In the Missouri Court of Appeals Eastern District DIVISION THREE
MICHAUD MITIGATION, INC. D/B/A ) No. ED108868 PUROCLEAN RESTORATION ) PROFESSIONALS, ) ) Appeal from the Circuit Court Respondent, ) of Jefferson County ) vs. ) ) Honorable Joseph A. Rathert RAY M. BECKETT, ) ) Appellant. ) FILED: April 6, 2021
Introduction
Ray M. Beckett (“Beckett”) appeals from the judgment of the trial court following a
bench trial awarding Michaud Mitigation, Inc. (“Michaud Mitigation”) $51,189.75 in contractual
damages arising out of flooding mitigation work performed by Michaud Mitigation on Beckett’s
property. Beckett raises two points on appeal. In Point One, Beckett argues the trial court erred
in finding a contract existed between himself and Michaud Mitigation because the purported
contract did not contain a price term or a method for determining the price. In Point Two,
Beckett contends the trial court abused its discretion in accepting a software-generated invoice
into evidence because it was not supported by a proper foundation due to the uncertainties in
how the software calculated the charged price. Because the contract executed by Michaud
Mitigation falls within a recognized exception allowing the enforcement of a contract despite the
absence of a price term, we deny Point One. Because the record contains sufficiently detailed evidence as to how the software-generated invoice was created, the trial court did not abuse its
discretion when admitting the invoice into evidence, and we deny Point Two. Accordingly, we
affirm the judgment of the trial court.
Factual and Procedural History
In July 2015, Beckett contacted Michaud Mitigation after his home sustained flood
damage approximately two weeks prior. David Michaud walked the property with Beckett and
surveyed the damage, which he observed to be severe. Specifically, David Michaud observed
that Beckett’s shed had flooded, that the water line stood approximately three-and-a-half feet
high outside of the shed, that the home’s basement had several feet of standing water, that the
carpet was saturated with water, that the moisture content of the drywall was at 100 percent, and
that there was severe mold growth on the home’s main floor’s walls, furniture, and flooring. The
flooding was so severe that David Michaud determined that even the second story of Beckett’s
home was damaged. David Michaud explained to Beckett that he could not know what all
needed to be done until he began working on the project. Beckett signed a service authorization
form permitting Michaud Mitigation to begin remediating the damage to the property.
David Michaud made a sketch of the property and took notes on a daily basis for the
purpose of invoicing Beckett. David Michaud also took extensive photos of the property and the
work performed. Following completion of the work on the property, David Michaud used the
software Xactimate to generate an invoice for Beckett. David Michaud entered the sketch and
the days various pieces of equipment were used into Xactimate. The fees were calculated based
upon this information. Xactimate suggested that Michaud Mitigation charge Beckett $51,189.75
for the work (the “Xactimate Invoice”).
David Michaud filed claims for breach of contract, unjust enrichment, and quantum
meruit against Beckett after Beckett did not pay him the requested $51,189.75. Michaud 2 Mitigation was subsequently substituted as the proper plaintiff. In his answer, Beckett admitted
that he had not paid Michaud Mitigation anything for the work performed. Beckett raised the
defense that there was no valid contract between him and Michaud Mitigation because the
purported contract lacked a required price term.
The case proceeded to a bench trial. David Michaud testified extensively about the
damage done to Beckett’s property and the extensive work required to remediate the damage.
Michaud Mitigation sought to have the Xactimate Invoice entered into evidence. Beckett
objected to a lack of foundation, contending there was no evidence as to “how [Xactimate] runs,
what’s the basis of it, what’s its algorithm look like, or any of the other functions that go into
spitting out this invoice.” The trial court overruled the objection and admitted the Xactimate
Invoice, but expressly noted that it was not necessarily accepting the charges in the Xactimate
Invoice as fair and reasonable. David Michaud testified that he used Xactimate for all of his
customers, that he had used it as long as he had been in the mitigation industry, that its use is
directed by the industry, and that it is a unified billing platform used by both the insurance and
mitigation industries. David Michaud believed that $51,189.75 was a fair and reasonable charge
for the work done. On cross-examination, David Michaud testified that he did not create
Xactimate, understand its code, or understand how it was created.
Beckett testified that he believed $51,189.75 was not a reasonable charge for the work
done. When asked to provide an amount that he believed to be reasonable for services
performed, Beckett offered no evidence.
