Mid-Country Meats, Inc. v. Woodruff-Evans Construction

334 N.W.2d 332, 1983 Iowa App. LEXIS 1603
CourtCourt of Appeals of Iowa
DecidedApril 8, 1983
Docket2-67205
StatusPublished
Cited by10 cases

This text of 334 N.W.2d 332 (Mid-Country Meats, Inc. v. Woodruff-Evans Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-Country Meats, Inc. v. Woodruff-Evans Construction, 334 N.W.2d 332, 1983 Iowa App. LEXIS 1603 (iowactapp 1983).

Opinion

*334 DONIELSON, Judge.

Plaintiff corporation appeals the dismissal of its petition alleging breach of a construction contract entered upon defendant contractor’s motion for judgment notwithstanding the jury’s failure to return a verdict after deliberating three days and remaining deadlocked in a four to four split vote on liability. On appeal the plaintiff contends that the trial court erred (1) by sustaining defendant’s motion for judgment notwithstanding the jury’s failure to return a verdict; (2) by refusing to give plaintiff’s requested jury instructions regarding the applicable standard of care and negligence; (3) by refusing to give a portion of plaintiff’s requested jury instruction regarding express warranty; (4) by limiting evidence and testimony regarding consequential damages resulting from allegedly lost profits and wasted overhead expenses; (5) by refusing to give plaintiff’s requested jury instructions regarding consequential damages; (6) by instructing the jury that, as a matter of law, plaintiff had waived any claims for damages arising from defendant’s failure to timely complete the construction; and (7) by sustaining defendant’s motion for adjudication of law points and striking the express and implied warranty provisions contained in divisions II and III of plaintiff’s petition. Plaintiff seeks a new trial. We reverse and remand.

Our scope of review is on assigned errors. Iowa R.App.P. 4.

I.

Plaintiff, Mid-Country Meats, Inc., produces various meats and sausage. In 1978 plaintiff entered into a contract with the defendant, Woodruff-Evans Construction Co., for the construction of a meat processing plant. The contract price was $643,828 with construction to be completed by November 1, 1978.

Construction on the project was delayed for various reasons which the parties dispute, and the project was not completed by November 1st. Plaintiff initially agreed to a thirty-day extension of the contract. Subsequently, in late January 1979, plaintiff executed a waiver of any claim for damages against defendant arising from delay in completion of the building. On January 30,1979, plaintiff accepted the building, holding back $25,000 pending completion of certain details on the building.

After accepting the building, plaintiff commenced production. In late February, 1979, the dry room roof began leaking. A subcontractor attempted to remove snow from the roof, but this merely resulted in larger holes being torn in the roof. A large amount of pepperoni curing in the dry room began to mold and ultimately was destroyed. The plant closed on April 28,1979. The roof was finally completed in June, but the plant never reopened. Plaintiff asserted that loss of its product and the consequent inability to fulfill contracts completely destroyed its business, resulting in foreclosure and loss of all assets.

On September 26, 1979, plaintiff filed a petition seeking $1,500,000 damages for defendant’s alleged breach of contract, breach of implied warranty, breach of express warranty, and negligence. The case was subsequently tried to a jury. There was considerable testimony regarding the construction contract, the construction itself, and the circumstances surrounding plaintiff’s acceptance of the building.

After deliberating for three days, the jury remained deadlocked at a 4 to 4 vote and was released. Defendant then filed a motion pursuant to Iowa Rule of Civil Procedure 243 for judgment notwithstanding the jury’s failure to return a verdict, asserting that the evidence was insufficient as a matter of law to prov.e either breach of contract or damages related thereto. Trial court subsequently sustained the motion and entered judgment for defendant. The court concluded that plaintiff accepted the building knowing the roof had not been completed and would not be completed until spring when the work could be properly done. Plaintiff then instituted this appeal.

II.

The plaintiff’s first contention is that the trial court erred in granting defendant’s *335 motion for judgment notwithstanding the jury’s failure to return a verdict. We must agree with plaintiffs.

Our review of this issue is limited to the grounds urged in defendant’s earlier motion for directed verdict since a motion for judgment notwithstanding the verdict must stand or fall on the grounds asserted in the motion for directed verdict. Meeker v. City of Clinton, 259 N.W.2d 822, 827-27 (Iowa 1977). The defendant’s motion for directed verdict was predicated on the claim that the evidence was insufficient to submit the issues of breach of contract or negligence to the jury. In determining whether the trial court correctly ruled on this issue, we view the evidence in accordance with the same principles which govern the trial court’s decision:

In determining whether a jury question was engendered when a party seeks a directed verdict, dismissal, or judgment notwithstanding the verdict, the trial court views the evidence in the light most favorable to the party against whom the motion was made regardless of whether such evidence is contradicted and every legitimate inference which may be reasonably deducted therefrom must be carried to the aid of the evidence and if reasonable minds can differ on the issue it is for the jury. Schiltz v. Cullen-Schiltz & Assoc., Inc., 228 N.W.2d 10, 17 (Iowa 1975).
Our function is to review the evidence to determine, not whether it proves defendants’ negligente] . .. but whether it is sufficient so the trial court was justified in submitting the question to the jury as the trier of facts. Miller v. Young, 168 N.W.2d [45, 51 (Iowa 1969)].

Meeker, 259 N.W.2d at 828.

Plaintiff claimed, in its petition, that the building was not completed according to contract specifications and that the construction was not timely completed. It also claims that defendant constructed the building negligently, causing the roof to leak which, in turn, caused the meat to spoil. The trial court had instructed the jury that, as a matter of law, plaintiff had waived any claims for damages arising from defendant’s failure to timely complete the construction, despite plaintiff’s arguments that the alleged waiver was without knowledge of all the relevant facts. Plaintiffs also assert that, prior to accepting the building, the defendant assured plaintiff that the roof was weatherproof. The defendant disagrees and contends that the parties were aware that the roof bf the dry room was not completed when the plaintiff took the building and began production.

In its ruling on defendant’s motion for judgment notwithstanding the jury’s failure to return a verdict, the court ruled that there was not sufficient evidence to show a breach of contract by defendant. Specifically, the court ruled that plaintiff accepted the building with full knowledge that the roof had not been completed and that the construction was properly completed in the spring. The court did not specifically address the other theories urged by plaintiff in its petition or the other matters urged by defendant in its motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BBSERCO v. Green Bay Dressed
Eighth Circuit, 2003
Housing 21 v. Atlantic Home
Eighth Circuit, 2002
MUTUAL SERVICE CAS. INS. CO., INC. v. Armbrecht
142 F. Supp. 2d 1101 (N.D. Iowa, 2001)
Hasselman v. Hasselman
596 N.W.2d 541 (Supreme Court of Iowa, 1999)
Aetna Casualty & Surety Co. v. Leo A. Daly Co.
870 F. Supp. 925 (S.D. Iowa, 1994)
Hagan v. Liberty Loan Corp.
423 N.W.2d 886 (Court of Appeals of Iowa, 1988)
Bushman v. Cuckler Building Systems
421 N.W.2d 145 (Court of Appeals of Iowa, 1988)
Oberreuter v. Orion Industries, Inc.
398 N.W.2d 206 (Court of Appeals of Iowa, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
334 N.W.2d 332, 1983 Iowa App. LEXIS 1603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-country-meats-inc-v-woodruff-evans-construction-iowactapp-1983.