Mid-Ohio Mechanical, Inc. v. Carden Metal Fabricators, Inc.

862 N.E.2d 543, 169 Ohio App. 3d 225, 2006 Ohio 5293
CourtOhio Court of Appeals
DecidedOctober 6, 2006
DocketNo. 2006-CA-13.
StatusPublished
Cited by5 cases

This text of 862 N.E.2d 543 (Mid-Ohio Mechanical, Inc. v. Carden Metal Fabricators, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-Ohio Mechanical, Inc. v. Carden Metal Fabricators, Inc., 862 N.E.2d 543, 169 Ohio App. 3d 225, 2006 Ohio 5293 (Ohio Ct. App. 2006).

Opinion

Gwin, Judge.

{¶ 1} Plaintiff, Mid-Ohio Mechanical, Inc., appeals a summary judgment of the Court of Common Pleas of Guernsey County, Ohio, granted in favor of Eisenmann Corporation. Mid-Ohio assigns two errors to the trial court:

{¶ 2} “I. The trial court erred in concluding that the mechanic’s lien of appellant was barred as a matter of law, and in granting summary judgment to appellee, where: (A) There were (at a minimum) genuine facts in dispute as to whether the equipment and machinery provided constitute ‘materials’ under R.C. 1311.01(i); (B) There was a genuine issue of fact in dispute as to whether the labor and work provided improved the property; (C) There was a genuine issue *227 of fact in dispute as to whether the improvements were fixtures; and (D) There was an admission by appellee that appellant provided ‘work’ to the improvement.

{¶ 3} “II. The trial court erred in concluding that the mechanic’s lien of appellant was barred as a matter of law, and in granting summary judgment to appellee, where: (A) The definition of ‘materials’ in R.C. 1311.01(1) plainly covers equipment and machinery; (B) There was an abundance of evidence demonstrating that Mid-Ohio provided labor, work and materials to the improvement, which is lienable under R.C. 1311.02; and (C) The tax cases cited by appellee and apparently relied upon by the court have no application.”

{¶ 4} Mid-Ohio’s statement pursuant to Loc.R. 9 asserts the trial court erred as a matter of law and also because there were genuine issues of material fact.

{¶ 5} Certain facts are undisputed. LDMTPlastech (“LDM”) is the owner of a factory in Byesville, Ohio. LDM contracted with defendant appellee Eisenmann Corporation to upgrade the paint line in the factory. The paint line applies high-tech coatings to car bumpers. The overall project included replacing a cure oven and its platform under the roof with an oven and platform mounted above the roof, replacing existing paint-sludge removal equipment, replacing and adding paint-booth scrubbers and other pollution control equipment, replacing and adding robotic paint sprayers, moving and extending the conveyor, and numerous other items.

{¶ 6} Eisenmann is an Illinois process-engineering firm that designs, manufactures, buys, sells, and installs factory machinery and equipment. Eisenmann subcontracted with Carden Metal Fabricators, Inc. to remove old equipment and install new equipment. Carden, in turn, subcontracted with appellant Mid-Ohio to work on structural steel beams and columns, on a roof, and on oven modules installed and welded to the structural steel.

{¶ 7} Before the project was completed, Carden went out of business. Eisenmann then issued purchase orders to Mid-Ohio to have Mid-Ohio continue to work on Carden’s project. Shortly thereafter, Eisenmann asked Mid-Ohio to cease work.

{¶ 8} Carden had not paid Mid-Ohio in full, so Mid-Ohio filed a mechanic’s lien for $768,396.67. Eisenmann also filed a mechanic’s lien for $897,052 and a second one for $1,599,269.

{¶ 9} Thereafter, LDM insisted Mid-Ohio’s lien be bonded off to protect its property. Under an indemnity arrangement, Eisenmann provided the cash deposit, and Mid-Ohio’s claim transferred to the deposit, freeing its lien against the property.

{¶ 10} Mid-Ohio then voluntarily dismissed all claims against LDM and addressed its claim to the cash bond that Eisenmann had posted. Eisenmann *228 argued that when Mid-Ohio dismissed the other defendants, any and all parties who might be liable to Mid-Ohio were gone from the suit. Eisenmann moved the court to release the cash deposit held in escrow. The court overruled Eisenmann’s motion and continued the escrow. Eisenmann asserted that Mid-Ohio’s work was defective and that it was not entitled to the funds.

{¶ 11} The trial court’s judgment merely stated that Eisenmann had met its burden on the summary judgment, and Mid-Ohio had not.

{¶ 12} R.C. 1311.02 states: “Every person who performs work or labor upon or furnishes material in furtherance of any improvement undertaken by virtue of a contract, express or implied, with the owner, part owner, or lessee of any interest in real estate, or his authorized agent, and every person who as a subcontractor, laborer, or materialman, performs any labor or work or furnishes any material to an original contractor or any subcontractor, in carrying forward, performing, or completing any improvement, has a lien to secure the payment therefor upon the improvement and all interests that the owner, part owner, or lessee may have or subsequently acquire in the land or leasehold to which the improvement was made or removed.”

{¶ 13} R.C. 1311.01 sets forth definitions:

{¶ 14} “(D) ‘Subcontractor’ includes any person who undertakes to construct, alter, erect, improve, repair, demolish, remove, dig, or drill any part of an improvement under a contract any person other than the owner, part owner, or lessee.

{¶ 15} “ * * *

{¶ 16} “(I) ‘Materials’ means all products and substances including, without limitation, any gasoline, lubricating oil, petroleum products, powder, dynamite, blasting supplies, and other explosives, tools, equipment, or machinery furnished in furtherance of an improvement.

{¶ 17} “ * * *

{¶ 18} “(J) ‘Improvement’ means constructing, erecting, altering, repainting, demolishing, or removing any budding or appurtenance thereto, fixture, bridge, or other structure, and any gas pipeline or well including, but not limited to, a well drilled or constructed for the production of oil or gas; the furnishing of tile for the drainage of any lot or land; the excavation, cleanup, or removal of hazardous waste material or waste from real property; the enhancement or embellishment by seeding, sodding, or planting any shrubs, trees, plants, vines, small fruits, flowers, or nursery stock of any kind; and the grading or filling to establishing grade.”

*229 {¶ 19} We note at the outset that the Revised Code sets forth certain requirements that must be strictly performed to perfect the lien. However, questions regarding the value of the work and any setoffs are issues concerning the value of the lien and not the enforceability of the lien; see Wame v. Bamfield, Guernsey App. No. 2005-CA-33, 2006-Ohio-850, 2006 WL 438674. Under the Revised Code’s definition of improvement, it is not necessary for the work to add value to the property, so the value of the lien is irrelevant for this analysis.

{¶ 20} Eisenmann argues that Mid-Ohio has no mechanic’s lien for work or materials supplied for personal property under the current version of the statute. This argument presents two separate issues: the question of the materials and labor and the question of whether the property is personal property.

{¶ 21} The statute was amended in 1991. Am.Sub.H.B. No. 238, 143 Ohio Laws, Part III, 3676, 3680. Prior to 1991, the Revised Code and case law allowed mechanic’s liens to attach to personal property even when there was no underlying real property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
862 N.E.2d 543, 169 Ohio App. 3d 225, 2006 Ohio 5293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-ohio-mechanical-inc-v-carden-metal-fabricators-inc-ohioctapp-2006.