3 The court found that an enforceable contract existed between the parties and awarded
Michaud Mitigation the $51,189.75 sought under the contract as well as $16,551.90 in attorneys’
fees. Beckett now appeals.1
Points on Appeal
In Point One, Beckett argues the trial court erred in finding a contract between himself
and Michaud Mitigation because the purported contract did not contain a price term or a method
for determining the price. In Point Two, Beckett contends the trial court abused its discretion in
accepting the Xactimate Invoice into evidence because it was not supported by a proper
foundation due to the uncertainties in how the price estimate it contained was calculated.
Discussion
I. Point One—The Contract Was Valid Despite the Absence of a Price Term
Beckett challenges the existence of a valid contract between himself and Michaud
Mitigation because the agreement lacked the required price term and did not fall into the
exceptions allowing for a valid contract despite the absence of a price term.
A. Standard of Review
In court-tried cases, we will affirm the judgment of the trial court “unless there is no
substantial evidence to support it, unless it is against the weight of the evidence, unless it
erroneously declares the law, or unless it erroneously applies the law.” Murphy v. Carron, 536
S.W.2d 30, 32 (Mo. banc 1976); see also Rule 84.13(d)(1).2 Whether an enforceable contract
exists is a question of law that we review de novo. See May v. Williams, 531 S.W.3d 576, 582–
83 (Mo. App. W.D. 2017) (internal citations omitted) (reviewing de novo an appellant’s
1 On March 1, 2021, we took this appeal under submission. Subsequently, Michaud Mitigation moved for leave to file and for attorneys’ fees on appeal. Because our Local Rule 400 requires that such motions for attorneys’ fees be made before the cause is taken under submission, we deny the motions. 2 All Rule references are to Mo. R. Civ. P. (2020).
4 argument that no enforceable contract existed between the parties due to the absence of a price
term).
B. Analysis
Both parties acknowledge the precedent established in Allied Disposal, Inc. v. Bob's
Free access — add to your briefcase to read the full text and ask questions with AI
In the Missouri Court of Appeals Eastern District DIVISION THREE
MICHAUD MITIGATION, INC. D/B/A ) No. ED108868 PUROCLEAN RESTORATION ) PROFESSIONALS, ) ) Appeal from the Circuit Court Respondent, ) of Jefferson County ) vs. ) ) Honorable Joseph A. Rathert RAY M. BECKETT, ) ) Appellant. ) FILED: April 6, 2021
Introduction
Ray M. Beckett (“Beckett”) appeals from the judgment of the trial court following a
bench trial awarding Michaud Mitigation, Inc. (“Michaud Mitigation”) $51,189.75 in contractual
damages arising out of flooding mitigation work performed by Michaud Mitigation on Beckett’s
property. Beckett raises two points on appeal. In Point One, Beckett argues the trial court erred
in finding a contract existed between himself and Michaud Mitigation because the purported
contract did not contain a price term or a method for determining the price. In Point Two,
Beckett contends the trial court abused its discretion in accepting a software-generated invoice
into evidence because it was not supported by a proper foundation due to the uncertainties in
how the software calculated the charged price. Because the contract executed by Michaud
Mitigation falls within a recognized exception allowing the enforcement of a contract despite the
absence of a price term, we deny Point One. Because the record contains sufficiently detailed evidence as to how the software-generated invoice was created, the trial court did not abuse its
discretion when admitting the invoice into evidence, and we deny Point Two. Accordingly, we
affirm the judgment of the trial court.
Factual and Procedural History
In July 2015, Beckett contacted Michaud Mitigation after his home sustained flood
damage approximately two weeks prior. David Michaud walked the property with Beckett and
surveyed the damage, which he observed to be severe. Specifically, David Michaud observed
that Beckett’s shed had flooded, that the water line stood approximately three-and-a-half feet
high outside of the shed, that the home’s basement had several feet of standing water, that the
carpet was saturated with water, that the moisture content of the drywall was at 100 percent, and
that there was severe mold growth on the home’s main floor’s walls, furniture, and flooring. The
flooding was so severe that David Michaud determined that even the second story of Beckett’s
home was damaged. David Michaud explained to Beckett that he could not know what all
needed to be done until he began working on the project. Beckett signed a service authorization
form permitting Michaud Mitigation to begin remediating the damage to the property.
