Michigan 180 LLC v. Traffic Tech, Inc.

2025 IL App (1st) 242043-U
CourtAppellate Court of Illinois
DecidedSeptember 24, 2025
Docket1-24-2043
StatusUnpublished

This text of 2025 IL App (1st) 242043-U (Michigan 180 LLC v. Traffic Tech, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan 180 LLC v. Traffic Tech, Inc., 2025 IL App (1st) 242043-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (1st) 242043-U Order filed: September 24, 2025

FIRST DISTRICT THIRD DIVISION

No. 1-24-2043

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT ______________________________________________________________________________

MICHIGAN 180 LLC, ) Appeal from the ) Circuit Court of Plaintiff-Appellee, ) Cook County ) v. ) No. 21 L 10243 ) TRAFFIC TECH, INC., ) Honorable ) Daniel J. Kubasiak, Defendant-Appellant. ) Judge, presiding. _________________________________________________________________________

JUSTICE ROCHFORD delivered the judgment of the court. Presiding Justice Martin and Justice Reyes concurred in the judgment.

ORDER

¶1 Held: We reversed the judgment in favor of plaintiff on its breach of contract claim, holding that the parties never entered into a binding contract because they never agreed on certain material terms. We entered judgment in favor of defendant.

¶2 Plaintiff, Michigan 180 LLC, filed a breach of contract action against defendant, Traffic

Tech, Inc., alleging that the parties entered into a contract whereby plaintiff would build out office

space in the building at 180 North Michigan Avenue (Building) and then lease that space to

defendant for a five-year term. Defendant subsequently determined that the agreement was null

and void and never moved into the office space or paid rent thereon. Plaintiff sought damages for

unpaid rent, real estate taxes, operating expenses, and mitigation costs. Following a bench trial,

the court entered judgment in favor of plaintiff and awarded it $593,893.06 in damages. Defendant No. 1-24-2043

appeals, arguing that the parties never entered into a binding contract obligating it to lease the

office space in the Building. We reverse the judgment for plaintiff and enter judgment for

defendant.

¶3 In its amended complaint for breach of contract, plaintiff alleged that it was the owner of

the Building and that on December 22, 2010, the parties entered into a lease for defendant to rent

office space on the 12th floor. Defendant moved into the 12th-floor offices. On December 18,

2014, the parties entered into a fourth amendment to the lease (Fourth Amendment), which stated

that plaintiff would build out office space on the seventh floor (Suite 700) at a cost of $39,900 “in

substantial conformity with a Space Plan to be mutually approved by Landlord and Tenant.” Any

extra buildout costs in excess of $39,900 would be borne by defendant. After the buildout,

defendant would relocate and rent the office space in Suite 700 on or about February 1, 2015, for

a term ending on January 31, 2021.

¶4 The Fourth Amendment further stated that plaintiff also would build out office space on

the eighth floor (Suite 800) at a cost of $81,970 “in substantial conformity with a Space Plan to be

mutually approved by Landlord and Tenant.” Any extra buildout costs in excess of $81,970 would

be borne by defendant. After the buildout, defendant would rent the office space in Suite 800 (in

addition to Suite 700) on February 1, 2016, for a five-year term ending on January 31, 2021.

¶5 In accordance with the Fourth Amendment, plaintiff built out the office space in Suite 700

pursuant to a mutually agreed-upon space plan and defendant relocated there. However, the parties

never mutually agreed to a space plan and buildout for the office space in Suite 800 because

defendant decided that Suite 800 would not provide it with enough space for its employees.

Instead, defendant informed plaintiff it wanted to lease the entire eighth floor, consisting of Suites

800 and 810.

-2- No. 1-24-2043

¶6 Plaintiff notified defendant that it already had a tenant in Suite 810, but that it would

attempt to relocate that tenant to accommodate defendant’s request for the entire eighth floor.

Plaintiff warned defendant that the relocation of the other tenant could delay the move to the eighth

floor until after June 2016. Defendant acquiesced in the delay “because it wanted the entire floor.”

