Mid-Atlantic Business v. Virginia Dmv
This text of 606 S.E.2d 835 (Mid-Atlantic Business v. Virginia Dmv) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
MID-ATLANTIC BUSINESS COMMUNICATIONS, INC.
v.
VIRGINIA DEPARTMENT OF MOTOR VEHICLES.
Supreme Court of Virginia.
*836 Hugh M. Fain, III, Richmond (Mary Elizabeth Davis; M.F. Connell Mullins, Jr.; Spotts Fain, on briefs), for appellant.
Julie M. Whitlock, Asst. Atty. Gen. (John S. Westrick, Sr. Asst. Atty. Gen.; Eric K.G. Fiske, Sr. Asst. Atty. Gen., on brief), for appellee.
Present: All the Justices.
LACY, Justice.
The Virginia Public Procurement Act, Code §§ 2.2-4300 through -4377 (VPPA or the Act), requires that a claim against a public body based on a contract awarded under the Act must be filed within six months of the final decision of the public body. Code § 2.2-4363(D). Mid-Atlantic Business Communications, Inc.'s (MABC) *837 claim against the Virginia Department of Motor Vehicles (the Department) was denied in a letter from the Department dated August 22, 2002 and in a letter from the Comptroller dated January 31, 2003. MABC filed this litigation on February 27, 2003. Because the August 22, 2002 letter was the final decision of the Department, the trial court correctly dismissed MABC's motion for judgment because it was not filed within the Act's six-month limitation period.
Facts
The Department awarded MABC a contract to create and install an Internet Call Center. The terms of the Vendors Manual were incorporated into the Contract. Code § 2.2-4363(B) and (C); Department of General Services, Commonwealth of Virginia, Vendors Manual (Dec.1998). The contract was for a fixed price of $207,111.78 and was to be performed and paid in two phases. The first phase was completed and paid for without incident. In June 2002, the Department's Manager of MIS Budget and Procurement, George S. Goodman, Jr., notified MABC by letter that the Department was rejecting the work done under the second phase because MABC's product had a number of security issues. MABC was given 30 days to redesign the system to meet the Department's requirements. In a July 23, 2002 letter, Goodman told MABC that its response was unsatisfactory, that the contract was cancelled, and that the Department would not pay the remaining $102,451.67 due under the contract for the second phase.
MABC appealed the Department's decision to the Procurement Appeals Board but was notified that the Board had no jurisdiction to entertain the appeal. MABC then sent a letter, dated July 31, 2002, to the Department arguing that the alleged security problems were new requirements not previously listed in the contract and requesting that the Department honor the full payment price under the contract. Goodman responded by letter on August 22, 2002, stating, "Your claim for payment is hereby denied."
MABC then sent a letter, dated August 26, 2002, to Asbury W. Quillan, Commissioner of the Department, requesting payment of the second phase amount. The letter stated that legal action would be taken if no response was received within 10 days. On August 30, 2002, Thomas P. Falat, Assistant Commissioner of the Department, notified MABC that "the DMV stands by the decision to cancel." On October 23, 2002, MABC mailed a certified letter to the Comptroller of the Commonwealth and the Commissioner of the Department seeking payment pursuant to Code § 2.2-814 (formerly Code § 2.1-223.1). As required by Code § 2.2-815, the Commissioner informed the Comptroller on January 29, 2003 that MABC's claim had been previously denied and he recommended that the Comptroller deny MABC's pecuniary claim. In a letter dated January 31, 2003, the Comptroller denied MABC's claim.
Proceedings
MABC instituted this litigation on February 27, 2003 against the Department and the Comptroller claiming breach of contract and seeking damages in the amount of $102,451.67, the remainder of the contract price for the second phase. The defendants filed a Plea in Bar, Demurrer, and Grounds of Defense, arguing that the Comptroller was not a proper party and that the claim was filed beyond the Act's six-month limitations period and therefore was time-barred. The trial court sustained the defendants' Demurrer and Plea in Bar, dismissed the Comptroller as a party, and held that because the August 22, 2002 letter was the final decision of the Department, MABC's action was untimely. The trial court also held that Code § 8.01-229(D) did not toll the running of the limitations period. We awarded MABC an appeal.
Discussion
On appeal, MABC contends that the action was timely filed first because the January 31, 2003 letter from the Comptroller was the Department's final decision. The VPPA states that a decision by a "public body" is final unless appealed within six months of the final decision of the "public body." Code § 2.2-4363(D). MABC's first argument is based on the definition of "public body." The Vendors Manual, which was promulgated pursuant to the VPPA and incorporated into the contract between the Department *838 and MABC, recites that a claim denial is final if issued by an agency's "purchasing office." "Purchasing office" is not defined in the Manual, and MABC argues that "because of the significance attached to the final decision," the phrase should be interpreted as meaning the head of the agency involved.
This interpretation is further supported, according to MABC, when considered in conjunction with the procedure for filing a pecuniary claim against the Commonwealth. This procedure, Code §§ 2.2-814 and -815, provides that pecuniary claims against the Commonwealth must be presented first to the "head of the ... agency" against which the claim is lodged and that officer must make a recommendation on the claim to the Comptroller. Reading these provisions together, MABC concludes that the only decision of the head of the Department was contained in the January 31, 2003 letter and that letter, therefore, constitutes the final decision by the Department.
This argument fails first because the absence of a definition of "purchasing office" in the Vendors Manual does not make the term ambiguous or in need of further interpretation. As applied to these facts, there was no ambiguity about the position held by Goodman. Each letter Goodman signed stated his title as Manager of the MIS/ITS Budget and Procurement Office. This designation is also recited on the signature line of the contract.
MABC's argument also fails because it seeks to incorporate into the VPPA terms contained in a separate, unrelated procedure. The VPPA is a specific statute relating to the acquisition of goods and services by public bodies. We have previously held that the provisions of that Act, not the predecessors to Code §§ 2.2-814 and 2.2-815, apply to disputes arising from goods or services provided under the VPPA. The Dr. William E.S. Flory Small Bus. Dev. Ctr. v. Commonwealth, 261 Va. 230, 239, 541 S.E.2d 915, 920 (2001). Therefore, we decline to interpret provisions of the VPPA by incorporating provisions relating to filing pecuniary claims against the Commonwealth.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
606 S.E.2d 835, 269 Va. 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-atlantic-business-v-virginia-dmv-va-2005.