David Michaud made a sketch of the property and took notes on a daily basis for the
purpose of invoicing Beckett. David Michaud also took extensive photos of the property and the
work performed. Following completion of the work on the property, David Michaud used the
software Xactimate to generate an invoice for Beckett. David Michaud entered the sketch and
the days various pieces of equipment were used into Xactimate. The fees were calculated based
upon this information. Xactimate suggested that Michaud Mitigation charge Beckett $51,189.75
for the work (the “Xactimate Invoice”).
David Michaud filed claims for breach of contract, unjust enrichment, and quantum
meruit against Beckett after Beckett did not pay him the requested $51,189.75. Michaud 2 Mitigation was subsequently substituted as the proper plaintiff. In his answer, Beckett admitted
that he had not paid Michaud Mitigation anything for the work performed. Beckett raised the
defense that there was no valid contract between him and Michaud Mitigation because the
purported contract lacked a required price term.
The case proceeded to a bench trial. David Michaud testified extensively about the
damage done to Beckett’s property and the extensive work required to remediate the damage.
Michaud Mitigation sought to have the Xactimate Invoice entered into evidence. Beckett
objected to a lack of foundation, contending there was no evidence as to “how [Xactimate] runs,
what’s the basis of it, what’s its algorithm look like, or any of the other functions that go into
spitting out this invoice.” The trial court overruled the objection and admitted the Xactimate
Invoice, but expressly noted that it was not necessarily accepting the charges in the Xactimate
Invoice as fair and reasonable. David Michaud testified that he used Xactimate for all of his
customers, that he had used it as long as he had been in the mitigation industry, that its use is
directed by the industry, and that it is a unified billing platform used by both the insurance and
mitigation industries. David Michaud believed that $51,189.75 was a fair and reasonable charge
for the work done. On cross-examination, David Michaud testified that he did not create
Xactimate, understand its code, or understand how it was created.
Beckett testified that he believed $51,189.75 was not a reasonable charge for the work
done. When asked to provide an amount that he believed to be reasonable for services
performed, Beckett offered no evidence.
3 The court found that an enforceable contract existed between the parties and awarded
Michaud Mitigation the $51,189.75 sought under the contract as well as $16,551.90 in attorneys’
fees. Beckett now appeals.1
Points on Appeal
In Point One, Beckett argues the trial court erred in finding a contract between himself
and Michaud Mitigation because the purported contract did not contain a price term or a method
for determining the price. In Point Two, Beckett contends the trial court abused its discretion in
accepting the Xactimate Invoice into evidence because it was not supported by a proper
foundation due to the uncertainties in how the price estimate it contained was calculated.
Discussion
I. Point One—The Contract Was Valid Despite the Absence of a Price Term
Beckett challenges the existence of a valid contract between himself and Michaud
Mitigation because the agreement lacked the required price term and did not fall into the
exceptions allowing for a valid contract despite the absence of a price term.
A. Standard of Review
In court-tried cases, we will affirm the judgment of the trial court “unless there is no
substantial evidence to support it, unless it is against the weight of the evidence, unless it
erroneously declares the law, or unless it erroneously applies the law.” Murphy v. Carron, 536
S.W.2d 30, 32 (Mo. banc 1976); see also Rule 84.13(d)(1).2 Whether an enforceable contract
exists is a question of law that we review de novo. See May v. Williams, 531 S.W.3d 576, 582–
83 (Mo. App. W.D. 2017) (internal citations omitted) (reviewing de novo an appellant’s
1 On March 1, 2021, we took this appeal under submission. Subsequently, Michaud Mitigation moved for leave to file and for attorneys’ fees on appeal. Because our Local Rule 400 requires that such motions for attorneys’ fees be made before the cause is taken under submission, we deny the motions. 2 All Rule references are to Mo. R. Civ. P. (2020).
4 argument that no enforceable contract existed between the parties due to the absence of a price
term).
B. Analysis
Both parties acknowledge the precedent established in Allied Disposal, Inc. v. Bob's
Home Serv., Inc., 595 S.W.2d 417 (Mo. App. E.D. 1980). Allied recognized “the general rule
that an agreement must fix a price or provide a method to ascertain the price in order to form an
enforceable contract,” but nevertheless found an enforceable contract existed between the parties
where the parties had agreed upon a price to be determined at a future time. Id. at 419, 421.
