Libby Corp. (“Libby”) was the general contractor for the renovation of that shopping center. Plaintiff Mid-State Electric, Inc. (“Mid-State”) was a Subcontractor for electrical work on that project. Mid-State has asserted two claims against Libby — one for breach of contract and one for recovery in quasi-contract for unjust enrichment.

In response, Libby has joined two third-party defendants in the case and has coun *496 terclaimed against Mid-State. Specifically, it has asserted a breach of contract claim, a fraud claim and two RICO claims against Mid-State; a fraud claim and, two RICO claims against third-party defendant Richard Morgan; and a fraud claim against third-party defendant Sunray Electric Supply Co. (“Sunray”).

Currently pending before the court is a motion for partial summary judgment (as to liability only) filed by Libby on its breach of contract claim against Mid-State. This motion presents exactly the same parol evidence rule issue as does an earlier motion in limine filed by Libby. Granting Libby’s motion would effectively determine liability (or lack thereof) on Mid-State’s claims against Libby, too, since their claims both involve the same subcontract — each side arguing that the other breached the contract.

Libby points to the subcontract and the specifications entered into between Mid-State and itself as the basis for its motion. Page 16-1 of the specifications, subsection 1.02, point 10 provides that Mid-State would provide a new emergency generator. Page 16-6, subsection 2.06 of the spécifica-tions provides that Mid-State would “furnish and install the lighting fixtures as noted on Drawings.” Article 7, paragraph A of the subcontract provides that “No part of this Subcontract shall be subcontracted by the Subcontractor except with the express prior written approval of the Contractor.” 1 Both Mid-State and Libby agree that the subcontract and specifications as written and signed contain these provisions.

Both Mid-State and Libby agree that Mid-State did not provide a new emergency generator. Rather, the generator installed in the Zayre’s store at the shopping center in question came from another company. Similarly, Mid-State and Libby agree that Mid-State did not furnish the lighting fixtures. It only installed them. (Third-party defendant Sunray furnished them.) Furthermore, it is undisputed that Mid-State did not obtain the prior written approval of Libby before hiring John Lucarini’s company, Lucarini Electric, as a sub-subcontractor for certain electrical work.

Libby thus claims that Mid-State breached each of these provisions. Mid-State seeks to admit evidence outside of the exact language of the contract to explain why, in its view, its failure'to adhere to the language of the contract does not result in its being liable to Libby. Libby argues that as a matter of law such parol evidence is not admissible.

I. The Integration Clause and the Parol Evidence

The subcontract between Mid-State and Libby . contains the following integration provision;

It is expressly agreed that this Subcontract constitutes the entire and only agreement between the parties hereto, superseding any previous agreements or understandings; that there are no agreements, understandings or covenants between the parties of any kind, nature or description, expressed or implied, oral or otherwise, pertaining to the Work hereunder, which have not been set forth herein; and that this Subcontract cannot be modified, altered, amended, changed or cancelled nor any provision hereof waived or abrogated, except by an instrument in writing duly executed and acknowledged on behalf of the Contractor by a corporate officer or by a representative duly authorized in writing by a corporate officer.

Article 23, paragraph B.

The other relevant contract provisions and points upon which the parties expressly agree are set forth above. In addition, however, Mid-State has submitted an un-controverted affidavit from Robert Stangl, its owner, which contains facts which must *497 be taken as true for the purposes of this summary judgment motion. Construing all facts in favor of Mid-State as non-movant, as this court must, the affidavit reveals the following:

Stangl personally handled all matters regarding Mid-State’s bid for the LaValle job. Stangl says that his first bid, which was accepted by Richard Morgan (whose signature on contracts was approved and ratified by Libby’s president, H.L. Libby), was for all of the electrical work, but that lighting fixtures were to be supplied by others.

Thereafter, Stangl says, H.L. Libby contacted him and negotiated a lower bid, explaining that Mid-State need not provide an emergency generator as part of its contract because Libby had already ordered one from another company. Because the emergency generator was deleted, the bid was reduced by some $48,000. This was in late April, 1986.

Mid-State proceeded to perform work in accordance with the subcontract, but the actual subcontract which is the result of this suit was not presented to Stangl until May 20, 1986, when the first payment was due to Mid-State. Stangl did not bother to read the subcontract at that time. He simply signed it. As Mid-State admits, the written subcontract includes provisions requiring it to provide lighting fixtures and an emergency generator. Stangl states:

At the time of the execution of the document I relied on the integrity and followed the usual industry practice herein that the general contractor, or in this case, H.L. Libby Corporation, to [sic] properly prepare the document pursuant to the original bid proposal and the modifications. That the electrical subcontract documents as executed does [sic] not, in fact, reflect the entire contract as entered into between the parties. '

Stangl Affidavit ¶ 6.

Documents of record indicate that Libby (or some representative thereof) ordered the generator and lighting fixtures at issue from the companies which supplied them, and, further, that such orders were placed before Libby and Mid-State signed the written subcontract in May, 1986.

II. The Parol Evidence Rule

The parties agree that Maryland law applies. They also generally agree that “when the contractual language is clear and unambiguous, and in the absence of fraud, duress or mistake, parol evidence is not admissible to show the intention of the parties to vary, alter or contradict the terms of that contract.” General Motors Acceptance Corp. v. Daniels, 303 Md. 254, 261-62, 492 A.2d 1306, 1310 (1985). Rather, when contract language is clear and unambiguous (which is to be determined objectively), the court must review only the contract itself to determine liability. Id. at 262, 492 A.2d at 1310.

In fact, Mid-State quotes the Maryland Court of Appeals as saying:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
787 F. Supp. 494, 18 U.C.C. Rep. Serv. 2d (West) 372, 1992 U.S. Dist. LEXIS 8516, 1992 WL 63198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-state-electric-inc-v-hl-libby-corp-pawd-1992.