Michael R. Gianatasio, PE, P.C. v. City of New York

53 Misc. 3d 757, 37 N.Y.S.3d 828
New York Supreme Court·Decided August 26, 2016·Published·Cited by 5 cases

Opinion

OPINION OF THE COURT

Shirley Werner Kornreich, J.

Motion sequence numbers 001 and 002 are consolidated for disposition.

Defendants the City of New York (the City) and the New York City Administration for Children’s Services (ACS) (collectively, the NYC defendants) move, pursuant to CPLR 3211, to dismiss the claims asserted against them in the amended complaint (the AC). (Sequence No. 001.) Defendant Leake & Watts Services, Inc. (LWS) separately moves to dismiss the claims asserted against it in the AC and for sanctions against plaintiff Michael R. Gianatasio, PE, P.C. (MRG). (Sequence No. 002.) MRG opposes both motions and cross-moves for sanctions against LWS. For the reasons that follow, defendants’ motions to dismiss are granted and the cross motions for sanctions are denied.

I. Factual Background and Procedural History

As this is a motion to dismiss, the facts recited are taken from the AC (see Doc No. 33)1 and the documentary evidence submitted by the parties.

This action concerns the NYC defendants’ failure to pay MRG the full amount owed under two construction contracts. The NYC defendants admit nonpayment and have no issue with the quality of MRG’s work. They contend, however, that the contracts are illegal and, therefore, unenforceable. The other defendant in this action, LWS, also seeks dismissal on the ground that the contracts only obligate the NYC defendants, and not LWS, to pay MRG.

[761]*761In March 2012, Governor Cuomo signed what is known as the “Close to Home” legislation, which authorizes the City to house young people who were adjudicated as delinquent by the Family Court to be placed in secure facilities near their homes. (See AC ¶¶ 14-15.) The facilities would be under the auspices of and in buildings owned by ACS. A not-for-profit entity, in this case LWS, would provide the youth services. (Id.)

In November 2014, ACS reached out to and hired MRG to build two of the six facilities. Those two facilities are located at 170 East 210th Street in the Bronx (the Bronx location) and 1125 Carroll Street in Brooklyn (the Brooklyn location) (collectively, the facilities). ACS wanted both facilities to be operational by March 13, 2015. Consequently, in November 2014, ACS asked MRG to begin work immediately even though contracts for the work had not yet been executed. MRG agreed to do so, commencing work at the Bronx location on November 15, 2014 and at the Brooklyn location on December 8, 2014. The parties negotiated the contracts during the next few weeks. The final versions are dated December 3, 2014 (see Doc No. 56 [the Bronx contract]; Doc No. 57 [the Brooklyn contract] [collectively, the contracts])2 and were fully executed on December 23, 2014. (See Doc No. 56 at 6; Doc No. 57 at 8-9.) LWS signed as “Financial Conduit/Service. Provider,” ACS signed as “Managing Agent,” and MRG signed as “General Contractor.” (See id.) The contracts were approved by ACS’s commissioner.3

The contracts provide that “[LWS] shall promptly reimburse, once they receive payment from ACS, MRG all costs incurred in connection with the Services rendered.” (See Doc No. 56 at 4 [emphasis added]; Doc No. 57 at 7.) The contracts also provide that “MRG shall provide standard general liability, workman’s compensation, professional liability and disability insurance naming [LWS] as certificate holder and additional insured.” (See id.)

The total price of the Bronx contract is $4,598,000. (See Doc No. 56 at 5.) The initial deposit was $1,532,667; $1,500,000 [762]*762was due on February 2, 2015; $1,000,000 was due on March 2, 2015; and the final $565,333 was due on April 3, 2015. (See id. at 6.) The total price of the Brooklyn contract is $1,565,120. (See Doc No. 57 at 8.) The initial deposit was $521,000; $521,000 was due on February 2, 2015; $261,560 was due on March 2, 2015; and the final $261,560 was due on March 15, 2015. (See id.)

MRG was partially paid pursuant to the contracts. Under the Bronx contract, MRG 'received the initial deposit of $1,532,667 on December 29, 2014 and $1,500,000 on February 11, 2015, for a total of $3,032,667. MRG was not paid on its third invoice of $1 million, was not paid on a $20,000 purchase order issued by ACS, and was out of pocket $61,000 because MRG had to pay one of its subcontractors a restocking fee due to ACS’s nonpayment. Under the Brooklyn contract, MRG received $521,707 on December 24, 2014 and $521,000 on February 12, 2015, for a total of $1,042,707. MRG was not paid on its third and fourth invoices in the amounts of $261,560 and $260,853, was not paid for $20,000 of work performed under a purchase order issued by ACS, and was not paid for $109,250 of work performed under a change order.

In early March 2015, MRG requested payment of these amounts. On a March 4, 2015 phone call between MRG and ACS, ACS’s deputy commissioner, Mitch Gipson, discussed ACS’s failure to pay and attempts to remedy the nonpayment. In the recorded conversation, he stated, among other things, that “Close to Home . . . is a project that is near and dear to both the governor and the mayor. . . . [E]veryone is becoming very thoughtful and cautious about how we fix a problem which I, unfortunately at the moment, can’t describe to you in detail.” (See Doc No. 83 at 6.) Gipson noted that ACS was discussing the issue directly with “City Hall.” (See id. at 7 [emphasis added].) He stated:

“I want to just say to you that it would be very, very harmful to everybody if .. . MRG or any other contractor or general contractor or CM stopped work. I understand the challenge that you’re in, . . . but there are others that are, I mean, officially, everybody is in this challenge . . . the spigot has been turned off by a directive, and we are now trying to figure out what we have to do to open it. . . So, you know, this is at the highest levels. I don’t know whether the mayor and the governor know [763]*763that we’ve done this, but I suspect it’s possible that they very well may, at some point. At least they will know what we’ve done to fix it.” (See id. at 7-8 [emphasis added].)

In other words, just as when ACS wanted MRG to begin working before entering into a contract, ACS was now asking MRG to continue expediting work despite not being paid. Gipson stressed “the sensitivity [of] this matter, because it goes all the way to the governor’s house” and that “any delay in bringing those young people closer to home will be frowned upon and disappoint people, including the governor.” (See id. at 10 [emphasis added].) Gipson did not know if the mayor was involved, but stated that “I know [the] deputy mayors are involved in this.” (See id. at 14.)

On March 11, 2015, Gipson again spoke with MRG. He stated in the recorded conversation:

“So just so you understand a little bit, I’ll have to go back a little bit in time to when we approached you in the first place. We were at a point where we realized that we could not do this work with our internal staff. And so we needed, and we weren’t sure of the scope and time, the time and cost of the work had apparently surprised us. And that was an initial frustration of mine, back in November or December.

Free access — add to your briefcase to read the full text and ask questions with AI

Michael R. Gianatasio, PE, P.C. v. City of New York, 53 Misc. 3d 757, 37 N.Y.S.3d 828 (N.Y. Super. Ct. 2016).

53 Misc. 3d 757 (Michael R. Gianatasio, PE, P.C. v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.