Beckett contends that while Allied allowed the parties to create a valid and binding contract even
though they expressly agreed to later determine the price, that exception applies only in a narrow
set of cases, such as exclusive sale and distribution agreements and contracts for the sale of
goods under the Uniform Commercial Code. Conversely, Michaud Mitigation posits that Allied
obviated the strict necessity for price terms in contracts and provided that courts may consider
the particular facts and circumstances at issue in determining whether a contract without a price
term is enforceable. We agree with Michaud Mitigation’s characterization of Allied, and we
hold an enforceable contract existed in the present case. Indeed, holding otherwise would
severely undermine the reasonable and common practice in home repairs where the contractor is
able to calculate the amount owed for the services performed only after sufficient work has been
completed from which the contractor is able to calculate its own expenses from the project.
In Allied, the trial court dismissed all counts in a breach of contract action, apparently
finding no contract existed between the parties because the purported contract did not contain a
price term, but contained a term providing only that “[t]he price . . . shall be mutually agreed
upon[.]” Id. at 418–19. On appeal, we recognized “the general rule that an agreement must fix a
price or provide a method to ascertain the price in order to form an enforceable contract.” Id. at 5 419 (citing Barling v. Horn, 296 S.W.2d 94 (Mo. 1956)). However, we also recognized the
exception that there exists an implied standard of reasonableness when the purported contract has
no price term but has been executed. Id. (internal citation omitted). Additionally, we concluded
that the Missouri legislature had made statutory changes that “reflect[ed] a legislative policy of
the state to obviate the prior doctrine invalidating contracts where the price was left to further
agreement.” Id. at 421 (citing Sections 400.2-204, 400.2-3053). Instructive for our analysis of
this case, we approvingly cited cases finding contracts enforceable despite the absence of a price
term where an appropriate price would be difficult or impossible to determine before
performance of the contract. Id. at 420 (citing United States v. Swift & Co., 270 U.S. 124
(1926); Mantell v. Int'l Plastic Harmonica Corp., 55 A.2d 250 (N.J. 1947)). Ultimately, we
concluded that the absence of a price term, even absent execution by one party, “does not
preclude, in and of itself, the validity of a contract.” Id. at 421. Based on the fact that
“establishing a price in advance . . . was difficult or impossible,” we held that the contract at
issue in Allied was enforceable even without a set price term. Id.
Here, we first note that the contract was fully executed by Michaud Mitigation. We note
also that, on appeal, Beckett does not dispute the reasonableness of the price sought by Michaud
Mitigation. Thus, even if Beckett’s more constrained reading of Allied were correct, we are
persuaded the present case would fall into the preexisting exception implying a reasonable price
where the contract had been executed. See id. at 419. Second, Beckett’s narrower reading of
Allied is incorrect. Nothing in Allied requires an express “agreement to agree[,]” to apply the
exception or that the exception applies only to exclusive sale and distribution contracts or
contracts for the sale of goods under the Uniform Commercial Code. See id. at 419–21. The
3 All Section references are to RSMo (2016).
6 record shows David Michaud told Beckett that he could not determine a price before beginning
to work on his property because of the severity of the damage. With this understanding, Beckett
not only signed the contract at that time but allowed Michaud Mitigation to execute it. Indeed,
Beckett does not suggest that any price could have been accurately determined for the extensive
remediation of his home before Michaud Mitigation began working on his property. Because
establishing a price in advance was impossible in the context of the complex flood mitigation
project, we hold the exception discussed in Allied applies, and that the contract between
Michaud Mitigation and Beckett was enforceable. See id. at 421.
Because the contract between Michaud Mitigation and Beckett was enforceable despite
the absence of a price term, the trial court did not err in finding and enforcing a contract between
them. See id.; Murphy, 536 S.W.2d at 32; May, 531 S.W.3d at 582–83. Point One is denied.
II. Point Two—The Xactimate Invoice Was Supported by a Proper Foundation
In his second point on appeal, Beckett argues the trial court abused its discretion in
admitting the Xactimate Invoice because Michaud Mitigation failed to lay a proper foundation
by explaining how Xactimate calculated the amount to be charged.
“The trial court has discretion to determine whether a sufficient foundation was laid for
the admission of evidence . . . and this Court will not reverse absent a showing the trial court
abused its discretion.” Weltmer v. Signature Health Servs. Inc., 417 S.W.3d 856, 863 (Mo. App.
