Michael W. Barger v. Charles MacHine Works, Inc., a Corporation

658 F.2d 582, 1981 U.S. App. LEXIS 18030
CourtCourt of Appeals for the Eighth Circuit
DecidedSeptember 3, 1981
Docket80-1868
StatusPublished
Cited by8 cases

This text of 658 F.2d 582 (Michael W. Barger v. Charles MacHine Works, Inc., a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael W. Barger v. Charles MacHine Works, Inc., a Corporation, 658 F.2d 582, 1981 U.S. App. LEXIS 18030 (8th Cir. 1981).

Opinion

HENLEY, Circuit Judge.

Michael W. Barger appeals from an adverse judgment of the district court, entered upon a jury verdict in favor of Charles Machine Works, Inc., in a products liability action brought by Barger to recover damages for a leg injury sustained while he was using a combination trenching, backhoe, and cable plow machine 1 (a Ditch *584 Witch) that was designed and manufactured by appellee. We reverse the judgment and remand the case for a new trial.

On July 2, 1976 Barger, a construction foreman with Northwestern Bell Telephone Company, was supervising a crew of four men who were using appellee’s machine to plow telephone cable into ground located along a row of lilac bushes and pine trees with dense branches that overhung the property on which the crew was working. Although only the cable laying equipment on the machine was necessary to complete the work, appellant, who was experienced in working with heavy machinery, directed his crew to unchain and lower the stowed backhoe boom and the outriggers to a height of about eighteen inches above the ground because the boom was too high to allow the machine to proceed through the overhanging branches. In order to prevent the backhoe from being raised or lowered or from swinging to the side, he then instructed Randy Hutchinson, one of his crewmen, to stand on one of the lowered outriggers to lift pine branches over the backhoe controls. After plowing cable into the ground for a short while, the crew took a coffee break. While the crew was on break, appellant stepped around the row of lilac bushes to talk with the owner of the property on which the trees were located. 2 The crew resumed work while Barger talked with the property owner for about five minutes. As he was returning to the work site, he “saw that Randy Hutchison [sic] had stepped with one foot down on the backfill blade, and it looked ... to [him] that the branch he was trying to lift over the controls was becoming entangled in the levers.” Barger immediately “rushed in to try and help him get it over so that he wouldn’t get hurt.” As Barger was reaching for the branch, it hit the backhoe boom control lever, which caused the boom to swing around and crush his leg against the backfill blade.

After the accident, Richard Hemmingsen, construction manager for Northwestern Bell, formed an investigation committee to determine the cause of the accident. The committee’s report noted that “[t]he supervisor and another member of the crew were obviously too close to the machine during the job task.” At trial Hemmingsen testified that Barger and Hutchinson were too close to the machine because they were within a fifteen foot semicircle from the center pivot of the backhoe, which had been designated a danger zone by Northwestern Bell. He indicated that no one would have been injured if Barger and his crewman had remained outside the fifteen foot area. 3 *585 Both Hemmingsen and Barger stated that the fifteen foot radius was the distance of the swing of the extended backhoe arm and noted that this danger zone was originally intended to apply to situations in which someone was in the backhoe operator’s seat working the controls and digging with the backhoe. Barger, however, admitted knowing that regardless whether anyone was in this seat, the backhoe boom would move if the control levers were accidentally hit while the machine’s hydraulic system was activated. Moreover, Hemmingsen testified that the fifteen foot rule also applied when the backhoe had been unchained and the boom had been moved to the uphill side of a bank to counterbalance the machine’s weight while plowing across the bank, even though no one was in the backhoe operator’s seat during this procedure. He stated that this information was included in the instructions given to employees of Northwestern Bell Telephone Company and noted that a safety demonstration covering appellee’s machine was held the day before the accident and was attended by Barger and his crewmembers.

Hemmingsen concluded his report by stating: “[T]he members of the crew and particularly the supervisor were more concerned with getting the job done than they were for their own safety.” This conclusion was based on conversations with Barger’s crewmen, which apparently disclosed that Barger had originally intended to take July 2 off, but decided to complete the cable laying project before the Independence Day weekend. Other evidence tended to bolster Hemmingsen’s conclusion: Barger’s testimony that he told the company’s right-of-way buyer that it was possible to lay cable in the area in question, but he preferred not to do so; Barger’s decision to proceed with the work when he was unsuccessful in contacting the property owner to obtain permission to trim the trees; Hemmingsen’s testimony that although it was the construction foreman’s responsibility to determine how to complete a particular project, he was not required to proceed with the work if a dangerous situation existed; Hemmingsen’s statement that two acceptable alternative' means of laying the cable existed that would not have required the machine to proceed through the overhanging trees; 4 and evidence that the tree branches were tied back with ropes to complete the remaining twenty feet of cable laying work after the accident occurred. 5

Over appellant’s objection, the trial court gave the following instruction on assumption of risk, asserted as an affirmative defense by appellee.

INSTRUCTION NO. 17
The defendant, Charles Machine Works, Incorporated, also contends that the plaintiff, Michael W. Barger, assumed the risk of injury, if any, by using the Ditch Witch equipment in the manner and by placing .. . himself in the position he did under the circumstances then existing. The plaintiff cannot recover if you find that the defendant has established by a preponderance of the evidence each and all of the following propositions:
No. 1. That a dangerous condition existed;
No. 2. That the dangerous condition was obvious or that the plaintiff knew of the dangerous condition; and
No. 3. That plaintiff voluntarily and unreasonably exposed himself to the danger and was injured thereby.
*586 In determining whether plaintiff voluntarily and unreasonably assumed a known risk of injury, you should consider all the facts established by the evidence, including the plaintiff’s age, experience, knowledge and understanding, as well as the obviousness of the alleged defect and the danger it posed.

In addition, the trial court gave the following “rescue” instruction, which appellant requested after his objection to the assumption of risk instruction was overruled. 6

INSTRUCTION NO. 17A
You are instructed that one who sees another in imminent and serious peril, which peril was not caused by the plaintiff’s own actions, cannot be charged with assumption of risk, as set out in Instruction No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
658 F.2d 582, 1981 U.S. App. LEXIS 18030, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-w-barger-v-charles-machine-works-inc-a-corporation-ca8-1981.