Michael v. State

187 Misc. 342, 63 N.Y.S.2d 517, 1946 N.Y. Misc. LEXIS 2444
CourtNew York Court of Claims
DecidedJuly 22, 1946
DocketClaim No. 25419
StatusPublished
Cited by4 cases

This text of 187 Misc. 342 (Michael v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael v. State, 187 Misc. 342, 63 N.Y.S.2d 517, 1946 N.Y. Misc. LEXIS 2444 (N.Y. Super. Ct. 1946).

Opinion

Ryan, J.

The claimant herein, Isadore Michael, is the assignee of the claim of Miller Brothers Construction Co., Inc., filed with the clerk of this court on March 24,1939. The assignment bears date February 26, 1943, and the assignee has been substituted as party claimant herein by order duly made and entered.

The Attorney-General, by affidavit and notice of motion, has applied for an order dismissing the claim on the ground that the court is without jurisdiction to hear it because it was not duly filed. Upon the return day of the motion counsel agreed that the proceeding should take the form of a trial of the claim and the "court received documentary proofs on the question of jurisdiction, that issue to be separately tried and determined at this time. The real question for our consideration is: When did the claim of Miller Brothers accrue? If it did not accrue more than six months prior to March 24, 1939, the Attorney-General’s motion must be denied. (Court of Claims Act of 1920, § 15, subd. 4, as added by L. 1936, ch. 775; now § 10, subd. 4, as added by L. 1939, ch. 860.)

Under date of November 20, 1934, Miller Brothers contracted with the State of New York, through its Department of Public Works, Division of Highways, to construct 5.63 miles of highway, including bridges, in, the county of Essex for the agreed price of $273,542.95. The contracting corporation entered upon and proceeded with the work and received seventeen estimates and progress payments, the last one of them, dated November 4, 1935, showing that the work done and materials in place to October 31, 1935, were of the value of $213,149.06 of which the State held in retained percentages the sum of $42,629.81.

[344]*344It is alleged in the claim that the State delayed and interfered with the progress of the work and required the contractor to perform certain extra work for all of which the contractor requested a supplemental agreement. When this was refused, in the spring of 1936, the contractor advised the State that it deemed the contract breached and that it would not return to the site and complete performance. It appears .that Miller Brothers did not in fact resume performance and under date of May 28, 1936, the Commissioner of Highways cancelled the contract. Thereupon, and in accordance with contract terms, the work was readvertised and relet to one Zoli. The final estimate on Zoli’s contract was prepared by the Division of Highways and approved on or about February 23,1937, receipt was signed by Zoli under date of February 25, 1937, and the document was transmitted by the Division of Highways to the Comptroller for payment under date of March 26, 1937.

An estimate known as No. 18 and final, which, like estimate No. 17, covered the materials and work in place October 31, 1935, Miller Brothers having done no work thereafter, was also prepared by the Division of Highways. It credits Miller Brothers with having performed work of the value of $221,-516.43, upon which that corporation had been paid $170,519.25, leaving an unpaid balance due it of $50,997.18, a revision upward of the figure appearing in estimate No. 17. Estimate.No. 18 is dated July 31, 1936. A final agreement, bearing the same date, and covering this final estimate, was also prepared by the Division of Highways for signature by Miller -Brothers. Although this, proposed agreement was approved by the State Comptroller under date of October 1,1936, the Attorney-General has conceded on the record that it was never signed by anybody on behalf of Miller Brothers and an officer of that corporation now swears that no final estimate or agreement was ever received by it from the State of New York. His testimony is not disputed.

Upon completion of the work by Zoli the State of New York computed the excess cost thereof at $30,440.63 and charged this against the balance due Miller Brothers which it had retained. There remained the sum of $20,556.55. This sum was later and on May 2, 1940, disbursed by the State Comptroller to various creditors and lienors of Miller Brothers pursuant to a judgment of the. Supreme Court, Westchester County, entered April 8, 1940, in an action brought by the County Trust Company of White Plains for the foreclosure of an assignment of moneys [345]*345due and to become due on the contract made to it by Miller Brothers. This judgment recites that Miller Brothers defaulted and failed to appear upon the trial of the action. We are not informed of the date when the summons and complaint therein were served upon Miller Brothers although it does appear that they were served upon the Attorney-General on or before February 26, 1937, and it may be presumed that service upon Miller Brothers was accomplished at about the same time. However, if the process and pleadings in that action, whenever served upon them, disclosed to Miller Brothers the details of the State’s final estimate upon their contract or otherwise informed them . as to the extent of their damages by its breach, the Attorney-General has failed to bring such facts to the attention of the court to controvert the proofs of the claimant. The only document relating to the action in evidence before us is the certified copy of the judgment.

Thus it appears that although the State of New York knew when its Division of Highways had made its surveys and measurements how much money Miller Brothers had earned, at contract prices, and knew, when Zoli’s contract was finally approved, how much was the excess cost of completion of the work, the officers of the State never accounted to Miller Brothers until the distribution to that corporation’s creditors in 1940. Indeed, although the State Comptroller approved the proposed, but. unexecuted, final agreement on October 1, 1936, it is disclosed by Exhibit 7 that he did not finally audit the account of Miller Brothers, offsetting against the amount due them and deducting from such amount the excess cost of Zoli’s completion contract, until April 25, 1940, after he had received the certified copy of the judgment hereinabove referred to.

In the meantime there were other occurrences. Under date of August 25, 1936, Miller Brothers filed with the Clerk of the Court of Claims a notice of intention to file claim for breach of contract alleging that said claim arose on or about May 4, 1936,” by the State of New York refusing to execute (furnish claimant with) a supplemental contract providing for the performance of and payment for extra work required to be performed by claimant, which extra work was not included within this original contract nor contemplated by the terms of said contract, or to otherwise provide or arrange for payment to claimant for said extra work

No claim was filed within two years after May 4, 1936, but, under date of October 21, 1938, Miller Brothers applied to this court for an order permitting the filing'of its claim in accord[346]*346anee with the provisions of the Court of Claims Act then found in subdivision 5 of section 15 (L. 1920, cli. 922, as added by L. 1936, ch. 775, and"amd. by L. 1937, cli. 515). The attorney and counsel for Miller Brothers who filed the notice of intention and who made the application for permission to file the claim is the same person who now represents this claimant, the assignee of Miller Brothers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fletcher-McCarthy Construction Co. v. State
53 Misc. 2d 62 (New York State Court of Claims, 1967)
L. Rosenman Corp. v. State
51 Misc. 2d 773 (New York State Court of Claims, 1966)
Terry Contracting, Inc. v. State
51 Misc. 2d 545 (New York State Court of Claims, 1966)
Michael v. State
193 Misc. 834 (New York State Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
187 Misc. 342, 63 N.Y.S.2d 517, 1946 N.Y. Misc. LEXIS 2444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-v-state-nyclaimsct-1946.