E.D. 2014) (internal citation omitted). “A decision to admit or exclude evidence constitutes an
abuse of discretion when it is clearly against the logic of the circumstances then before the court
and is so unreasonable and arbitrary that it shocks the sense of justice and indicates a lack of
careful, deliberate consideration.” Kappel v. Prater, 599 S.W.3d 189, 192 (Mo. banc 2020)
7 (internal quotation omitted). Even if we find the trial court abused its discretion, we will not
reverse unless the error materially prejudiced the appellant. Id. (internal citation omitted).
We first note that an allegation that evidence was admitted without a foundation can
mean a number of things in context, such as that the evidence lacked authentication,
identification, logical relevance, or legal relevance. Id. at 192 n.2. As a result, a general
allegation of a lack of foundation is not sufficiently specific to draw a court’s attention as to what
aspect of the foundation is allegedly lacking. Riley v. Headland, 311 S.W.3d 891, 895 (Mo.
App. S.D. 2010) (citing Stewart v. Dir. of Revenue, 702 S.W.2d 472, 476 (Mo. banc 1986))
(additional citation omitted). Here, while we observe that Beckett does not explicitly identify the
exact legal basis for his objection—relevance, authentication, etc.—it is clear from the context of
his arguments and his citation to Section 490.680 that he believes the Xactimate Invoice lacked a
proper foundation because there was not sufficient testimony as to “the mode of its preparation.”
See Section 490.680 (requiring a qualified witness testify to a record’s mode of preparation).
Beckett identifies no authority directly supporting his proposition that evidence lacks a
proper foundation solely because the witness did not create the program that produced the
calculations relied upon and does not understand the underlying coding and algorithms. The
record clearly shows Michaud Mitigation laid a sufficient foundation for submission of the
Xactimate Invoice. David Michaud testified that the Xactimate Invoice was generated by
inputting his own sketches, notes, and equipment usage from the work and that he had used
Xactimate as long as he had been in the industry; the record also contains evidence that
Xactimate’s use is directed by the mitigation industry and that Xactimate is a unified billing
platform used by both the insurance and mitigation industries. See Bray v. Bi-State Dev. Corp.,
949 S.W.2d 93, 99 (Mo. App. E.D. 1997) (rejecting an argument that insufficient foundation was 8 laid as to a software’s validity where the relevant results were generated based on inputs by the
witness and the software was generally used and relied upon in the relevant industries); see also
Huffy Corp. v. Custom Warehouse, Inc., 169 S.W.3d 89, 94 (Mo. App. E.D. 2005) (finding a
spreadsheet that was generated by software satisfied Section 490.680 where the witness had
personal knowledge of the information that was input to generate the spreadsheet). Thus, the
trial court’s ruling that sufficient foundation existed to admit the Xactimate Invoice was not
unreasonable or arbitrary. See Kappel, 599 S.W.3d at 192.
Furthermore, Beckett fails to show the requisite prejudice caused by the admission of the
Xactimate Invoice to reverse the trial court’s ruling, even if we were to find an abuse of
discretion. See id. The trial court clearly explained when it admitted the Xactimate Invoice into
evidence that it was not necessarily finding that the suggested charge based upon the invoice was
fair and reasonable. Rather, the trial court’s determination as the trier of fact would depend on
the weight it accorded the evidence once admitted. Notably, Beckett neither testified as to what
he believed a reasonable payment to Michaud Mitigation would be for the work performed nor
put forward any other evidence to establish what a reasonable payment would be. Conversely,
David Michaud testified that he believed the charge of $51,189.75 was fair and reasonable for
the significant mitigation work completed on Beckett’s flooded home. Ultimately, because the
Xactimate Invoice was not the only basis for determining that $51,189.75 was a reasonable
charge for the services provided by Michaud Mitigation, and because Beckett provided no
evidence supporting an alternate amount, Beckett cannot show that Michaud Mitigation would
have recovered a lesser amount but for the admission of the Xactimate Invoice. See id.
9 The trial court did not abuse its discretion in admitting the Xactimate Invoice because
there was sufficient evidence as to how it was prepared and Beckett was not prejudiced by its
admission. See id.; Section 490.680; Weltmer, 417 S.W.3d at 863. Point Two is denied.
Conclusion
The judgment of the trial court is affirmed.
_______________________________ KURT S. ODENWALD, Judge
Angela T. Quigless, P.J., concurs. James M. Dowd, J., concurs.