¶7 On January 11, 2016, plaintiff delivered a space plan for the buildout of the entire eighth

floor to defendant for its approval. On February 18, 2016, defendant approved and signed off on

the January 11 space plan. Plaintiff thereafter obtained construction bids from contractors.

Defendant subsequently expressed unhappiness with the projected costs of the eighth-floor

buildout and requested that plaintiff increase the amount of the costs which it would cover.

Between August 2016 and October 2016, plaintiff repeatedly made changes to the space plan to

try and reduce the costs. However, on October 27, 2016, defendant sent plaintiff a letter stating

that it was ending the negotiations regarding the eighth-floor buildout, explaining:

“Pursuant to the Fourth Amendment to Lease, dated December 18, 2014, [defendant] was

supposed to have taken possession of the 8th floor by February 1, 2016. Due to the buildout

of the 8th floor being delayed for close to nine months, [defendant] was forced to expand

in other markets outside of Chicago. Consequently, [defendant] no longer wishes to occupy

the 8th floor at this time, and believes the expansion clause in the current lease to be null

and void.”

¶8 On November 7, 2016, plaintiff responded to defendant’s October 27 letter, denying that it

caused any delays in the buildout and stating that defendant was in breach of the Fourth

Amendment, which had contractually committed defendant to leasing the office space in Suite 800

for five years. Plaintiff notified defendant that it immediately would begin to market Suite 800 to

-3- No. 1-24-2043

mitigate its damages and it ultimately was able to build out and lease Suite 800 to other tenants

and receive a total of $445,729 in rent from them.

¶9 In its amended complaint for breach of contract, plaintiff alleged that after mitigation and

application of the security deposit, defendant still owed it $473,999 in rent and it sought damages

in that amount. Plaintiff also sought an award for its proportionate share of the real estate taxes

and operating expenses, plus the expenses incurred in preparing Suite 800 for the mitigating

tenants.

¶ 10 A bench trial was held on plaintiff’s amended complaint. The evidence at trial established

that plaintiff owns the Building, which is managed by Marc Realty, LLC. Defendant is a

commercial entity headquartered in Chicago which moves freight for customers via multiple

platforms, including railroads, ships, trucks, and airplanes. On December 22, 2010, the parties

executed a lease pursuant to which defendant rented Suite 1210 of the Building. In July 2011 and

February 2014, the lease was amended to allow defendant to rent Suites 1220 and 2010.

¶ 11 Defendant subsequently determined that it needed more space in the Building. In late 2014,

Mark Schiele, defendant’s president, spoke with Anthony Crotty, the asset manager for the

Building, about moving to the seventh and eighth floors and renting Suites 700 and 800. At the

time, the seventh floor needed to be built out to office specifications. The relevant space for Suite

800 was in raw condition, with no interior walls or hallways or offices, and needed to be

completely built out.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catholic Charities of the Archdiocese of Chicago v. Thorpe
741 N.E.2d 651 (Appellate Court of Illinois, 2000)
Southwest Bank of St. Louis v. POULOKEFALOS
931 N.E.2d 285 (Appellate Court of Illinois, 2010)
Academy Chicago Publishers v. Cheever
578 N.E.2d 981 (Illinois Supreme Court, 1991)
Chapman v. Brokaw
588 N.E.2d 462 (Appellate Court of Illinois, 1992)
Intaglio Service Corp. v. J. L. Williams & Co.
420 N.E.2d 634 (Appellate Court of Illinois, 1981)
Steenes v. Mac Property Management, LLC
2014 IL App (1st) 120719 (Appellate Court of Illinois, 2014)
Abbell v. United States
166 F. Supp. 602 (Court of Claims, 1958)
Arbogast v. Chicago Cubs Baseball Club, LLC
2021 IL App (1st) 210526 (Appellate Court of Illinois, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (1st) 242043-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-180-llc-v-traffic-tech-inc-illappct-2025.